CN-370000-CN229-T20CO1.pdf

PDF 735 KB Posted

Attached to
Master Agreement FL|CN229|dfa41f8fd7aaf35fff759ae62d3eefeb
Contract number
CN229
Issued by
Florida

About this file

This is a Task Assignment Change Order Form from the Florida Department of Environmental Protection (FDEP) for Contract CN229. The document authorizes additional consulting services for WGI, Inc., a civil engineering firm based in West Palm Beach, Florida. The change order covers unforeseen subsurface utility exploration services required for the Florida Keys Overseas Heritage Trail Connect project, specifically the Geiger Trail to Big Coppitt segment located in the Florida Keys.

The change order adds $14,723.00 to the existing task assignment for subsurface utility engineering (SUE) services consisting of two subtasks: Subtask 5 involves utility designation using ASCE 38-22 Quality Level B investigation methods, including ground penetrating radar, survey, and computer-aided design services at a fixed price of $5,994.15 plus $2,579.35 in reimbursable costs (hotel, meals, and mileage); Subtask 5A involves utility test holes using ASCE 38-22 Quality Level A investigation methods (vacuum excavation) limited to two test holes at a fixed price of $4,764.15 plus $1,385.35 in reimbursable costs. Both subtasks have a project schedule duration of 45 calendar days from the execution date. Payment is made upon FDEP approval of deliverables for each subtask. The document was executed with digital signatures from FDEP representatives (Tamika Bass, Garland Sandel, Ralph Perkins, and Bryan Bradner) and consultant representative Brett Oldford on September 9-19, 2024.

View the file

Other files

File Type Posted
CN-370000-CN229-A1.pdf PDF
CN-370000-CN229-CMC1.pdf PDF
CN-370000-CN229-CMC4.pdf PDF
CN-370000-CN229-T10CO3.pdf PDF
CN-370000-CN229-T10CO5.pdf PDF
CN-370000-CN229-T12CO6.pdf PDF
CN-370000-CN229-T15CO1.pdf PDF
CN-370000-CN229-T15CO3.pdf PDF
CN-370000-CN229-T20.pdf PDF
CN-370000-CN229-T22CO1.pdf PDF
CN-370000-CN229-T29.pdf PDF
CN-370000-CN229-T31.pdf PDF
CN-370000-CN229-T9CO1.pdf PDF
CN-370000-CN229-TA8 CO3.pdf PDF
CN-370000-CN229-CMC3.pdf PDF
CN-370000-CN229-CMC5.pdf PDF
CN-370000-CN229-T10CO6.pdf PDF
CN-370000-CN229-T12CO5.pdf PDF
CN-370000-CN229-T15Co4.pdf PDF
CN-370000-CN229-T21.pdf PDF
CN-370000-CN229-T22.pdf PDF
CN-370000-CN229-T24.pdf PDF
CN-370000-CN229-T3.pdf PDF
CN-370000-CN229-T6.pdf PDF
CN-370000-CN229-T7.pdf PDF
CN-370000-CN229-T8CO1.pdf PDF
CN-370000-CN229-TA1 CO1.pdf PDF
CN-370000-CN229-T1.pdf PDF
CN-370000-CN229-T10CO1.pdf PDF
CN-370000-CN229-T10CO2.pdf PDF
CN-370000-CN229-T10CO4.pdf PDF
CN-370000-CN229-T11.pdf PDF
CN-370000-CN229-T12.pdf PDF
CN-370000-CN229-T15CO2.pdf PDF
CN-370000-CN229-T17.pdf PDF
CN-370000-CN229-T17CO1.pdf PDF
CN-370000-CN229-T26.pdf PDF
CN-370000-CN229-T5.pdf PDF
CN-370000-CN229-TA12 CO2.pdf PDF
CN-370000-CN229-CMC2.pdf PDF
CN-370000-CN229-T10.pdf PDF
CN-370000-CN229-T12CO1.pdf PDF
CN-370000-CN229-T12CO3.pdf PDF
CN-370000-CN229-T12CO4.pdf PDF
CN-370000-CN229-T13.pdf PDF
CN-370000-CN229-T15.pdf PDF
CN-370000-CN229-T16.pdf PDF
CN-370000-CN229-T18.pdf PDF
CN-370000-CN229-T2.pdf PDF
CN-370000-CN229-T21 CO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

( ) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN229 20 01 61436C

FKOHT Trail Connect Geiger to Big Coppitt

WGI

Brett Oldford 561.839.1715 brett.oldford@wginc.com

Ralph Perkins or successor 850.245.2460 Ralph.Perkins@FloridaDEP.gov

Add subsurface utility exploration services due to unforeseen conditions for FKOHT Trail Connect – Geiger Trail to Big Coppitt. See proposal dated 6.11.24

$ 6,782.35 $ 105,823.87 $ 112,606.22 $ 6,782.35 $ 105,823.87 $ 112,606.22 $ 3,964.70 $ 10,758.30 $ 14,723.00 $ 10,747.05 $ 116,582.17 $ 127,329.22

01/19/25

01/19/25

01/19/25

01/19/25

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2024.09.09 14:46:44 -04'00'

Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2024.09.09 15:51:16 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2024.09.10 09:00:01 -04'00'

Brett Oldford Brett N Oldford Digitally signed by Brett N Oldford Date: 2024.09.10 13:24:18 -04'00'

Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2024.09.19 11:11:35 -04'00'

61436C 37505000263 080039/23 000286 U3200 131500 AD $ 14,723.00

$ 14,723.00

2035 Vista Parkway, West Palm Beach, FL 33411 t: 561.687.2220 f: 561.687.1110 www.WGInc.com

June 11, 2024

Garland Sandel Project Manager Florida Department of Environmental Protection Bureau of Design and Construction Division of Recreation and Parks 3900 Commonwealth Blvd., MS 520 Tallahassee, FL 32399-3000 Garland.Sandel@FloridaDEP.gov

RE: FDEP Contract Number CN 229, Change Order 1 for Task Assignment Number 20 Trail Connect – Geiger Trail to Big Coppitt Unforeseen Additional Services – Subsurface Utility Exploration

Dear Mr. Sandel, WGI, Inc. (WGI) is pleased to provide this additional services proposal to the Florida Department of Environmental Protection (FDEP, CLIENT) for subsurface utility exploration services due to unforeseen conditions on the above referenced project. Tasks being requested by the Department are outlined in the attached Scope of Work, along with corresponding fees. In addition, it is agreed that WGI’s services will be performed pursuant to the contract terms and conditions included in Agreement Number CN229, executed on May 11th, 2016, Amendment Number 1 dated February 4, 2021.

The Florida Keys Overseas Heritage Trail runs along the south side of Overseas Highway heading west from Shark Key and is used for pedestrian traffic. The existing asphalt trail ends at the west end of an existing boat ramp and has a 0.20-mile section that has no asphalt. The missing section of trail has mangroves along the shoulder and a shoulder that slopes towards the water.

The scope of services included in this proposal are for the installation of an asphalt walkway to connect the existing trail from the east adjacent to the existing boat ramp and to the west at Big Coppitt Key for a total trail length of 0.20-miles.

Please let me know if you have any questions regarding the attached information.

Sincerely, WGI, Inc.

Brett Oldford, PE Vice President, Civil Engineering Brettttt OOldldlldldldldllllddddddddddddddldldldldllddddldffffford PPPPPEPP

2035 Vista Parkway, West Palm Beach, FL 33411 t: 561.687.2220 f: 561.687.1110 WGInc.com

Trail Connect – Geiger Trail to Big Coppitt FDEP Contract Number CN 229, Change Order 1 for Task Assignment Number 20

Subtask 5 and 5A: Utility Designating (ASCE 38-22 Quality Level B) and Utility Test holes (ASCE 38-22 Quality Level A) Description: WGI will perform Subsurface Utility Engineering (SUE) of the areas depicted in figure 1 below. A detailed scope of the SUE services is provided below:

Utility Designating (ASCE 38-22 Quality Level B) w/ Survey & CADD

WGI will perform an ASCE 38-22 Quality Level B (QLB) utility investigation (designates) on existing utilities for verification and horizontal alignment confirmation for QLA Investigation within project limits as shown in Exhibit A.

This QLB investigation includes direct induction of toneable subsurface utility facilities from surface accessible features, and Ground Penetrating Radar sweep for non-toneable facilities. Detected facilities will be marked with American Public Works Association (APWA) compliant colors; flags and water based paint on soft ground and washable chalk on hard surfaces.

WGI will perform survey and location of utility designates using network corrected GNSS surveying methods tied to project control – includes offsite NGS control point verification.

Utility Test holes (ASCE 38-22 Quality Level A) w/ Survey

WGI will provide an ASCE 38-22 Quality Level A (QLA) field investigation (vacuum excavation test holes) within the project limits at the proposed locations as directed by EOR, as needed for utility verification, horizontal / vertical confirmation and in support of civil design services and conflict analysis.

WGI will perform survey and location of utility test holes using network corrected GNSS surveying methods tied to project control.

Any additional QLB and/or QLA days exceeding the proposed amount can be added with written CLIENT authorization, while WGI crews are on-site during initial mobilization.

This proposal is based on two (2) test holes requested.

BASIS OF SCOPE

1. WGI proposes to provide an ASCE 38-22 QLB utility investigation (designates) in order to determine the horizontal alignment of the existing utilities within the project limits (Exhibit A).

2. Geophysical designating techniques, although highly reliable, are subject to outside interference, which are beyond the control of WGI, and may impede the effectiveness of subsurface utility investigations. Soil conditions, utility materials, size, depth, salt water and conductivity may prevent the location of some subsurface utilities. WGI utilizes state of the art equipment and methodology during all phases of utility investigations, but no guarantee is hereby expressed that all facilities will be detected.

3. Survey services are included.

4. Horizontal control will be referenced to NAD83/2011 Adjustment and vertical control referenced to NAVD88.

5. Drafting and/or other CADD services are included.

6. CLIENT shall facilitate access for WGI field staff.

7. CLIENT shall provide a list of known utilities and any drawings, as-builts or other source of information that may help in the location of said utilities.

8. Basic work zone safety includes safety road signs and traffic cones.

9. Traffic control, lane closures, if needed are included.

10. Per Diems / Hotels per 2024 GSA rates.

EXCLUSIONS

1. ASCE 38-22 Quality Level A Investigation (test holes) is limited to two (2) test holes.

2. Traffic control conduit investigation is not included.

3. Permits and permit fees, if needed, are not included and are the responsibility of the

CLIENT.

4. Mapping of irrigation lines and sprinkler heads is not included.

5. Invert elevations of storm drainage manholes, culverts, catch basins, and outfalls including pipe sizes and types are not included in the SUE scope.

6. Sanitary sewer (gravity), service laterals and secondary services (private) are excluded.

7. Off duty police not included.

DELIVERABLES

1. WGI will provide a CADD deliverable with the QLB investigations drafted in plan view.

WGI will provide a Utility Report of Subsurface Utility Investigation in PDF format.

LIMITS OF WORK

FIG 1: Geiger Trail to Big Coppitt

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Utility Designating (ASCE 38-22 Quality Level B) w/ Survey & CADD

Total for Subtask 5: $ 5,994.15

Reimbursable Cost: (if applicable – provide for each task in which reimbursables are required) Postage NA Printing NA Overnight Travel (if applicable)

Hotel 2 nights @$329 x 3 people =$1,974.00 Meals 2 days $69.0 x 3 people =$414.00

Mileage (@ $0.445 per mile) 1 trip 430 miles=$191.35 Reimbursable Total Cost $2,579.35

Total for Subtask 5: $8,573.50

Utility Test holes (ASCE 38-22 Quality Level A) w/ Survey

Total for Subtask 5A: $ 4,764. 5

Reimbursable Cost: (if applicable – provide for each task in which reimbursables are required) Postage NA Printing NA Overnight Travel (if applicable)

Hotel 1 nights @$329 x 3 people =$987.00 Meals 1 days $69.0 x 3 people =$207.00

Mileage (@ $0.445 per mile) 1 trip 430 miles=$191.35 Reimbursable Total Cost $1,385.35

Total for Subtask 5A: $6,149. 0

Subtask 5 Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost WGI Sr. Professional Surveyor $204.45 3 $613.35 WGI Professional Surveyor $172.20 4 $688.80 WGI CADD Technician $81.00 12 $972.00 WGI Party Chief $86.01 20 $1,720.20 WGI Instrument Person $55.74 20 $1,114.80 WGI Rod Person $44.25 20 $885.00

Subtask 5A Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost WGI Sr. Professional Surveyor $204.45 3 $613.35 WGI Professional Surveyor $172.20 4 $688.80 WGI CADD Technician $81.00 6 $486.00 WGI Party Chief $86.01 16 $1,376.16 WGI Instrument Person $55.74 16 $891.84 WGI Rod Person $44.25 16 $708.00

Summary of Fees:

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.

Project Schedule:

Activity Duration (Calendar Days) Subtask 5: SUE – QLB 45 (from execution date) Subtask 5A: SUE – QLA 45 (from execution date)

Subtask Subtask Fixed Price Cost Subtask Reimbursable Subtask 5: SUE – QLB $5,994.15 $2,579.35 Subtask 5A: SUE – QLA $4,764. 5 $1,385.35

Total Fixed Price Cost: $10,758. 0 Total Reimbursable Cost: $3,964.70

Overall Total Cost: $14,723. 0

File details come from the government source that posted it. Updated .