This document is a Task Assignment Notification Form and Scope of Work executed under Florida Department of Environmental Protection (FDEP) Contract Number CN229 between the State of Florida and WGI, Inc. The task assignment, designated as Task Assignment Number 17, is managed by the FDEP's Bureau of Design and Construction, Division of Recreation and Parks, with Ralph Perkins serving as the FDEP Contract Manager. The project involves design, permitting, and construction support services for Long Key State Park in Monroe County, Florida, located in the Florida Keys.

The scope of work encompasses seven subtasks with a combined fixed price cost of $92,092.69 and reimbursable costs of $7,526.65, totaling $99,619.34. Subtask 1 involves topographical survey ($15,086.46 fixed plus $2,262.35 reimbursable); Subtask 2 includes geotechnical investigation with borings and soil testing ($6,903.37 fixed plus $605.95 reimbursable); Subtask 3 covers structural assessment and parking layout planning ($18,416.70 fixed plus $178.00 reimbursable); Subtasks 4, 5, and 6 address 90% construction documents ($26,055.90), 100% construction documents ($8,487.84), and bidding assistance ($3,456.72); and Subtask 7 provides environmental permitting services including wetland delineation and coordination with regulatory agencies ($13,685.70 fixed plus $4,302.35 reimbursable). The work schedule spans from May 23, 2023 to January 19, 2025, with payment contingent upon FDEP approval of deliverables for each subtask. The project focuses on designing and permitting the reconstruction of a 450-foot wooden boardwalk damaged by Hurricane Irma and expanding parking facilities at the state park.

View the file

Other files

File Type Posted
CN-370000-CN229-CMC3.pdf PDF
CN-370000-CN229-CMC5.pdf PDF
CN-370000-CN229-T10CO6.pdf PDF
CN-370000-CN229-T12CO5.pdf PDF
CN-370000-CN229-T15Co4.pdf PDF
CN-370000-CN229-T21.pdf PDF
CN-370000-CN229-T22.pdf PDF
CN-370000-CN229-T24.pdf PDF
CN-370000-CN229-T3.pdf PDF
CN-370000-CN229-T6.pdf PDF
CN-370000-CN229-T7.pdf PDF
CN-370000-CN229-T8CO1.pdf PDF
CN-370000-CN229-TA1 CO1.pdf PDF
CN-370000-CN229-A1.pdf PDF
CN-370000-CN229-CMC1.pdf PDF
CN-370000-CN229-CMC4.pdf PDF
CN-370000-CN229-T10CO3.pdf PDF
CN-370000-CN229-T10CO5.pdf PDF
CN-370000-CN229-T12CO6.pdf PDF
CN-370000-CN229-T15CO1.pdf PDF
CN-370000-CN229-T15CO3.pdf PDF
CN-370000-CN229-T20.pdf PDF
CN-370000-CN229-T22CO1.pdf PDF
CN-370000-CN229-T29.pdf PDF
CN-370000-CN229-T31.pdf PDF
CN-370000-CN229-T9CO1.pdf PDF
CN-370000-CN229-TA8 CO3.pdf PDF
CN-370000-CN229-T1.pdf PDF
CN-370000-CN229-T10CO1.pdf PDF
CN-370000-CN229-T10CO2.pdf PDF
CN-370000-CN229-T10CO4.pdf PDF
CN-370000-CN229-T11.pdf PDF
CN-370000-CN229-T12.pdf PDF
CN-370000-CN229-T15CO2.pdf PDF
CN-370000-CN229-T17CO1.pdf PDF
CN-370000-CN229-T26.pdf PDF
CN-370000-CN229-T5.pdf PDF
CN-370000-CN229-TA12 CO2.pdf PDF
CN-370000-CN229-CMC2.pdf PDF
CN-370000-CN229-T10.pdf PDF
CN-370000-CN229-T12CO1.pdf PDF
CN-370000-CN229-T12CO3.pdf PDF
CN-370000-CN229-T12CO4.pdf PDF
CN-370000-CN229-T13.pdf PDF
CN-370000-CN229-T15.pdf PDF
CN-370000-CN229-T16.pdf PDF
CN-370000-CN229-T18.pdf PDF
CN-370000-CN229-T2.pdf PDF
CN-370000-CN229-T20CO1.pdf PDF
CN-370000-CN229-T21 CO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN229 17 FDEP-DRP 61447C

Long Key State Park Boardwalk Rehab/ Parking Expansion

WGI

Brett Oldford 561.839.1715 brett.oldford@wginc.com

Ralph Perkins or successor 850.245.2460 Ralph.Perkins@FloridaDEP.gov

Design, Permit and construct boardwalk and parking expansion. See proposal 3.21.23

Garland Sandel or successor

05.23.23 $ 92,092.69 01/19/25 $ 7,526.65

$ 99,619.34

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.05.18 14:05:18 -04'00'

Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2023.05.18 14:46:48 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.05.18 16:29:27 -04'00'

Brett Oldford Brett Oldford Digitally signed by Brett Oldford Date: 2023.05.23 11:06:56 -04'00'

Michael W. Foster Jr., P.E Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2023.05.26 12:47:49 -04'00'

61447C 37505000050 080039/23 000286 134000 U3200 AD $ 99,619.34

$ 99,619.34

2035 Vista Parkway, West Palm Beach, FL 33411 t: 561.687.2220 f: 561.687.1110 WGInc.com

March 21, 2023

Garland Sandel Project Manager Florida Department of Environmental Protection Bureau of Design and Construction Division of Recreation and Parks 3900 Commonwealth Blvd., MS 520 Tallahassee, FL 32399-3000 Garland.Sandel@FloridaDEP.gov

Re: FDEP Agreement Number CN 229, Task Assignment Number 17 Long Key State Park Boardwalk Reconstruction and Parking Area Expansion

Dear Sandel, WGI, Inc. (WGI) is pleased to provide this proposal to the Florida Department of Environmental Protection (FDEP, CLIENT) for professional services on the above referenced project. Tasks being requested by the Department are outlined in the attached Scope of Work, along with corresponding fees. In addition, it is agreed that WGI’s services will be performed pursuant to the contract terms and conditions included in Agreement Number CN229, executed on May 11th, 2016.

Long Key State Park includes 965 acres located on Long Key in Monroe County, Florida. The park includes numerous amenities, including recreational opportunities such as kayaking, hiking, birding, picnicking, flats fishing and snorkeling; as well as a full-facility campground located at the southern end of the park. The park suffered significant damage from Hurricane Irma in 2017 and FDEP continues to restore the facilities. Among the facilities that are currently out of service and not open to the public is the 450-foot wooden boardwalk that provides a connection between the northern parking area and restrooms to the beach through a mangrove hammock that was also devastated from the storm surge associated with Hurricane Irma.

The scope of services included in this proposal are the design of a replacement boardwalk as well as the additional of a parking area west (upland) of the park’s access drive.

Please let me know if you have any questions regarding the attached information.

Sincerely, WGI, Inc.

Brett Oldford, PE Vice President, Civil Engineering

Long Key State Park Boardwalk and Parking

Long Key State Park Boardwalk Reconstruction and Parking Area Expansion FDEP Contract Number CN 229, Task Assignment Number 17

Subtask 1: Survey Description: WGI will perform a topographical survey of the areas depicted in figure 1 and figure 2 below. A detailed scope of the topographical survey is provided below:

1. Topographic Survey limits will be roughly as shown Figure 1 through 3 below included in this Scope of Services. Limits will be the approximate high-water line at the time of survey for most of the area and up to the edge of driving Surface of SR 5 when applicable

2. Crews will perform field recovery of horizontal and vertical survey control as required to meet the project objective. Control point pairs will be established at each planned parking area, planned crossover, and the entrance gate. These control points will be rebars with caps set approximately 0.5 feet below surface level in natural ground. If control points are set in asphalt or concrete, those points will be mag nails with washers. Coordinate information for each control point will be included in the survey for use during construction efforts.

3. The topographic survey will cover the area within the survey limits. This will include location of all visible improvements. Information on paved surfaces will include limits of differentiation in pavement materials as well as pavement striping. Care will be taken during survey enhancement to limit foot traffic as much as possible and protect sensitive vegetation.

Sufficient elevations will be obtained to create a Digital Terrain Model (DTM) and generate 1-foot contours.

4. Location of Edge of existing Mangroves within project limits.

5. Location of FDOT RW in the project area.

6. MHW (Mean High Water) will be depicted in the survey if elevation is provided by FDEP

7. Storm Sewer, culverts, and Sanitary Sewer information will include top of structure elevation as well as invert elevation, diameter, and material for each pipe entering and existing surveyed structures. Invert information for cleanouts and grease traps is excluded.

8. Upon completion of the field survey element of the project, we will create a drawing of the project area Civil 3D format, including the DTM together with an electronically signed copy in PDF format.

Survey Qualifications:

1. RULE OF LAW: All field and office efforts in connection with this project will be performed in strict accordance with the applicable provisions of the “Standards of Practice for Land Surveying in the State of Florida,” pursuant to Rule 5J-17, Florida Administrative Code.

2. CONTROL FACTORS: Horizontal control will be referenced the North American Datum of 1983/2011 Adjustment (NAD83/11), State Plane Coordinate System of for the North Zone of Florida. Vertical control will be referenced to the National Geodetic Vertical Datum of 1988

(NAVD88).

3. BOUNDARY SURVEY, CAUTION AND EXCLUSION: This proposal does not include a boundary survey nor road right-of-way resolution.

4. Mean High Water Line Survey, excluded: This project will not include a Mean High-Water Line Survey as defined under Chapter 177 of the Florida Statutes

5. TREES, VEGETATION, AND WETLANDS, EXCLUDED: These features are hereby excluded by reference.

6. SUBSURFACE UTILITIES: No designation of subsurface utilities is included in this proposal.

If utility designation markings happen to be visible at the time of survey, the marks will be located and incorporated into the survey information.

7. WORKING HOURS: Survey personnel will be allowed to work during normal daylight working hours, 7 days per week.

8. ENTRANCE FEES: If park entrance fees are charged, those will be reimbursed in addition to included estimated expenses.

LIMITS OF SURVEY

Figure 1: Boardwalk

Figure 2: Additional Parking

Deliverable:

Deliverable will be a DTM, an AutoCAD, and a signed and sealed plot of the Topographic Survey. One electronic copy to BDC Project Manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Subtask 1 Firm Name Position Classification Hourly

Rate Hours Total Fixed

Price Cost WGI Sr. Professional Surveyor $158.64 17 $2696.88 WGI Professional Surveyor $135.66 23 $3120.18 WGI CADD Technician $77.16 40 $3086.40 WGI Party Chief $75.75 36 $2727.00 WGI Instrument Person $51 36 $1836.00 WGI Rod Person $45 36 $1620.00 Total for Subtask 1: $15,086.46

Reimbursable Cost: (if applicable – provide for each task in which reimbursables are required) Postage NA Printing NA Overnight Travel (if applicable)

Hotel 3 nights x 175.00 x 3 people =$1,575.00 Meals 3 days $65.0 x 3 people =$585

Mileage (@ $0.445 per mile)

1 trip 230 miles=$102.35

Reimbursable Total Cost $2,262.35 Total for Subtask 1: $17,348.81

Subtask 2: Geotechnical Description: This proposal is based on performing the test borings in areas accessible to our standard geotechnical equipment. A detailed scope of the geotechnical investigation is provided below:

1. Mobilize truck mounted drilling equipment.

2. Perform one (1) Standard Penetration Test (SPT) boring to a depth of 10 feet below the existing ground surface in the proposed additional parking area.

3. Perform two (2) SPT borings to a depth of 30 feet along the proposed boardwalk alignment.

4. Measure the encountered groundwater level at the boring locations.

5. Visually classify soil samples obtained and perform soil classification testing on representative samples.

6. Develop soil profiles and boring location plan for the subsurface exploration performed.

7. Perform analyses and provide recommendations for timber piles/posts for the proposed boardwalk and provide recommendations for the proposed pavement section in the additional parking area.

8. Prepare a geotechnical report summarizing the exploration completed and geotechnical recommendations to guide the design and construction of the project.

Deliverable:

Geotechnical report summarizing the exploration completed and geotechnical recommendations. Send pdf copy via email to BDC Project Manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 2 Geotechnical – Field Investigation Firm Name Position Classification Rate Units Total Fixed

Price Cost Tierra Standard Penetration Test

(by Truck Mounted Equip) $12.32 70 LF $862.40

Tierra Grout Seal Boreholes (by Truck Mounted Equip)

$5.03 70 LF

$352.10

Tierra Casing Allowance $8.14 20 LF $162.80 Subtask 2 Geotechnical – Laboratory Testing Tierra Natural Moisture Content $9.58 2 tests $19.16 Tierra Grain-Size Analysis $40.92 3 tests $122.76 Tierra Organic Content Test $44.02 1 test $44.02 Tierra Atterberg Limit Test 124.62 1 test $124.62 Subtask 2 Geotechnical – Engineering and Technical Services Tierra Senior Engineer $178.60 2 $ 357.20 Tierra Senior Project Engineer $146.53 6 $ 879.18 Tierra Engineering Intern $87.67 12 $1,052.04 Tierra Designer $86.81 6 $ 520.86 Tierra Sr Engineering Technician $77.21 16 $1,235.36 Tierra Geotechnical Technician $68.45 16 $1,095.20 Tierra Secretary/Clerical $75.67 1 $ 75.67 Total for Subtask 2 $ 6,903.37

Reimbursable Cost: (if applicable – provide for each task in which reimbursables are required) Postage N/A Printing N/A Overnight Travel (if applicable)

N/A

Mileage (@ $0.445 per mile)

Drill Rig:(1) Round trip / 337 miles at $0.445 = 149.96 Support:(3) Round trip / 341.57 miles at $0.445 = $455.99

Reimbursable Total Cost $605.95 Total for Subtask 2: $ 7,509.32

Subtask 3: Structural Assessment and Parking Layout Plan Description: WGI will perform an on-site assessment of the existing boardwalk at Long Key (approximately 460 lineal feet) structural framing and provide Structural Engineering to include: Site data collection of the existing framing system, and assessment of the structure in accordance with 2020 Florida Building Code (FBC). The FDEP BDC desires the mid length observation platforms to be removed and replaced with a gateway sign. The construction documents will specify an ADD Alternate bid item for composite lumber decking. A parking layout plan will also be developed as part of this subtask.

Subtask 3 will include:

1. Site visit to assess the condition, identify deficiencies and gather the existing sub structure and superstructure framing sizes, spacing and material;

2. Structural Assessment Report with photo documentation, recommendations, and an Opinion of

Probable Construction Cost

Deliverable:

Structural Assessment Report, the Engineer’s Opinion of Probable Construction Costs, Parking Layout Plan, 1 electronic copy (for review only). Send pdf copy via email to BDC Project Manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 3 Structural Assessment and Parking Layout Plan Firm Name Position Classification Hourly

Rate Hours Total Fixed

Price Cost WGI Sr.Project Manager $180.12 35 $6,304.20 WGI Sr. Professional Engineer $118.26 45 $5,321.70 WGI Professional Engineer $115.38 $0.00 WGI Staff/Field Engineer $82.32 45 $3,704.40 WGI CADD Technician $77.16 40 $3,086.40 Total for Subtask 3 $18,416.70

Reimbursable Cost: (if applicable – provide for each task in which reimbursables are required) Postage N/A Printing N/A Overnight Travel (if applicable)

N/A

Mileage (@ $0.445 per mile)

(1) Round trip / 400 miles at $0.445 = $178.00

Reimbursable Total Cost $178.00 Total for Subtask 3: $18,594.70

Subtask 4-6: 90% Construction Documents, 100% Construction Documents, Bid Assistance:

Description: Based on the Assessment Report WGI will create and assemble Construction Documents for the boardwalk. The Construction documents will consist of a combination of photo documentation and typical repair details, improvements and/or removal and replacements. The two (2) ramps at the beginning of the boardwalk have been identified, by the 2021 WEC report to not comply with the American Disabilities Act (ADA) criteria will be removed, redesigned and replaced. It is anticipated that no Cad files exist for this boardwalk, therefore we will supplement the plan view with an aerial photography background. BDC desires the mid length observation platforms to be removed and replaced with a gateway sign. The construction documents will specify an ADD Alternate bid item for composite lumber decking. Construction documents will also be developed for the additional parking area.

Subtask 4 (90% Construction Documents) will include:

1. Development of improvement and repair construction documents

2. Structural Assessment Report with photo documentation, recommendations and an Opinion of

Probable Construction Cost

Deliverable:

Construction Documents, the Engineer’s Opinion of Probable Construction Costs, 1 electronic copy (for review only). Send pdf copy via email to BDC Project Manager.

Fixed Price Cost:

Subtask 4 90% Construction Documents Firm Name Position Classification Hourly

Rate

WGI Sr.Project Manager $180.12 40 $7,204.80 WGI Sr. Professional Engineer $118.26 55 $6,504.30 WGI Professional Engineer $115.38 $0.00 WGI Staff/Field Engineer $82.32 75 $6,174.00 WGI CADD Technician $77.16 80 $6,172.80 Total for Subtask 4 $26,055.90

Reimbursable Cost: (if applicable – provide for each task in which reimbursables are required) Postage N/A Printing N/A Overnight Travel (if applicable)

N/A

Mileage (@ $0.445 per mile)

(1) Round trip / 400 miles at $0.445 = $178.00

Reimbursable Total Cost $178.00 Total for Subtask 4: $26,233.90

Subtask 5 (100% Construction Documents) will include:

1. Incorporation of FDEP BDC 90% Comments

2. Final development of improvement and repair construction documents

3. 100% Construction Documents with photo documentation, recommendations, and an Opinion of

Probable Construction Cost

Deliverable:

100% Construction Drawings, the Engineer’s Opinion of Probable Construction Costs, 1 electronic copy (for review only). Send pdf copy via email to BDC Project Manager.

Fixed Price Cost:

Subtask 5 100% Construction Documents

WGI Sr. Project Manager $180.12 12 $2,161.44 WGI Sr. Professional Engineer $118.26 20 $2,365.20 WGI Professional Engineer $115.38 $0.00 WGI Staff/Field Engineer $82.32 20 $1,646.40 WGI CADD Technician $77.16 30 $2,314.80 Total for Subtask 5 $8,487.84

Reimbursable Cost: (if applicable – provide for each task in which reimbursables are required) Postage N/A Printing N/A Overnight Travel (if applicable)

N/A

Mileage (@ $0.445 per mile)

N/A

Reimbursable Total Cost N/A Total for Subtask 5: $8,487.84

Subtask 6 (Bidding Assistance) will include:

1. Assistance during Bidding

2. Responses to Request for Information

Deliverable:

Responses to Request for Information, 1 electronic copy (for review only). Send pdf copy via email to BDC Project Manager.

Fixed Price Cost:

Subtask 6 Bidding Assistance

WGI Sr. Project Manager $180.12 4 $720.48 WGI Sr. Professional Engineer $118.26 12 $1,419.12 WGI Professional Engineer $115.38 $0.00 WGI Staff/Field Engineer $82.32 16 $1,317.12 WGI CADD Technician $77.16 $0.00 Total for Subtask 6 $3,456.72

Reimbursable Cost: (if applicable – provide for each task in which reimbursables are required) Postage N/A Printing N/A Overnight Travel (if applicable)

N/A

Mileage (@ $0.445 per mile)

N/A

Reimbursable Total Cost N/A Total for Subtask 6: $3,456.72

Assumptions:

1. A Dept. of State Cultural Resource Assessment clearance has been or will be secured by the Bureau of Design and Construction (BDC).

2. WGI along with Geotechnical Engineer, and other agents will be provided access to the project site in order to perform services related to this agreement.

3. The Consultant will be providing the Construction Plans, calculations, and geotechnical report to the local municipality/county for their review, however the permit application and other documentation will be provided by the State’s Contractor and submitted separately as may be required.

Exclusions:

The following are Additional Services/Exclusions, not included in the above fee:

1. Services required by governmental agencies which are not specifically described in the Scope of Work.

2. Services required due to changes in regulations made after the date of this proposal.

3. Traffic Engineering/Planning, Environmental/Biological, Electrical Engineering, and

Archeological Services, except as specifically described in the Scope of Work.

Subtask 7: Environmental Services Description: Environmental Field Work and Permitting Services. A detailed scope of the environmental services is provided below:

1. Desktop analysis to compile information on existing natural resources and site conditions, and historical permits;

2. Site visit to gather information on the existing in situ environmental site conditions, habitat types, and general wildlife utilization, and to delineate natural resources, including but not limited to mangrove wetland limits, as required to facilitate environmental permitting in accordance with the Florida Department of Environmental Protection (FDEP) Florida Unified Wetland Delineation Methodology (Chapter 62-340, F.A.C.) and the U.S. Army Corps of Engineers 1987 Wetland Delineation Manual / Atlantic and Gulf Coastal Plain Regional Supplement (Version 2.0, November 2010). The mangrove wetland boundary(ies) will be flagged, using a sub-meter accurate Global Positioning System (GPS) to determine the location of each flag, and overlay the wetland boundary(ies) onto an aerial map and proposed site plan. Mark Mean High water line in the field; instrument survey of the elevation will be conducted under the survey section of the scope of work.

3. Identify required permits;

4. Prepare permit application packages along with the required associated environmental documentation as required by the regulatory agencies to facilitate environmental permitting for the proposed project based on the project scope of work and permit thresholds;

Agency coordination or permitting will be required for the following:

1) Boardwalk:

a. SFWMD/FDEP Exemption Verification;

b. FDEP Mangrove Alteration/Trimming Permit;

c. U.S. Army Corps of Engineers Section 10/404 Nationwide Permit 3;

d. Florida Keys National Marine Sanctuary (FKNMS) Letter of Authorization;

e. Monroe County Planning and Environmental Resources Department Permit;

2) Parking:

a. FDEP Coastal Construction Control Line (CCCL) permitting (critically eroded beaches, 50-foot setback).

5. Coordination with regulatory permitting consultation agencies (NMFS, FWC/USFWS, DHR

SHPO), as required, to facilitate environmental permitting for the project;

6. Representation and coordination: Attend meetings with CLIENT’s project team and regulatory agencies as required for project coordination, review, and planning. This includes, but is not limited to, field meetings with regulatory agency staff, pre-application and other meetings with environmental agencies, and coordination meetings with CLIENT.

Environmental Notes:

1. Access to the project site shall be granted upon prior notice to WGI and agency staff in order to perform services related to this agreement if restricted, gated, and/or locked;

2. Assumes in-water work (below the mean high water line) will not require a benthic resource survey to document submerged aquatic vegetation and corals within the project footprint to facilitate environmental permitting and this agreement excludes these services;

3. Assumes in-kind boardwalk repairs/replacement within the original footprint;

4. Assumes boardwalk repairs/replacement will not include any new permanent structures within

50-feet of the MHWL and excludes FDEP CCCL permitting (critically eroded beaches, 50-foot setback) services for boardwalk repairs/replacement under this agreement;

5. Assumes compensatory mitigation will not be required to facilitate environmental permitting and excludes mitigation planning services under this agreement;

6. Assumes tree survey and tree permitting coordination (excluding mangroves) are the responsibility of the CLIENT and this agreement excludes these services.

7. Provision of any permit and mitigation fees required by the regulatory agencies are the responsibility of the CLIENT.

Deliverable:

Complete permit application package(s) along with the required associated environmental documentation as required by the regulatory agency(ies) to facilitate environmental permitting for the proposed project. One electronic copy of each application package to the Bureau of Design and Construction (BDC) Project Manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 7 Environmental Services Firm Name Position Classification Hourly

Rate WGI Sr.Project Manager $180.12 15 $2,701.80 WGI Principal Environmental Scientist $135.57 20 $2,711.40 WGI Sr. Environmental Scientist $54.78 25 $1,369.50 WGI CADD/GIS Technician $92.04 75 $6,903.00 Total for Subtask 7 $13,685.70

Reimbursable Cost: (if applicable – provide for each task in which reimbursables are required) SFWMD/FDEP Exemption Verification

$100.00

FDEP Mangrove Alteration/Trimming Permit

$830.00

Monroe County Planning and Environmental Resources Department Permit

$2,660.00

Postage N/A Printing N/A Overnight Travel (if applicable)

Hotel 1 nights x $175.00 x 2 people =$350.00 Meals 2 days $65.0 x 2 people =$260.00

Mileage (@ $0.445 per mile)

1 trip 230 miles=$102.35

Reimbursable Total Cost $4,302.35 Total for Subtask 7: $17,988.05

Project Schedule:

Activity Duration (Calendar Days) Subtask 1: Survey 45 (from execution) Subtask 2: Geotechnical 45 (from execution) Subtask 3: Structural Assessment 30 (post completion of

Subtask 1 & 2) Subtask 4: 90% Construction Documents 30 (post completion of

Subtask 3) Subtask 5: 100% Construction Documents 20 (post completion of

Subtask 4) Subtask 6: Bidding Assistance 30 (post bid advertisement) Subtask 7: Environmental Services 180 (post completion of

Subtask 3)

Summary of Fees:

Subtask Subtask Fixed Price

Cost Subtask Reimbursable

Subtask 1: Survey $15,086.46 $2,262.35 Subtask 2: Geotechnical $6,903.37 $605.95 Subtask 3: Structural Assessment $18,416.70 $178.00 Subtask 4: 90% Construction Documents $26,055.90 $178.00 Subtask 5: 100% Construction Documents $8,487.84 Subtask 6: Bidding Assistance $3,456.72 Subtask 7: Environmental Services $13,685.70 $4,302.35

Total Fixed Price Cost: $92,092.69 Total Reimbursable Cost: $7,526.65

Overall Total Cost: $99,619.34

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.