This is a Change Summary document for a construction project at Bay Pines, dated June 16, 2026, detailing modifications to the IFC (Issued for Construction) set for a PET/CT installation project (Project Number 516-CSI-134). The document is issued by Above Group Inc., located in Melbourne, Florida, and specifies that this bulletin is not a formal change order but rather notification of required modifications that may warrant a Change of Work Proposal if they impact contract time or cost.

The changes encompass specification and drawing modifications, with the primary focus on post-installed anchor compliance requirements. Specification changes include additional quantities for abatement work under section 02 82 13.13. Drawing modifications across multiple sheets (S-001, S-301, and AD101) mandate that all post-installed anchors must be DeWalt brand for Building Automation (BA) compliance in Details 2, 4, and 5, and add general demolition notes to the AD101 sheet. Contractors responding to these changes must provide itemized labor, material, overhead, and profit breakdowns; lump sum pricing will not be accepted. Subcontractor and supplier quotations supporting the prime contractor's proposal must be included. Non-responding contractors waive all rights to claim increased compensation or time extensions resulting from these modifications.

View the file

Other files

File Type Posted
36C24826Q0459 0003.docx DOCX document
Bay Pines PET-CT Room 2025.07.24 - Shielding Report.pdf PDF
S02_36C24826Q0459 0002.docx DOCX document
S05_Site visit Sign in sheet 05262026 .jpg JPG image
516-CSI-144_Submittal_Log.pdf PDF
516-CSI-144_Install New PETCT_100 percent IFC Specs.pdf PDF
516-CSI-134_Bay Pines PET CT_IFC Change Summary.pdf PDF
S05_RFIs Prepare Site PET.xlsx XLSX spreadsheet
516-CSI-144_Submittal_Log.xlsx XLSX spreadsheet
Amendment 0001.pdf PDF
H4247213 - Bay Pines VA Hospital CT Update - ACM LBP Report Revised Final Signed.pdf PDF
516-CSI-134_Bay Pines PET-CT_100 percent IFC Drawings.pdf PDF
H4247213 Bay Pines PET-CT Mold Sampling Final - signed.pdf PDF
S02_RFP Attachment Past Performance Questionnaire 4 pages.pdf PDF
S02_RFP Attachment H4247213-BayPinesVA_CT_Update-ACM_LBP_Report_Revised 41 pages.pdf PDF
S02_RFP Attachment NARA 3 pages Bay Pines 2026.pdf PDF
S02_RFP Attachment 07b-516-CSI-144_New_PET-CT_100percent_IFB_Specs_REV_30MAR2026 945 pages.pdf PDF
S02_RFP Attachment SOW-516-CSI-134_2026-04-02 4 pages.pdf PDF
S02_RFP Attachment H4247213 Bay Pines PET-CT Mold Sampling Final 23 pages.pdf PDF
S02_RFP Attachment Specialized Experience Form 3 pages.pdf PDF
S02_RFP Attachment Divisional Price Breakdown.xlsx XLSX spreadsheet
S02_RFP Attachment WD FL20250222 01022026_Pinellas 10 pages.pdf PDF
S02_RFP Attachment 07a-516-CSI-134_BayPines_PET-CT_100percent_IFB_Drawings_REV31MAR2026 104 pages.pdf PDF
S02_Solicitation 36C24826R0112 FINAL.pdf PDF
S02_RFP Attachment EMR 1 page.pdf PDF
S02_RFP Attachment LOS 2 pages.pdf PDF
S02_RFP Attachment Price Schedule 1 page.pdf PDF
S02_RFP Attachment VA_Submittal_Register 17 pages.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(321) 345-9026 305 East Drive Suite H Melbourne, FL 32904 abovegroup@abovegroupinc.com

Change Summary

6/16/2026 Project Name: Bay Pines Prepare Site for Installation of a New PET/CT Project Number: 516-CSI-134 Addendum/Change Bulletin Designation: 100% ISSUE FOR CONSTRUCTION Subject: Change list for IFC Set

This Bulletin is not a change order. If work described in this Bulletin involves a change in time or contract sum, provide on Change of Work Proposal for each line item, itemizing labor and material, overhead and profit price breakdown in accordance with the Specifications. Also include any time extensions, if required. Lump sum labor and material prices will not be accepted. If sub-contractors’ or suppliers’ prices are included in the prime contractor’s proposal, provide a copy of their quotation. then the non-responding Contractor will be determined to not be affected by the change and any rights for increased compensation or time extensions shall be waived.

Specification Changes:

02 82 13.13 – 1.1.B.1 – additional quantities provided for abatement

Drawing Changes:

S-001 – Post-Installed General Notes 7 & 8 – post-installed anchors to be DeWalt for BA compliance S-301- Detail 2 – Drop-In Anchor – post-installed anchors to be DeWalt for BA compliance S-301 – Detail 4 – Clip Angle & Expansion Bolt – post-installed anchors to be DeWalt for BA compliance S-301 – Detail 5 – Anchor Plate & Expansion Bolt – post-installed anchors to be DeWalt for BA compliance AD101 – General Demolition Notes J – N added.