Change Summary.docx
DOCX document 508 KB Posted
- Solicitation number
- 36C24826Q0459
About this file
This is a Change Summary document for a construction project at Bay Pines, dated June 16, 2026, detailing modifications to the IFC (Issued for Construction) set for a PET/CT installation project (Project Number 516-CSI-134). The document is issued by Above Group Inc., located in Melbourne, Florida, and specifies that this bulletin is not a formal change order but rather notification of required modifications that may warrant a Change of Work Proposal if they impact contract time or cost.
The changes encompass specification and drawing modifications, with the primary focus on post-installed anchor compliance requirements. Specification changes include additional quantities for abatement work under section 02 82 13.13. Drawing modifications across multiple sheets (S-001, S-301, and AD101) mandate that all post-installed anchors must be DeWalt brand for Building Automation (BA) compliance in Details 2, 4, and 5, and add general demolition notes to the AD101 sheet. Contractors responding to these changes must provide itemized labor, material, overhead, and profit breakdowns; lump sum pricing will not be accepted. Subcontractor and supplier quotations supporting the prime contractor's proposal must be included. Non-responding contractors waive all rights to claim increased compensation or time extensions resulting from these modifications.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(321) 345-9026 305 East Drive Suite H Melbourne, FL 32904 abovegroup@abovegroupinc.com
Change Summary
6/16/2026 Project Name: Bay Pines Prepare Site for Installation of a New PET/CT Project Number: 516-CSI-134 Addendum/Change Bulletin Designation: 100% ISSUE FOR CONSTRUCTION Subject: Change list for IFC Set
This Bulletin is not a change order. If work described in this Bulletin involves a change in time or contract sum, provide on Change of Work Proposal for each line item, itemizing labor and material, overhead and profit price breakdown in accordance with the Specifications. Also include any time extensions, if required. Lump sum labor and material prices will not be accepted. If sub-contractors’ or suppliers’ prices are included in the prime contractor’s proposal, provide a copy of their quotation. then the non-responding Contractor will be determined to not be affected by the change and any rights for increased compensation or time extensions shall be waived.
Specification Changes:
02 82 13.13 – 1.1.B.1 – additional quantities provided for abatement
Drawing Changes:
S-001 – Post-Installed General Notes 7 & 8 – post-installed anchors to be DeWalt for BA compliance S-301- Detail 2 – Drop-In Anchor – post-installed anchors to be DeWalt for BA compliance S-301 – Detail 4 – Clip Angle & Expansion Bolt – post-installed anchors to be DeWalt for BA compliance S-301 – Detail 5 – Anchor Plate & Expansion Bolt – post-installed anchors to be DeWalt for BA compliance AD101 – General Demolition Notes J – N added.