C250192_PS.pdf

PDF 152 KB Posted

Attached to
Enterprise Asset Management Phase 2
Solicitation number
250192
Issued by
Orange County, California

About this file

This is a procurement schedule memorandum from the Orange County Transportation Authority (OCTA) outlining the timeline for the release, selection, and award of RFP 250192 for Enterprise Asset Management (EAM) Phase 2. The RFP solicits proposals from qualified consultants to provide an Enterprise Asset Management System for a two-year term with a project budget of $1,500,000. Key dates include Board approval and RFP release on May 11, 2026; advertisement on May 11 and 18, 2026; a pre-proposal conference scheduled for May 19, 2026 at 1:30 p.m.; a written questions deadline of May 26, 2026; OCTA's response to proposers on June 2, 2026; proposal submission deadline of June 9, 2026 at 2:00 p.m.; and a pre-evaluation meeting on June 9, 2026 at 4:00 p.m. Evaluation Committee proposal reviews are scheduled for June 23, 2026, with interviews on July 1, 2026 from 9:00 a.m. to 3:00 p.m. Best and Final Offers (BAFOs) are due July 9, 2026 as needed, followed by a CAMM staff report review meeting on July 14, 2026, and staff reports to the Project Manager on July 20, 2026, to the CEO on June 27, 2026, and to the Chief Operating Officer on August 3, 2026. Board approval of selection is scheduled for August 24, 2026, with contract execution targeted for October 1, 2026.

The memorandum does not contain specific information regarding pricing terms, set asides, incumbent contractors, funding sources, or other financial details beyond the stated project budget of $1,500,000. The document serves as an internal planning tool to coordinate the procurement process across OCTA departments, with approval and concurrence required from the Senior Project Manager for Information Technology within the Project Management Office.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INTEROFFICE MEMO

Date: April 3, 2026

To: Charyl Larson, Senior Project Manager - Consultant, Information

Technology Project Management Office

From: Gina Torres, Senior Contract Administrator, CAMM

Subject: Procurement Schedule for Release, Selection and Award

RFP 250192 “Enterprise Asset Management (EAM) Phase 2”

Please review the time schedule for release, selection and award for the subject RFP. If you have a problem with any of the dates or timelines let me know as soon as possible.

May 11, 2026 Board Approves Release / Issue RFP

May 11 & 18, 2026 Advertise

May 19, 2026 Pre-proposal Conference (in-person / virtual), 1:30 p.m. – Room 09 (Tentative)

May 26, 2026 Written questions due from proposers

June 2, 2026 OCTA’s response to proposers

June 9, 2026 Offers Submitted 2:00 p.m.

June 9, 2026 Pre-Evaluation Meeting 4:00 p.m.

June 23, 2026 Evaluation Committee Reviews Proposals Send interview notification letters

July 1, 2026 Interviews, 9:00 a.m. – 3:00 p.m. / Staff report to CAMM from Project Manager

July 9, 2026 BAFOs due (as needed)

July 14, 2026 CAMM staff report review meeting (Thursday

Meeting)

July 20, 2026 Staff report with procurement approach to

Project Manager

Procurement Plan and Schedule, RFP 250192

June 27, 2026 Staff report to CEO

August 3, 2026 Staff report to COB

August 20, 2026 Finance and Administration Committee

August 24, 2026 BOD Approves Selection

October 1, 2026 Contract Executed

Project Manager Concurrence:

Charyl Larson, Senior Project Manager - Consultant, Information Technology Date Project Management Office

File details come from the government source that posted it. Updated .