C250192_PP.pdf

PDF 166 KB Posted

Attached to
Enterprise Asset Management Phase 2
Solicitation number
250192
Issued by
Orange County, California

About this file

This is an interoffice memorandum from the Orange County Transportation Authority (OCTA) Finance and Administration department dated May 7, 2026, regarding the procurement plan and schedule for RFP 250192 "Enterprise Asset Management System Phase 2." OCTA is soliciting proposals from qualified consultants to implement the second phase of an Enterprise Asset Management (EAM) system. The procurement will be conducted as a Request for Proposals (RFP) rather than an Invitation for Bids, as the selection requires evaluation criteria beyond price considerations. The contract term is two years, effective September 1, 2026 through August 31, 2028, with no renewal options identified.

The project budget is $1,500,000 for the initial two-year term, funded through Local Measure M and Federal CMAQ sources. The contract will be structured as a firm-fixed price agreement based on the detailed Scope of Work provided to proposers. The evaluation criteria assign 25 percent weight to firm qualifications, 20 percent to staffing and project organization, 30 percent to the work plan and approach to meeting OCTA's asset management requirements, and 25 percent to cost. The procurement plan indicates that retention, prevailing wages, and liquidated damages provisions apply to this contract. The evaluation team comprises five members including the Senior Contract Administrator, Senior Project Manager, Senior Section Manager of Enterprise Computer Solutions and Support, Section Manager for OC Streetcar Operations, and Section Manager for Contract Services Maintenance Oversight. An independent cost estimate has been received, and the project requisition number is R000680.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INTEROFFICE MEMO

Date: May 7, 2026

To: Cheryl Larson, Senior Project Manager - Consultant, Finance and

Administration

From: Gina Torres, Senior Contract Administrator, CAMM

Subject: PROCUREMENT PLAN AND SCHEDULE RFP 250192 “Enterprise Asset Management System”

Please review the procurement plan for the subject RFP and advise your concurrence with the evaluation criteria and contract elements. Include suggested evaluation team members and/or comments.

Procurement Type: RFP IFB

Justification: A Request for Proposals (RFP) was issued as the nature of the requirement demands that evaluation criteria, in addition to price, be used to select a consultant.

Evaluation Criteria:

PROPOSAL WEIGHT

Qualifications of the Firm 25%

Staffing/Project Organization 20%

Work Plan 30%

Cost 25%

Justification: Qualifications of the firm is weighted at 25 percent as the firm must demonstrate it has prior experience providing similar services. Staffing and project organization is weighted at 20 percent to ensure the firm’s staff have the requisite expertise for completing the project of similar size. Work plan is weighted the highest at 30 percent to ensure the firm’s approach and EAM system phase 2 meet OCTA’s asset management requirements. Cost and price are weighted at 25 percent to ensure OCTA receives value for the services provided.

Contract Type: Time & Expense CTO-Based Firm Fixed Price

Justification: The contract type is firm-fixed because the firms are requested to propose fixed prices for the efforts specified in the Scope of Work. The RFP has a specific Scope of Work detailing individual tasks and deliverables;

therefore, a firm-fixed price contract shall be used.

Procurement Plan and Schedule, RFP 250192

Retention: Yes % No N/A

Prevailing Wages: Yes $ No N/A

Liquidated Damages: Yes $ No N/A

P.M. to provide support documentation identifying how the LD amount was established.

Suggested Evaluation Team Members:

5 members are required over $250k

Internal Evaluators:

Gina Torres, Senior Contract Administrator, CAMM Cheryl Larson, Senior Project Manager - Consultant, Information Technology Project Management Office Mike Henry, Senior Section Manager, Enterprise Computer Solution & Support Tamika Wright, Section Manager III, OC Streetcar Operations Fermin Mora, Section Manager III, Contract Services Maintenance Oversight

Contract Term: Two (2)-year Term effective September 1, 2026 through August 31, 2028

Funding Source: Local Measure M Federal (CMAQ)

Dollar Amount: Initial Term $1,500,000 Option Term N/A

Independent Cost Estimate Received: Yes No

Scope of Work Verification Form Received: Yes No

Requisition Received: Yes R000680 No

DBE Goal: Yes No

Project Manager Concurrence:

Charyl Larson, Senior Project Manager - Consultant, Information Technology Date Project Management Office

CAMM Section/Department Manager Concurrence:

Georgia Martinez, Department Manager, CAMM Date

File details come from the government source that posted it. Updated .