C250192_PP_GMEDITS.docx

DOCX document 48 KB Posted

Attached to
Enterprise Asset Management Phase 2
Solicitation number
250192
Issued by
Orange County, California

About this file

This is an interoffice procurement memo from the Orange County Transportation Authority (OCTA) regarding RFP 250192 for an Enterprise Asset Management System Phase 2 project. The RFP seeks qualified consultants to provide enterprise asset management services, with a contract term of two years effective September 1, 2026 through August 31, 2028. The memo does not specify response dates, due dates, site visits, or bidder's meetings; however, it establishes the evaluation framework and procurement structure for the solicitation.

The contract is structured as a firm-fixed-price engagement with a budget of $1,500,000 for the initial two-year term. Evaluation criteria are weighted as follows: Qualifications of the Firm (25%), Staffing and Project Organization (20%), Work Plan (30%), and Cost (25%), with the Work Plan weighted highest to ensure the proposed EAM system meets OCTA's asset management requirements. The evaluation team consists of five internal OCTA personnel from the Contract Administration and Mortgage Management (CAMM) section and related departments. The funding source is identified as local, with an independent cost estimate and Scope of Work verification form already received. No prevailing wage requirements, liquidated damages, or Disadvantaged Business Enterprise (DBE) goals apply to this contract.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INTEROFFICE MEMO

Procurement Plan and Schedule, RFP 250192

Date: May 6, 2026

To: Cheryl Larson, Senior Project Manager - Consultant, Finance and Administration

From: Gina Torres, Senior Contract Administrator, CAMM

Subject:PROCUREMENT PLAN AND SCHEDULE
RFP 250192 “Enterprise Asset Management System”

Please review the procurement plan for the subject RFP and advise your concurrence with the evaluation criteria and contract elements. Include suggested evaluation team members and/or comments.

Procurement Type: |X| RFP |_| IFB

Justification: A Request for Proposals (RFP) was issued as the nature of the requirement demands that evaluation criteria, in addition to price, be used to select a consultant.

Evaluation Criteria:

PROPOSAL
WEIGHT
Qualifications of the Firm
25%
Staffing/Project Organization
20%
Work Plan
30%
Cost
25%

Justification: Qualifications of the firm is weighted at 25 percent as the firm must demonstrate it has prior experience providing similar services. Staffing and project organization is weighted at 20 percent to ensure the firm’s staff have the requisite expertise for completing the project of similar size. Work plan is weighted the highest at 30 percent to ensure the firm’s approach and EAM system phase 2 meet OCTA’s asset management requirements. Cost and price are weighted at 25 percent to ensure OCTA receives value for the services provided.

Contract Type: |_| Time & Expense |_| CTO-Based |X| Firm Fixed Price

Justification: The contract type is firm-fixed because the firms are requested to propose fixed prices for the efforts specified in the Scope of Work. The RFP has a specific Scope of Work detailing individual tasks and deliverables; therefore, a firm-fixed price contract shall be used.

Retention:
|_| Yes
%
|X| No
|_| N/A
Prevailing Wages:
|_| Yes
$
|_| No
|X| N/A
Liquidated Damages:
|_| Yes
$
|_| No
|X| N/A

P.M. to provide support documentation identifying how the LD amount was established.

Suggested Evaluation Team Members:

5 members are required over $250k

Internal Evaluators:

Gina Torres, Senior Contract Administrator, CAMM Cheryl Larson, Senior Project Manager - Consultant, Information Technology Project Management Office Mike Henry, Senior Section Manager, Enterprise Computer Solution & Support Tamika Wright, Section Manager III, OC Streetcar Operations Fermin Mora, Section Manager III, Contract Services Maintenance Oversight

Contract Term: Two (2)-year Term effective September 1, 2026 through August 31, 2028

Funding Source: |X| Local |_| Measure M |_| Federal (CMAQ)

Dollar Amount: |X| Initial Term $1,500,000 |_| Option Term $ Comment by Georgia Martinez: Add the amounts for the option terms

Independent Cost Estimate Received: |X| Yes |_| No

Scope of Work Verification Form Received: |X| Yes |_| No

Requisition Received: |X| Yes R000680 |_| No

DBE Goal: |_| Yes |X| No

Project Manager Concurrence:

______________________________________________________
Charyl Larson, Senior Project Manager - Consultant, Information TechnologyDate

Project Management Office

CAMM Section/Department Manager Concurrence:

________________________________________________
Pia Veesapen, Department Manager, CAMMDateComment by Georgia Martinez: revise

image1.png

File details come from the government source that posted it. Updated .