This is an interoffice memorandum documenting the procurement plan and schedule for RFP 250192, "Enterprise Asset Management (EAM) Phase 2," issued by the Orange County Transportation Authority (OCTA) in California. The RFP seeks qualified consultants to provide an Enterprise Asset Management System Phase 2 with a two-year contract term. The procurement schedule establishes key milestones beginning with Board approval and RFP release on April 13, 2026, followed by advertisement on April 13 and 20, 2026. A pre-proposal conference is scheduled for April 21, 2026, at 1:30 p.m., with written questions from proposers due by April 28, 2026, and OCTA's responses provided by May 5, 2026. Offers are due on May 12, 2026, at 2:00 p.m., followed by a pre-evaluation meeting at 4:00 p.m. the same day. Proposal evaluation and interviews are scheduled for June 3, 2026, from 9:00 a.m. to 3:00 p.m., with Best and Final Offers (BAFOs) due by June 4, 2026, if needed. Board approval of the selected consultant is anticipated on July 27, 2026, with contract execution targeted for September 1, 2026.
The project budget is $1,500,000 for the two-year contract term. The procurement document establishes a structured review process involving multiple levels of approval, including meetings with the CAMM (Contract Administration and Management), Finance and Administration Committee, and Board of Directors. The schedule incorporates standard procurement phases including staff report submissions to the Project Manager, CAMM staff review, CEO and Chief Operating Officer approvals prior to final board approval. No other salient information regarding pricing terms, set asides, incumbents, or funding sources is provided in this procurement plan document.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INTEROFFICE MEMO
Procurement Plan and Schedule, RFP 250192
Date: March 20, 2026
To: Charyl Larson, Senior Project Manager - Consultant, Information Technology Project Management Office
From: Gina Torres, Senior Contract Administrator, CAMM
Subject: Procurement Schedule for Release, Selection and Award RFP 250192 “Enterprise Asset Management (EAM) Phase 2”
Please review the time schedule for release, selection and award for the subject RFP. If you have a problem with any of the dates or timelines let me know as soon as possible.
| April 13, 2026 |
| Board Approves Release / Issue RFP |
| April 13 & 20, 2026 |
| Advertise |
| April 21, 2026 |
| Pre-proposal Conference (in-person / virtual), 1:30 p.m. – Room 09 (Tentative) |
| April 28, 2026 |
| Written questions due from proposers |
| May 5, 2026 |
| OCTA’s response to proposers |
| May 12, 2026 |
| Offers Submitted 2:00 p.m. |
| May 12, 2026 |
| Pre-Evaluation Meeting 4:00 p.m. |
| May 26, 2026 |
| Evaluation Committee Reviews Proposals |
Send interview notification letters
| June 3, 2026 |
| Interviews, 9:00 a.m. – 3:00 p.m. / |
Staff report to CAMM from Project Manager
| June 4, 2026 |
| BAFOs due (as needed) |
| June 11, 2026 |
| CAMM staff report review meeting (Thursday Meeting) |
| June 15, 2026 |
| Staff report with procurement approach to Project Manager |
| June 25, 2026 |
| Staff report to CEO |
| July 2, 2026 |
| Staff report to COB |
| July 16, 2026 |
| Finance and Administration Committee |
| July 27, 2026 |
| BOD Approves Selection |
| September 1, 2026 |
| Contract Executed |
Project Manager Concurrence:
| ________________________________________ | ______________ |
| Charyl Larson, Senior Project Manager - Consultant, Information Technology | Date |
Project Management Office image1.png
File details come from the government source that posted it. Updated .