Boone_AASF_Lighing_Data.xlsx

XLSX spreadsheet 32 KB Posted

Attached to
Boone AASF Modernize Lighting
Solicitation number
582-RFB-2490-2026
Issued by
Buchanan County, Iowa

About this file

This data file contains a detailed lighting inventory and modernization specifications for the Boone Army Aviation Support Facility (AASF), a 34,185 square-foot complex operated by the Iowa Army National Guard in Boone, Iowa. The spreadsheet documents existing lighting conditions across 34 rooms and exterior areas as of a site visit conducted on January 7, 2026, identifying current fixture types, quantities, and required upgrades. The project scope encompasses the replacement of existing T8, T5, and can light fixtures with LED alternatives, installation of occupancy sensors in 21 rooms, conversion of specific fixtures to 2x2 flat panel LEDs, addition of ceiling-mounted occupancy sensors and dimmer switches, and modernization of exterior wall packs and display lighting. A mandatory pre-bid walkthrough is scheduled for February 12, 2026, at 9:00 AM, with bids due by March 5, 2026, at 2:00 PM CST. The solicitation requires bidders to submit responses as a lump sum amount.

Pricing terms allow the State of Iowa sixty days from invoice submission to process payment in accordance with Iowa Code 8A.514. No specific budget range or award value is disclosed in the available documentation, and no set-aside designations or restrictions limiting participation to disadvantaged enterprises are identified, indicating the procurement is open to qualified bidders. The project is funded through the Iowa Department of Public Defense with no incumbent vendors or current contractors identified. Bidders must meet specified insurance requirements, certify their bids, authorize release of information, and acknowledge federal terms and conditions. The issuing officer is Philip Payton (515-975-6211, philip.payton@dpd.iowa.gov), and the RFB Number is 582-RFB-2490-2026.

View the file

Other files

File Type Posted
L7 ldn6.pdf PDF
L1 blt-2x4.pdf PDF
Footcandles.pdf PDF
Typical Office-Classroom Fixture.pdf PDF
OC1 BCS-WS-CS-DT-300.pdf PDF
L4 clx-strip-light-spec-sheet.pdf PDF
SOW BooneAASF_ReLighting.docx DOCX document
1370207-event.pdf PDF
R2-3_LED Linear Recessed.pdf PDF
L5 - AVX_led.pdf PDF
R1_LED Downlight.pdf PDF
LB1 dl_pgn_spec_WallPack.pdf PDF
F1-2_LED Flat Panel.pdf PDF
19A25-AASF1-001-11x17.pdf PDF
L6 LED_V70269_CS51922.pdf PDF
R4_LED Retrofit.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 Boone Army Aviation Support Facility (AASF) Modernize Lighting Date: 17DEC25/Sit visit 7January 2026

Room TypeRoom#Lighting TypeQuantityNotes
Entry128Can lights2
Lobby/corricdor101B138/101BCan lights27-2x2 T8 / 8-2x4 drop ceiling T8s
Copy room129A1x4 covered T8s3Convert to 2x2 flat panel LED
Office129B1x4 covered T8s4Convert to 2x2 flat panel LED, Need OCS
Office1302x4 T8 3 bulb covered2with OC (validate switch or ceiling)
Office1312x4 T8 3 bulb covered2add OC swiltch
Office1322x4 T8 3 bulb covered3add OC swiltch
Office1342x4 T8 3 bulb covered2add OC swiltch
Office1352x4 T8 3 bulb covered2add OC swiltch
Office1362x4 T8 3 bulb covered4no oc needed
Entry137Can lights1
Garage1391x4 Double T88
Office1532'x4' T8 3 bulb covered6add OC swiltch
Work Room138B
Lockers Male1411.5'x4', 4 bulb drop lights12Occ sensor needed (see photo)
Janitorial1451x4 drop1has oc switch
Female Latrine1472 cans, 2 2x4add occ senser
Male Latrine1443 cans, 2 2x4
w/ 2 wall monutedswitching and occupancy needs reviewed
Breakroom1272x4 T8 3 bulb covered19Need occ added to ceiling
Classroom123This is combined with RM 127
Publications
(Converted to office)1222x4 T8 3 bulb covered6add occ to ceiling
Office1182x4 T8 3 bulb covered4add occ switch
Mechanical1191x4 covered T8s
(combined together)4no occ needed
Mechanical1201x4 covered T8s
(combined together)2-Janadd occ switch
Electrical1211x4 covered T8s
(combined together)2has oc switch
Office1522x4 T8 3 bulb covered4add occ switch
Office1512x4 T8 3 bulb covered4switch covered, change to ceiling occupany
Hanger1012x4 10 bulb T528
Work Room1172x4 T5 with 2 switches8Need occ added to ceiling
Work room117A1x4 covered T8s
(combined together)2add occ switch
FOTS117Badded to RM 117
Latrine1161x4 wall mounted T81see photo
Electrical1131x46Need occ added to ceiling
Battery114explosion proof3no occ needed
Parts Storage1121x4 covered T8s13(1 2x4 light that needs to be replaced like the rest of the lights in the room) add occ in ceiling
Tool storage1001x4 Double T82Light will need to be relocated to accoodate room
Office1111x4 covered T8s4no occ needed
Corridor101D1x42change to 2x2 flat panelled LED add occ to ceiling
Hazmat Storage1091x4 chained and caged8add occ to ceiling (see photo)
Hazmat Storage(outside)107expolsion proof6no occ needed (see photo_
Work Room1061x4 Double T8163 1x4 on wall that need switching added,
Work Room1051x4 Double T816Need occ added to ceiling
Office1041x4 Double T86Need occ added to ceiling
Storage1021x4 Double T86occ switch needed
Vault102ANo accessno change to room
Storage102Bcombined with 102
Storage102Ccombined with 102

Work Room 108 1x4 lights see photo, 47 simplify switching add ceiling occ

Exterior Lighting Armory
Wall Packswall lighting8North and west side of building only
Street Lightscomplete
Flag and Displayscomplete