B08_Section_J_Attachment_13_307127_Rehab_Ft_Yellowstone_Phasing_Plan.pdf
PDF 814 KB Posted
- Attached to
- YELL 307127 - Rehabilitate historic Structures
- Solicitation number
- 140P2024R0177
About this file
This document appears to be a draft construction phasing plan for the rehabilitation of historic structures at Fort Yellowstone. The phasing plan provides details on the sequence of construction activities across multiple buildings and phases, including the use of temporary housing units to accommodate displaced occupants during the renovations.
The key details include the construction phasing from 2025 to 2028, with five main phases affecting different buildings and housing units. The plan identifies the building numbers, number and type of housing units (single, couple, family), and bed counts in each phase. It also designates staging areas and indicates which units will be vacant during construction. This phasing plan is related to the federal contract opportunity YELL 307127 - Rehabilitate Historic Structures, which is being solicited by the Department of the Interior National Park Service.
View the file
Other files
Show all 46
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BARRACKS ST.
STABLE ST.
P O W E R
H O U S E
R D
WASHTU
B ROW
P O W E R H O U S E
B Y P A S S
S T A B L E
S T
G R A N D
LO
O P
R D
OFFICERS ROW
Copyright 2020 Hennebery Eddy Architects, Inc.
YELL 307127 - FORT YELLOWSTONE EXT. REHAB - DRAFT CONSTRUCTION PHASING PLAN | 08/08/24
SCALE OF FEET
0 50 10050
PROJECT
NORTH
08/22/24
OVERALL SITE PLANPHASE
DISPLACED
HOUSING UNIT
TEMPORARY
HOUSING UNIT
4A VACANT
4B VACANT
6A VACANT
6B VACANT
8 VACANT
9A VACANT
9B VACANT
5A 4A 5B 4B 7A 8 7B 6A 7C 9B 7D 9B
10A SHORT 5 BEDS
10B 6B 11A 9A
11B SHORT 5 BEDS
12A 9A 12B 9B 14 8 30 4A 31 4B 32 6A 33 6B 2A 4A 2B 4B 3 6A
83 N/A
SUMMARY TABLE
2A
2B
P O W E R H O U S E
B Y P A S S
2A 2A
2B
2B
4 4
TEMPORARY HOUSING
PHASE 1
LEGEND
PHASES 2A / 2B
PHASE 3
STAGING AREA
PHASE 4
PHASE 5
OFFICERS ROW
Copyright 2020 Hennebery Eddy Architects, Inc.
YELL 307127 - FORT YELLOWSTONE EXT. REHAB - DRAFT CONSTRUCTION PHASING PLAN | 08/08/24
SCALE OF FEET
0 20 4020
PROJECT
NORTH
08/22/24
BARRACKS ST.
PHASE 1
8 - 3FP - 2 BEDS9A - 4SS - 5 BEDS
9B - 4SS - 5 BEDS
6A - 3 FP - 4 BEDS
6B - 4 FP - 4 BEDS
4A - 2CP - 4 BEDS
4B - 2CP - 4 BEDS
4A - 4 BEDS
4B - 4 BEDS
6A - 4 BEDS
6B - 4 BEDS
8 - 2 BEDS
9A - 5 BEDS
9B - 5 BEDS
TEMPORARY HOUSING UNITS
VACANT
VACANT
VACANT
VACANT
VACANT
VACANT
VACANT
TEMPORARY HOUSING
PHASE 1
LEGEND
PHASES 2A / 2B
PHASE 3
SINGLE, SEASONAL
SINGLE, PERMANENT
COUPLE, PERMANENT
FAMILY, PERMANENT
SS
SP
CP
FP
STAGING AREA
OFFICERS ROW
BARRACKS ST.
Copyright 2020 Hennebery Eddy Architects, Inc.
YELL 307127 - FORT YELLOWSTONE EXT. REHAB - DRAFT CONSTRUCTION PHASING PLAN | 08/08/24
SCALE OF FEET
0 20 4020
PROJECT
NORTH
08/22/24
PHASE 2B
PHASES 2A / 2B
PHASE 2A
B A R R A C K S
S T
10A - 5SS - 5 BEDS
10B - 4FP - 5 BEDS
11A - 8FP - 5 BEDS
11B - 5SS - 5 BEDS
OFFICERS ROW
7A - 1SP - 1 BED
7B - 4SS - 4 BEDS
7C - 4SS - 4 BEDS
7D - 2SS - 1 BED
5A - 2CP - 4 BEDS
5B - 2CP - 4 BEDS
5A - 2CP - 4 BEDS
5B - 2CP - 4 BEDS
7A - 1SP - 1 BED
7B - 4SS - 4 BEDS
7C - 4SS - 4 BEDS
7D - 2SS - 1 BED
10A - 5SS - 5 BEDS
10B - 4FP - 5 BEDS
11A - 8FP - 5 BEDS
11B - 5SS - 5 BEDS
4A - 4 BEDS
4B - 4 BEDS
8 - 2 BEDS
6A - 4 BEDS
9B - 4 BEDS
9B - 1 BED
SHORT 5 BEDS
6B - 4 BEDS
9A - 5 BEDS
SHORT 5 BEDS
DISPLACED HOUSING UNITS TEMPORARY HOUSING UNITS
TEMPORARY HOUSING
PHASE 1
LEGEND
PHASES 2A / 2B
PHASE 3
SINGLE, SEASONAL
SINGLE, PERMANENT
COUPLE, PERMANENT
FAMILY, PERMANENT
SS
SP
CP
FP
STAGING AREA
B A R R A C K S
S T
Copyright 2020 Hennebery Eddy Architects, Inc.
YELL 307127 - FORT YELLOWSTONE EXT. REHAB - DRAFT CONSTRUCTION PHASING PLAN | 08/08/24
SCALE OF FEET
0 20 4020
PROJECT
NORTH
08/22/24
PHASES 3 / 4
WASHTUB ROW
30 - 2FP
2 BEDS
31 - 1SP
2 BEDS
32 - 2CP
2 BEDS
33 - 2CP
3 BEDS
12A - 5SS - 5 BEDS
12B - 4SS - 5 BEDS
14 - 1SP - 2 BEDS
30 - 2FP - 2 BEDS
31 - 1SP - 2 BEDS
32 - 2CP - 2 BEDS
33 - 2CP - 3 BEDS
9A - 5 BEDS
9B - 5 BEDS
8 - 2 BEDS
4A - 4 BEDS
4B - 4 BEDS
6A - 4 BEDS
6B - 4 BEDS
DISPLACED HOUSING UNITS TEMPORARY HOUSING UNITS
PHASE 3 PHASE 4
B A R R A C K S
S T
14 - 1SP
2 BEDS
12A - 5SS - 5 BEDS
12B - 4SS - 5 BEDS
TEMPORARY HOUSING
PHASE 1
LEGEND
PHASES 2A / 2B
PHASE 3
SINGLE, SEASONAL
SINGLE, PERMANENT
COUPLE, PERMANENT
FAMILY, PERMANENT
SS
SP
CP
FP
STAGING AREA
OFFICERS ROW
BARRACKS ST.
Copyright 2020 Hennebery Eddy Architects, Inc.
YELL 307127 - FORT YELLOWSTONE EXT. REHAB - DRAFT CONSTRUCTION PHASING PLAN | 08/08/24
SCALE OF FEET
0 20 4020
PROJECT
NORTH
08/22/24
PHASE 5
P O W E R H O U S E
B Y P A S S
NO
DISPLACEMENT
TEMPORARY HOUSING
PHASE 1
LEGEND
PHASES 2A / 2B
PHASE 3
SINGLE, SEASONAL
SINGLE, PERMANENT
COUPLE, PERMANENT
FAMILY, PERMANENT
SS
SP
CP
FP
STAGING AREA
PHASE 4
PHASE 5
OF
FIC
ER
S
RO
W
3 - 2CP - 8 BEDS
2A - 4CP - 6 BEDS
2B - 4FP - 6 BEDS
2A - 2CP - 6 BEDS
2B - 4FP - 6 BEDS
3 - 2CP - 8 BEDS
4A - 4 BEDS
4B - 4 BEDS
6A - 4 BEDS
6B - 4 BEDS (VACANT)
8 - 2 BEDS (VACANT)
9A - 5 BEDS (VACANT)
9B - 5 BEDS (VACANT)
DISPLACED HOUSING UNITS TEMPORARY HOUSING UNITS
| Sheets |
| Overall Site Plan |
| PHASE 1 - BLDGS 4, 6, 8, 9 |
| PHASES 2A & 2B - BLDGS 5, 7, 10-11 |
| PHASES 3 & 4 - BLDGS 12, 14 30-33 |
| PHASE 5 - BLDGS 2-3, 83 |