This document is an amendment to a solicitation for the project "YELL 307127 - Rehabilitate Fort Yellowstone Structures". The key details are:

The amendment provides the latest round of Questions and Answers, updates the self-performance requirement from 60% to 40%, and provides the updated Wage Determination applicable to this requirement. It also clarifies details such as the availability of the Stable Street staging area, the exclusion of work on Building 83, the process for re-pointing exterior foundation walls, and the paint preparation for chimneys. The amendment also revises Specification 01 35 91 to better define the role of the Historic Preservation Treatment Specialist and remove the requirement to salvage metal roof tiles. Additionally, the amendment addresses responsibilities for the NPDES permit, mortar analysis, and archaeological/cultural monitoring. The government anticipates a Notice to Proceed date of 03/03/25.

View the file

Other files

File Type Posted
Sol_140P2024R0177_Amd_0006.pdf PDF
B09_Amend_6_140P2024R0177_0006.pdf PDF
B09-140P2024R0177-Amd_5_0005.pdf PDF
Sol_140P2024R0177_Amd_0005.pdf PDF
Sol_140P2024R0177_Amd_0004.pdf PDF
B09-140P2024R0177-Amd_4_0004.pdf PDF
Sol_140P2024R0177_Amd_0003.pdf PDF
001_YELL_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_06_SEPT_2024_REV_01_Part3_0002.pdf PDF
001_YELL_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_06_SEPT_2024_REV_01_Part7_0002.pdf PDF
001_YELL_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_06_SEPT_2024_REV_01_Part2_0002.pdf PDF
Sol_140P2024R0177_Amd_0002.pdf PDF
001_YELL_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_06_SEPT_2024_REV_01_Part1_0002.pdf PDF
001_YELL_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_06_SEPT_2024_REV_01_Part4_0002.pdf PDF
001_YELL_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_06_SEPT_2024_REV_01_Part6_0002.pdf PDF
B09-140P2024R0177-Amd_2_0002.pdf PDF
001_YELL_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_06_SEPT_2024_REV_01_Part5_0002.pdf PDF
B09-140P2024R0177-Amendment_1_0001.pdf PDF
Pre-Proposal_Conference_Sign_In_Sheet_0001.jpg JPG image
YELL_307127_-_Ft_Yell_Preproposal_Conference_2024-09-24_0001.pptx PPTX presentation
Sol_140P2024R0177_Amd_0001.pdf PDF
B08_Section_J_Attachment_1_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_23_AUG_2024_Part5.pdf PDF
B08_Section_J_Attachment_19__Solit_PSP_Vol_I_Past_Performance_Questionnaire.pdf PDF
B08_Section_J_Attachment_1_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_23_AUG_2024_Part3.pdf PDF
B08_Section_J_Attachment_1_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_23_AUG_2024_Part6.pdf PDF
B08_Section_J_Attachment_6_307127_Rehab_Ft_Yellowstone_Closeout_and_O_M_23_AUG_2024.xlsx XLSX spreadsheet
B08_Section_J_Attachment_1_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_23_AUG_2024_Part4.pdf PDF
B08_Section_J_Attachment_16_307127_Rehab_Exteriors_Ft_Yellowstone_CPS_Blank.xlsx XLSX spreadsheet
B08_Section_J_Attachment_2_307127_Rehab_Ft_Yellowstone_CD_Specifications_23_AUG_2024.pdf PDF
Sol_140P2024R0177.pdf PDF
B08_Section_J_Attachment_11_307127_Rehab_Exteriors_Ft_Yellowstone_XRF_analysis_Report.pdf PDF
B08_P2024R0177_YELL_307127_1442_Solit_Clauses_9_24_24.pdf PDF
B08_Section_J_Attachment_18_Letter_of_Comm.pdf PDF
B08_Section_J_Attachment_10_307127_Hazardous_Materials_Report.pdf PDF
B08_Section_J_Attachment_14_Wage_Determination.pdf PDF
B08_Section_J_Attachment_1_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_23_AUG_2024_Part1.pdf PDF
B08_Section_J_Attachment_15_Contract_Admin_Form.pdf PDF
B08_Section_J_Attachment_7_307127_Rehab_Exteriors_Ft_Yellowstone_Condition_Assessment.pdf PDF
B08_Section_J_Attachment_1_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_23_AUG_2024_Part7.pdf PDF
B08_Section_J_Attachment_1_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_23_AUG_2024_Part2.pdf PDF
B08_Section_J_Attachment_12_Rehab_Exteriors_Ft_Yellowstone_Radon_Assessment_Report.pdf PDF
B08_Section_J_Attachment_17_General_References_Form.pdf PDF
B08_Section_J_Attachment_4_YELL_307127_StatementOfStructuralTestsSpecialInspections.pdf PDF
Pages_from_B08_Section_J_Attachment_19__Solit_PSP_Vol_I_Project_Experience_Questionnaire.pdf PDF
B08_Section_J_Attachment_13_307127_Rehab_Ft_Yellowstone_Phasing_Plan.pdf PDF
B08_Section_J_Attachment_9_307127_Rehab_Exteriors_Ft_Yellowstone_Final_Paint_Schemes.pdf PDF
B08_Section_J_Attachment_5_307127_Rehab_Ft_Yellowstone_Submittal_List_23_AUG_2024.xlsx XLSX spreadsheet
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P2024R0177 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PDS

Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div

10/22/20240003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

09/24/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

YELL 307127 - Rehabilitate Ft. Yellowstone Structures

The purpose of this amendment is to provide the following items:

1. To provide the latest round of Questions and Answers received to date.

2. To update the self-performance requirement for Factor 2 from 60% to 40% self-performance.

3. To provide for the updated Wage Determination applicable to this requirement. Wages shall be in conformance with General Decision Number: WY20240013 dated 10/18/2024.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Vicki Freese-supler

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P2024R0177/0003

All other terms and conditions of the solicitation remain unchanged and in full force and effect.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

# Question: Answer Amendment No.:

1 Please clarify whether the Stable Street staging area shown on Sheet 00-G006 is available for the duration of the project.

Sheet 00-G006 is available for the duration of the project. This has been changed in the updated Sheet 00-G006.

2 Please clarify whether Building 83 is included in this project.

Any work associated with Building 83 his hereby deleted from this project. No work is required at Building 83.

3 Please clarify whether re-pointing of the exterior foundation walls is required all the way down to the top of the footings, as is stated on the Exterior Demolition Elevation sheets (Notes 7 and 8), or only as deep as the bottom of the perimeter gravel bed excavations, as is shown on the "perimeter gravel bed at (e) foundation details," like on 06-A801.

Re-point in accordance with "sequence of installation" shown on the detail you referenced.

Ignore the reference to the required depth of re-pointing on the Exterior Demolition Elevation sheets.

4 What structural upgrades are required at the walls and roofs of Buildings 2 and 3, as referenced in the Summary of Work for each of these buildings?

There are no wholesale upgrades required to the walls and roofs of these buildings. Ignore these references in the Summaries of Work and complete the work described in the remainder of the sheets associated with these buildings.

5 Can Site Superintendent function as the safety specialist?

No. No dual-hatting. 2

6 If possible to open the past performance period to at least 10 years

Yes. 2

7 Could we receive clarification regarding the paint preparation on the chimneys prior to repainting? Will they be fully abated and stripped to bare masonry prior to painting, or will they be prepared and encapsulated with new paint?

To clarify, existing paint at brick masonry chimneys will not be fully removed prior to repainting. The existing paint will be prepared and cleaned to receive new paint based on the “Degree of Surface Degradation” as defined in Section 09 03 91, 3.9 Surface-Preparation Schedule. Likely, there will be different surface preparations for different conditions. Contractors should bid on an “average” condition.

8 Spec 01 35 91, para 1.4 mentions that there will be a Historic Preservation Treatment Specialist. It also states that this person’s qualifications will meet 36 CFR Part 61.

However, there are no qualifications listed in 36 CFR Part

61. This CFR references “Procedures of State, Tribal, and Local Government Historic Preservation Programs.”

9 Is it a requirement to salvage metal roof tiles? 2 10 Spec 01 35 23, para 1.4 B calls for a Site Safety

Supervisor. Can this role also be filled by the same person as the Site Superintendent?

No. 2

11 Can one person serve as the SSHO, CQC and Superintendent? If not, please clarify which roles can be combined so that the total number of field managers on site can be determined.

No. 2

12 All around each house, there were numerous borrows seen for chipmunks and other animals. Please clarify who will be responsible for their removal. Once captured, did NPS want them released or handled by an exterminator?

The contractor is not responsible for capturing and disposing of rodents that are encountered during the performance of the site work.

Replace Specification 01 35 91 in the CDs with the 01 35 91 provided with this amendment. The new spec achieves the following:

1. Better defines the role of the Historic Preservation Treatment Specialist, and reduces the time-on-site requirement; and

2. Deletes the requirement to salvage metal roof tiles. They do not need to be salvaged.

13 01 57 23- Temp SWPP. Please clarify who is responsible for the NPDES permit fees.

Per Spec 01 31 00 (1.9)(A)(1), the Contractor is responsible for obtaining permits, which includes the payment of permit fees.

Revised Spec 01 31 00 (1.9)(C)(9) has been changed to read as follows: "Stormwater Pollution Prevention Permit - No permit anticipated, as improvements will occupy less than one acre of area."

An Under-an-Acre Pollution Prevention Plan (UPPP) as described in Spec 01 57 23 is anticipated.

14 What type of historic mortar analysis is required? E.g., Petrographic, X-Ray Diffraction, X-Ray Fluorescence, Scanning Electron Microscopy. How many mortar test samples are required per building? Please identify which parts of building the tests should be taken from? E.g., Chimney, foundation, etc.

Mortar analysis was completed for each building in August 2021. "Custom Mortar Matching Reports" by U.S. Heritage Group are included in Appendix C of the Project Specifications. Mortar mix designs listed in 04 03 00 of the Project Specifications are the same mortar mix designs proposed by U.S. Heritage Group. Attached is the Mortar Sample Log indicating where samples were taken. No additional mortar analysis is required.

15 Will archaeological and Cultural monitors be provided? The Park will be providing the archeological and cultural resources monitors.

16 What is the NTP date for planning purposes? Assume an NTP date of 03/03/25. 2 17 Who is responsible for snow removal in staging areas The contractor is responsible for snow removal within the staging areas.

18 Can the paint removal be done onsite? Location of paint removal is at the discretion of the contractor, however all federal, state and municipal guidelines are applicable, regardless of location.

19 ½” plywood added. Will now be created a 1/2” gap between the window and the trim. (see below sketch) How do we fill the void? We assume that NPS wants to salvage and reuse the existing trim and jamb. Hence, we will need to put in a filler piece. Will that be acceptable

The existing trim and jamb must be salvaged and reused to the greatest extent possible. However, existing sheathing (assumed to be true 1x) will be removed and replaced with 1/2" plywood sheathing and 1/4" furring strips. There is no net gain in sheathing thickness.

20 Spec 07 31-16-3 Field conditions 1.8A states not to install metal shingles when windchill <45degrees? This is unnecessarily restrictive and will limit the ability to have the work done. Can this be change to above 35 degrees ambient. I don’t understand the relevance of wind chill, either, unless the concern is that the workers will be too cold to do a good job.

For all components noted in 1.8.A, Contractor must comply with manufacturer's installation instructions.

21 Please clarify for the areas where we are to apply to paint to existing materials, are we to scrape down to a sound surface, or will we have to remove the existing paint 100% to the bare material.

Refer to 06 03 12 – 3.5 Paint Removal. Remove existing paint to bare substrate.

22 If there is a combination of scraping and full removal, please clarify which areas those would apply.

Refer to 06 03 12 – 3.5 Paint Removal. Remove existing paint to bare substrate.

23 Sheet 02-A901, why does only 4 openings show ‘exterior trim’ with level 1 repair? Why are the other windows shown as N/A? On the elevations, there does not seem to be any difference in these windows.

The exterior trim repair level for 2.N1.04, 2.N1.05, 2.N1.06, and 2.N3.01 should be “N/A.” The reason “N/A” is noted for all exterior trim, is because these windows are set into a stone masonry wall and do not have exterior trim.

24 Will electrical service be available at any of the staging areas shown on Sheet 00-G006?

There is an electric service available at the staging area located due east of Buildings 7 and 8, and northeast of Building 12.

25 Do you want all paint removed, down to bare wood, from all the window/door components regardless of needed repairs? Does paint need to be removed to bare wood only when necessary to perform repairs? Loose paint can be removed, and stable existing paint can be encapsulated.

Refer to Specification Sections 08 03 14 Historic Treatment of Wood Doors, and 08 03 52 Historic Treatment of Wood Windows, and 09 03 91 Historic Treatment of Plain Painting.

26 Will the contractor have to pay for gate entrance fees? No. The park will be providing access passes for all contractor personnel.

27 What is the retainment expectation for siding? See Specification Section 02 41 19 Selective Demolition for table showing assumed amount of salvageable siding.

28 Will wood shingles on building 2 and 3 be removed/ restored? Clarify scope of wood shingle siding throughout.

Wood shingles at Buildings 2 and 3 are to remain and will be repainted. Wood shingles at Buildings 4- 8, 10-12, and 30-33, will be removed and replaced in kind with new shingles. See Specification section 07 31 29-2, 2.1.A. Shingles and Shakes.

29 Is there matching stone available for use in masonry repairs?

Yes, replacement stone is available in the Yellowstone National Park stockpile. See Specification section 04 03 00-6 Historic Treatment For Masonry – 2.3.B.1. Feldspathic Sandstone:

Coordinate with Contracting Officer to obtain replacement material from Yellowstone National Park stockpile.

30 The siding on the dormers on Buildings 30-33 consists of shingles. Is there any scope associated with these shingles?

The intention is to remove the existing shingles and then replace them, per Detail 2 on Sheet 30-A803 (for example).

31 Buildings 30 to 33, Floor Plan Notes 9 and 10 say to salvage stair parts and skirt trim. Is that realistic?

See Specification Section 06 03 12 Historic Wood Repair. Subsection 3.8 Repair Procedures lists three levels of repair that correspond to Keynotes 22, 23 and 24 on the A100 Existing/Demo Exterior Elevation drawing sheets. If the removal of wood components causes damage beyond a Level 2 Repair, then a Level 3 wood repair (replacement in-kind) is acceptable.

32 "Repair spalling" is vague. Please list criteria where spalling needs to be repaired and methods of repair that will be acceptable.

For bidding purposes, spalling stone will be repaired with a masonry unit dutchman. See Specification section 04 03 00 - Historic Treatment of Masonry.

Subsection 3.7.B outlines the repair procedures for a dutchman installation.

33 "Repair stone delamination" is vague. Please list criteria where spalling needs to be repaired and methods of repair that will be acceptable.

For proposal submission purposes, delaminated stone will be repaired with a masonry unit dutchman. See Specification section 04 03 00 - Historic Treatment of Masonry. Subsection 3.7.B outlines the repair procedures for a dutchman installation.

34 Temporary facilities - What size storage container can we place on the site? How many storge containers can we bring on site?

Storage container size limited by extents of staging area.

35 Can we have a storage container on Officer’s Row if we have it blocked visually with temp fencing and screens?

Not prohibited by the contract, but YELL should be consulted. The Park requires at least one lane be provided for vehicle traffic to pass through the area.

36 Where can we place our work trailer? Can one be placed at Officer’s Row? Work trailer = job office?

Work trailer can be placed in area designated as staging location behind the Officer Row housing.

See Sheet 00-G006.

37 Are we permitted to use the public toilets in lieu of bringing in temp toilets?

No. The contractor must provide their own temporary toilet facilities, please reference Construction Specification 01 50 00 (Section 3.2(e).

38 Spec 06 03 12-6, para 3.3 E.1&2 states to remove landscape covering at the end of each work day. Can we use a breathable cover and pull it off only on the weekends.

No. 2

39 Spec 07-31-16-2 , para-1.6 mock ups , states to construct an 8’x8’ roofing mockup. Can that be 4’x4’ on the ground?

No. Mockup must be as denoted in the specification. 2

40 Please clarify that this a lead in construction project, not a lead abatement project.

Lead abatement is the responsibility of the contractor. Refer to 02 83 00 – Lead-Based Paint Stabilization, Component Removal, and Soil Removal. Refer to Appendix B: Hazardous Materials Inspection Report, Tetra Tech, Inc., August 2021.

41 Also do we need to itemize OH&P, PM/Superintendent/Labor rates, etc. on the price schedule?

Not on the price schedule but this information may be included in the narrative portion of the Volume II submission

42 Could spray insulation be used in the roof/ walls, to address concerns about construction time?

Use of spray foam insulation is not permitted unless approved by the Contracting Officer.

43 Are chimneys to be painted? Yes, only if they are currently painted. 2 44 Can we get a two-week extension for receipt of proposals?

The proposal due date is extended to November 4, 2024, at 2:00 p.m. Mountain time.

45 Which lanes do we use to enter the Park? If entering the Park through the Gardiner entrance gates, all contractors shall utilize the two gates reserved for visitors with the name of their company denoted on their truck for identification purposes.

At no time are contractors to utilize the employee-only gate.

46 What are the work hours for the project? Normal workhours are 7:00 a.m. to 6:30 p.m.

Monday through Friday. No noisy work before 8:00 a.m. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the contracting officer.

47 Is signature required on the price schedule? No - signature is required on the SF 1442. 2 48 Do we need to itemize OH&P, PM/Superintendent/Labor rates, etc., on the price schedule?

No - this information should be included in hte narrative portion of Volume II submission.

49 Will all buildings be unoccupied at the start of the project?

No. The park cannot accommodate the displacement of all the residents of the buildings in this project simultaneously. Specification Section 01 11 00 (1.3), as modified by Proposal Amendment 2, identifies the limitations to working on multiple buildings at once, based on the Park’s ability to re-house displaced residents. The selected contractor will provide a project schedule per these limitations that, when reviewed and accepted by the Contracting Officer, will determine when the residents will have to move out to allow for construction. Contractors can assume that on the date their approved schedule says work will begin on a particular building that it will be unoccupied.

50 Please provide a detail for the rafter tail repairs Detail 3/02-A801 does not show any rafter tail repairs.

No wood repair work is anticipated on Building 2 or Building 3 rafter tails.

51 From the water table, how deep is the top of footing? Refer to question 3 and response posted w/solicitation amendment #2 on 08 oct 2024.

52 For bidding purposes, please clarify how much level 1,2 wood repair we should assume for the assumed quantities of clapboard to be restored.

REFER TO 06 03 12 for definition of Level 1/2/3 repair. Refer to Specification Section 02 41 19, 3.6 Wood Siding Salvage Table for estimated percentage of salvageable siding. No further definition or distinction between level of repairs shall be provided.

53 Per Detail 3/A801 What is the material/profile we are using for the soffit on all porches?

No repair/replacement of the underside of existing roof sheathing/boards is anticipated at this location.

54 BLDG #4-33, please confirm that the “Exterior Siding Types” are referring to shiplap siding, not exterior wood siding.

The term wood siding was used as a catch-all since there is more than one type of siding present at the subject buildings. For additional information, see the sheet legend titled “Exterior Siding Types,” on the A300 series exterior elevation sheets. Exterior siding types S-1 thru S-5 is shiplap. Exterior siding type S-6 is a vertical beadboard panel siding.

55 Per detail 3/30-S501 How many openings are required?

Is it for every Chimney? What does it mean “must be installed on different sides of the chimney with a minimum of 1’-0” vertical spacing.” Please provide elevations.

The opening in this detail is intended for installation of a new radon mitigation system through the chimney. At least one (1) opening is required in one

(1) chimney for each building. The note is to ensure that two (2) openings are not created in one wall of the chimney. If two openings are required (i.e. Bldg.

2), then a vertical distance between openings (in separate walls) is required. The intent is to not lose too much brick section in one area of chimney height. For additional information regarding the radon system, see detail 8/30-AA801.

56 Per Building 11 we are adding a (2) new slab on grade to the west porches, Is there any work on the foundation wall? Is there anything in that room? Can the existing slab be cut out and replaced without touching the foundation wall?

The existing foundation at the rear (west) porches of Building 11 is a pier and beam system. The presence of concrete pier bases is unknown. Exterior grade is high at the rear porch of Building 11 and the existing wood floor framing has been observed to be in contact with soil and in poor condition. A new slab on grade foundation will eliminate the issue of wood framing in contact with soil. The porches are used as utility/laundry rooms.

57 In BLDG. 14 drawings there is no details for the screen doors. Should we use the same detail that is in BLDG.

11?

Per Door/Window Note #2 or sheet A901, all existing screen doors are to be restored with new screen material. The level of wood repair is noted on the door schedules. Per Door/Window Note #3 of sheet A901, fabricate and install new screen and storm doors when noted on the door schedule. Only door 7B.101 at Bldg. 7 is to receive a new storm door per detail 10/07-A806.

58 Per sheet 30-A101, are we installing a new concrete foundation ledge or is it existing?

The concrete foundation ledge is existing. 3

59 Please confirm that the intent is to have the haunch slab edge sit on top of the Sono tube concrete footing per detail 3/31-S503.

Confirmed. The structural intent is for the vertical bar in the sonotube to extend into the thickened slab above.

60 Is the contractor only repointing the full interior foundation walls at Building 33? Please confirm there is no pointing needed in building 31, 32. Please show access point to get into the crawl space.

The drawing note on view 1/33-S101 “Repoint all interior stone that is accessible from crawlspace” was added in error. Access to all crawlspaces is noted on Foundation Plans.

61 Why are only selected buildings getting storm doors? See response to Question 57. 3

62 For all buildings with wood porches, is the contractor building new structural framing or are we reinstalling the existing structure framing?

Refer to structural plans for extent of structural framing being retained vs. replaced. For example, sheet 04-S201 notes “(E) Porch joists; Replace damaged joists as needed; Assume 50% replacement.” In some instances, existing roof porches may need to be shored while structural framing members below are being replaced.

63 For buildings #3-33 on sheet A901, if there is a “no” for new storm windows, is the contractor restoring the existing storm window?

Per Door/Window Note #6 on sheet A901, for Buildings 3-33, all existing storm windows will be removed (demolished) and new storm windows will be fabricated and installed. Note #6 should be supplemented with “unless noted “N” on the window schedule “New Storm Window” column.”

The “N” indicates the window will not receive a new storm window.

64 Due to the amount of work requested, and the limited amount of work available in the winter months, we are asking that the contract duration be extended to 1300 calendar days.

The period of performance remains unchanged. 3

65 Please confirm that the only interior foundation wall repointing is where a bolded line is shown and noted.

Correct. See response to question 68. 3

66 The prevailing wages included in the specifications states it is for “Montana”. This project is located in Wyoming.

Please confirm that the prevailing wages in the RFP is correct.

The prevailing wage rate shall be in accordance with General Decision Number: WY20240013 dated 10/18/2024. A copy is attached to this amendment.

67 Please provide the type of insulation that is existing in the perimeter walls of Bldgs 4-33.

The perimeter wall insulation was not visible during site investigations, however, where siding was damaged or missing, exterior wall insulation was observed to be pink fiberglass batt insulation. The same insulation was also observed in select roof/attic cavities.

68 05-S101- please confirm the bolded lines in the basement are areas to be pointed. Otherwise, there are no notes indicating any pointing of the interior foundations.

Correct, bolded lines with the following note are areas to be pointed: “Indicates approximate extent of (E) stone wall to be repointed. Repointing requirements per architectural drawings.” See snippet below for occurrence of bold line and note at Building 5. See Demolition Exterior Elevations for extent of interior foundation pointing.

Keynote #188: Extents of structural repairs to masonry foundation. Use the mortar joint as noted on this sheet. RE: Structural foundation plans for additional information.

Correction to Keynote #188: Extents of structural repairs to masonry foundation. At exterior of wall, use the mortar joint as noted on this sheet. At the interior of wall, use joint Type 2C, Overgrout as shown on detail 6/05-A801. RE: Structural foundation plans for additional information.

Demolition Exterior Elevation Notes #7 and #8:

Repoint exterior of all stone foundation walls from top of footing to… Correction to Demolition Exterior Elevation Notes #7 and #8: Repoint exterior of all stone foundation walls from lowest point of excavation as noted on civil drawings to….

69 Bldg 2,3 : The 2 front porches require a new concrete slab. The only way to do this is to saw cut out the existing slab, while leaving the rest of the porch structure in place. Ie. Piers, retaining walls.

This approach is structurally acceptable. With this approach, the new concrete slab will tie into the existing surrounding concrete foundation elements to remain. This can be accomplished by epoxy doweling slab rebar into the remaining concrete prior to pouring the new slab.

70 Please confirm how we are to 'flip' the stone treads with the porch columns sitting on top? Can we cut the stone treads at the face of the columns so that we do not have to disturb the columns? Can we grind the stone tread to account for the new slope?

The top tread at Building 2 front porches appears to be a separate stone. See photos.

71 30-A501 (typical for Bldg 30-33) Note 150 states to reinstall repaired components. Can you provide the expected level of finish and a chart indicating the % of wood that will need to be restored versus new.

Refer to Demolition Plans and Demolition Elevations for level of repair.

72 Why does Bldg #32,33 have a slab on grade on the rear porch, but Bldg 30,31 do not have such slab? Is that correct?

Building 30 will have a sonotube foundation with wood-framed floor. Buildings 31 thru 33 will have a slab on grade foundation with pressure treated framing members. Exterior grade is high at the rear porches of Buildings 31 thru 33 and the existing wood floor framing has been observed to be in contact with soil and in poor condition. A new slab on grade foundation will eliminate the issue of wood framing in contact with soil.

73 Is there any information available (manufacturer, date of installation, etc.) for the tile roofing?

To be answered in a future amendment. NA

74 Typical for bldg. #4-33, it calls for Level 2 repair of the clapboard siding. We do not believe that attempting a dutchman, splice will be feasible, nor aesthetically acceptable upon completion. We recommend only using epoxy or replacing sections with new clapboard. Please confirm if this is acceptable.

Product substitutions shall be submitted through the submittal approval process denoted in the contract documents after contract award. The proposal submission shall be submitted in accordance with the solicitation requirements.

NA

75 Please confirm if NPS will have a representative on site to make the determination as to where the clapboard is to be repaired and if a level 2 repair will be adequate.

To be answered in a future amendment. NA

76 04-A803 (typical bldg. #4-33) , detail 7,8,9- when we restore the clapboard, what is the maximum number of splice joints over 10’ length, we have to consider, before we can replace the entire board?

To be answered in a future amendment. NA

77 Can we assume that we must span at least 2 wall studs for the minimum length of clapboard to be replaced?

To be answered in a future amendment. NA

78 Storm windows- Does NPS only want the top mounted storm with the push out where it calls it out in the notes of the window schedule (sheet A901)?

- Where it does not call out “provide top hung storm,” are we to only replicate the storm?

- Or, is every DBL Hung needing a new storm getting a top hung storm?

To be answered in a future amendment. NA

79 In Bldg. 32 (and most likely in Bldg. 31-33), there is existing spray foam on the interior of the foundation walls. Should the crawlspace radon barrier be placed over the spray foam?

To be answered in a future amendment. NA

80 In Add#1 , rebid #2, included a chart called “basement and crawlspace stone repointing locations.” Is this chart to be ignored as part of Bid #3?

To be answered in a future amendment. NA

81 Will the Superintendent be permitted to work with their hands while at the job?

No NA

82 For the clapboard that is salvaged and restored, will we have the option to install where needed per elevation?

Or, will it have to be installed exactly in the same location where it was removed?

To be answered in a future amendment. NA

83 Should all of the new clapboard be combined into one location, or installed where the damaged clapboard was replaced?

To be answered in a future amendment. NA

84 Please provide a drawing showing the metal shingle dimensions so that we can get accurate pricing.

To be answered in a future amendment. NA

85 Please confirm Bldg #8 is the only building that gets snow guards.

To be answered in a future amendment. NA

86 Please clarify if we can redistribute the excavated soils for the gravel bed on site around the building for site restoration. This assumes the top lead layer has been properly disposed of.

To be answered in a future amendment. NA

87 Please confirm if the options 1-15 will be taken in order.

Alternatively, will the options be taken in order per the phasing plan? Or, will NPS have the ability to take options in a random sequence.

The options will be exercised in any order that the Government determines appropriate.

Amd. 3

88 Will NPS award option during the course of the contract? Please refer to Solicitation Clause "Special Requirement: Option for Additonal Services - Separately Priced Line Items - The Government may require the delivery of the numbered line items identified in the Schedule as option items at the price stated in the Schedule. The CO may unilaterally exercise the option by written notice to the Contractor within 90-days after contract award.

Performance of added line-item tasks shall be at the price negotiated in the contract Schedule."

Amd. 3

89 When we create our CPM schedule, do we follow the phasing plan or the options schedule?

Please follow the phasing plan identified in the solicitation documents.

Amd. 3

90 Will the site options 11-15, be taken in conjunction with its respective buildings in Options 1-10?

Please see response to Q88. Amd. 3

91 Please confirm that the full NTP will not start until 3/03/25 during mobilization. However, an administrative partial NPT will be issued during award so that we can being submittals.

The full NTP will start on March 3, 2025 provided that the contractor has submitted and the NPS has approved the Division 1 submittals identified in Construction Specification 01 31 00 Section 1.4(d).

An administrative partial NTP will not be issued for the completion of these activities.

Amd. 3

92 Factor 2 experience requests 60% of the cost of contract self-performance by the prime contractor. Can this request be omitted?

The requirement will not be removed; however, the percentage of self-performed work is hereby changed to 40%.

Amd. 3

93 Please provide estimated quantities of the Stone Stockpile referenced in Amendment 2, Q&A 29.

To be answered in a future amendment.

94 Can work proceed if the CO, QCM, or Superintendent is absent as long as 2 "supervisors" are present (ref. 01 35 91-5, 3.2B)?

No - the reference in the specifications is in regards to the work associated with the Historic Preservation Treatment Plan and due to the sensitivity of the work being performed no exception will be granted for this portion of the work.

Amd. 3

95 Media blasting (off-site) in a concealed enclosure with filtered ventilation is the most efficient way to remove such a large quantity of LBP from the large quantity of removed siding and trim. This does not appear to be prohibited in the Specs so please confirm; is this an acceptable method of treatment?

To be answered in a future amendment.

96 Due to the complexity of the scope for the "Options" buildings, can the bid date be extended by a couple of weeks?

The proposal due date remains unchanged. Amd. 3

97 There is no mention of an extension of the Contract Completion terms for the "Options" scopes in the RFP.

Do the Contract Completions terms only apply to the Base Bid scope? Will there be time added to the period of performance based on how many of the options are awarded?

The Period of Performance stated includes the base and all options. No additional contract time will be added in the event the options are exercised.

Amd. 3

98 Please provide the cutoff date for questions. The cutoff date for questions is October 18, 2024 as was denoted in the Power Point Presentation attached as part of Amendment 1.

Amd. 3

99 Are the sidewalks for Buildings 4-9 an option or base bid item? They are noted as "option" in the drawings, see C402-C404.

To be answered in a future amendment.

100 Is there a required finish for roll top steel edger, see Detail 5/C501?

To be answered in a future amendment.

101 Given the limited area for staging& laydown, can the CO's field office located in an alternate location?

No, it shall be placed in the location denoted. Amd. 3

102 Can RFI deadline be extended to 10/25? The Q&A deadline date remains October 18, 2024. Amd. 3

Bid 3 Amendment 3-10-22-24.pdf