YELL_307127_-_Ft_Yell_Preproposal_Conference_2024-09-24_0001.pptx

PPTX presentation 13 MB Posted

Attached to
YELL 307127 - Rehabilitate historic Structures
Solicitation number
140P2024R0177
Issued by

About this file

The document is a PowerPoint presentation for a pre-proposal conference related to the federal contract opportunity "YELL 307127 - Rehabilitate Historic Structures." The solicitation number is 140P2024R0177, and the contracting agency is the Department of the Interior National Park Service National Office.

The presentation provides an overview of the project scope, which involves the rehabilitation of historic structures within Yellowstone National Park. Key details include the submission deadline, estimated award date, and pricing terms. The presentation also covers contractor qualifications, site visit information, and the proposal evaluation criteria. Small business set-asides and specific sustainability requirements are also noted.

View the file

Other files

File Type Posted
Sol_140P2024R0177_Amd_0006.pdf PDF
B09_Amend_6_140P2024R0177_0006.pdf PDF
B09-140P2024R0177-Amd_5_0005.pdf PDF
Sol_140P2024R0177_Amd_0005.pdf PDF
Sol_140P2024R0177_Amd_0004.pdf PDF
B09-140P2024R0177-Amd_4_0004.pdf PDF
B09-140P2024R0177-Amd_3_0003.pdf PDF
Sol_140P2024R0177_Amd_0003.pdf PDF
001_YELL_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_06_SEPT_2024_REV_01_Part3_0002.pdf PDF
001_YELL_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_06_SEPT_2024_REV_01_Part7_0002.pdf PDF
001_YELL_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_06_SEPT_2024_REV_01_Part2_0002.pdf PDF
Sol_140P2024R0177_Amd_0002.pdf PDF
001_YELL_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_06_SEPT_2024_REV_01_Part1_0002.pdf PDF
001_YELL_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_06_SEPT_2024_REV_01_Part4_0002.pdf PDF
001_YELL_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_06_SEPT_2024_REV_01_Part6_0002.pdf PDF
B09-140P2024R0177-Amd_2_0002.pdf PDF
001_YELL_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_06_SEPT_2024_REV_01_Part5_0002.pdf PDF
B09-140P2024R0177-Amendment_1_0001.pdf PDF
Pre-Proposal_Conference_Sign_In_Sheet_0001.jpg JPG image
Sol_140P2024R0177_Amd_0001.pdf PDF
B08_Section_J_Attachment_1_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_23_AUG_2024_Part5.pdf PDF
B08_Section_J_Attachment_19__Solit_PSP_Vol_I_Past_Performance_Questionnaire.pdf PDF
B08_Section_J_Attachment_1_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_23_AUG_2024_Part3.pdf PDF
B08_Section_J_Attachment_1_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_23_AUG_2024_Part6.pdf PDF
B08_Section_J_Attachment_6_307127_Rehab_Ft_Yellowstone_Closeout_and_O_M_23_AUG_2024.xlsx XLSX spreadsheet
B08_Section_J_Attachment_1_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_23_AUG_2024_Part4.pdf PDF
B08_Section_J_Attachment_16_307127_Rehab_Exteriors_Ft_Yellowstone_CPS_Blank.xlsx XLSX spreadsheet
B08_Section_J_Attachment_2_307127_Rehab_Ft_Yellowstone_CD_Specifications_23_AUG_2024.pdf PDF
Sol_140P2024R0177.pdf PDF
B08_Section_J_Attachment_11_307127_Rehab_Exteriors_Ft_Yellowstone_XRF_analysis_Report.pdf PDF
B08_P2024R0177_YELL_307127_1442_Solit_Clauses_9_24_24.pdf PDF
B08_Section_J_Attachment_18_Letter_of_Comm.pdf PDF
B08_Section_J_Attachment_10_307127_Hazardous_Materials_Report.pdf PDF
B08_Section_J_Attachment_14_Wage_Determination.pdf PDF
B08_Section_J_Attachment_1_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_23_AUG_2024_Part1.pdf PDF
B08_Section_J_Attachment_15_Contract_Admin_Form.pdf PDF
B08_Section_J_Attachment_7_307127_Rehab_Exteriors_Ft_Yellowstone_Condition_Assessment.pdf PDF
B08_Section_J_Attachment_1_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_23_AUG_2024_Part7.pdf PDF
B08_Section_J_Attachment_1_307127_Rehab_Exteriors_Ft_Yellowstone_CD_Drawings_23_AUG_2024_Part2.pdf PDF
B08_Section_J_Attachment_12_Rehab_Exteriors_Ft_Yellowstone_Radon_Assessment_Report.pdf PDF
B08_Section_J_Attachment_17_General_References_Form.pdf PDF
B08_Section_J_Attachment_4_YELL_307127_StatementOfStructuralTestsSpecialInspections.pdf PDF
Pages_from_B08_Section_J_Attachment_19__Solit_PSP_Vol_I_Project_Experience_Questionnaire.pdf PDF
B08_Section_J_Attachment_13_307127_Rehab_Ft_Yellowstone_Phasing_Plan.pdf PDF
B08_Section_J_Attachment_9_307127_Rehab_Exteriors_Ft_Yellowstone_Final_Paint_Schemes.pdf PDF
B08_Section_J_Attachment_5_307127_Rehab_Ft_Yellowstone_Submittal_List_23_AUG_2024.xlsx XLSX spreadsheet
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Proposal Conference

YELLOWSTONE National Park Rehabilitate EXTERIORS OF

FORT YELLOWSTONE STRUCTURES

Solicitation: 140P2024R0177

NPS PMIS #: YELL 307127

September 24, 2024 E X P E R I E N C E Y O U R A M E R I C A

Agenda WELCOME & INTRODUCTIONS : Lawrence Mason, DSC Project Manager Agenda Pre-Proposal Site Visit Logistics PROJECT OVERVIEW : Lawrence Mason, DSC Project Manager Location, History, Resources, Existing Conditions Brief Review : Scope of Work, Project Phasing PROJECT CONSIDERATIONS : David Longtin, DSC Project Specialist Project Execution and Logistics; Simultaneous Heating Line Project PROPOSAL INFORMATION : Vicki Freese-Supler, DSC Contracting Officer Summary of Solicitation

PROJECT SITE TOUR : NPS

PRE-PROPOSAL CONFERENCE QUESTIONS : Vicki Freese-Supler, DSC Contracting Officer CONCLUSION : Lawrence Mason, DSC Project Manager

NPS – Rehabilitate Exteriors of Fort Yellowstone Structures

Project Location Fort Yellowstone History https://www.nps.gov/thingstodo/yell-tour-fort-yellowstone.htm Resources Existing Conditions Scope of Work

Project Overview

Project Location Location Map Aerial image of the Mammoth area

Project Site Overlay

Yellowstone History Yellowstone National Park established in 1872.

Railroad arrived in 1883, allowing easier visitor access.

The US Army managed the park from 1886 through 1918.

Automobiles allowed into the park in 1915, making visits easier and more economical.

National Park Service created in 1916.

First boundary adjustment of the park made in 1929.

Fort Yellowstone History

Fort Yellowstone History

Soldiers drilling in front of Bachelors Officers’ Quarters ca.1910 – building now in use as the Albright Visitor Center.

Resources for Project Information:

Technical PlansSep 2024 *
Technical SpecificationsSep 2024 *

Supporting Studies, Reports, Assessments *

Condition AssessmentNov 2021 *
Treatment GuidelinesMar 2021 *

Secretary of the Interior’s Standards for Historic Preservation NPS Preservation Briefs *Included in solicitation Resources

There are several resources available online on our NPS websites as well as in the solicitation package that will aid in a better understanding of this very complicated building. With the evolution of construction, each wing was developed slightly differently with different construction methods. The resources that are available online are the park’s General Management Plan, developed in 2009 that provides high level planning for the overall park, The Secretery of Interior Standards for Historic Preservation governs all of the NPS existing buildings and landscape capital improvements projects, and

Refer to the solicitation package of technical plans and specifications, including the appendices – these documents will prepare you for understanding not only the technical aspects of the project but also the importance of the historic fabric that we’re going to be working with and around. There is a Historic Preservation Plan Matrix that will aid in your understanding of how the technical plans and specifications will impact some of the character-defining features of the building – the matrix document references the developmental history, NPS historic preservation policies, Secretary of Interior Standards for Historic Preservation and assists in identifying areas warranting historic fabric protection, the document will be issued in an upcoming amendment.

Note that included in the solicitation package - there are hazardous material reports, interior wayfinding and signage drawing set, the historic structure report that provides background on history and significance and General Hierarchy of Decisions and Protections in understanding how the design was developed to minimize impacts to the historic fabric. Also note that with any excavations in and around historic buildings and cultural landscapes, archaeology is a consideration and so there will be archaeological monitoring provided by the NPS as the projects moves forward with any excavation, digging, ground disturbance. That coordination is very important to NPS.

Existing Conditions : Roof

Existing Conditions : Masonry

Existing Conditions : Siding

Existing Conditions : Windows & Doors

Existing Conditions : Miscellaneous

Project Scope

Typical details

Door and window schedules

Demo and Site Work

Grading, Landscape, and Storm Drainage

Project Phasing

Project Phasing (example schedule)

Project Execution and Logistics

SOLICITATION NO.140P2024R0177

SUMMARY OF SOLICITATION AND AWARD INFORMATION

Refer to the Solicitation for complete information.

PRE-PROPOSAL ON SITE MEETING – September 24, 2024 PRE-PROPOSAL QUESTIONS DUE – October 18, 2024 OFFERS DUE – October 28, 2024 at 2:00 p.m. Mountain Time SUBMISSION – Electronic only to: Vicki Freese-Supler and Jason Longshore (Section L) SECTION L – 52.216-1 – Type of Contract – Firm Fixed Price NAICS Code: 236220 – Commercial and Institutional Building Construction Small Business Size Standard : $45M

THIS IS A FULL AND OPEN COMPETITION – NO RESTRICTIONS

PERIOD OF PERFORMANCE: Project completion 1,009 calendar days after Notice to Proceed.

CONTRACT VALUE: More than $10M

SOLICITATION CLAUSES

FAR 52.211-12 – Liquidated Damages-Construction - $1,560.00 FAR 52.236-2 – Differing Site Conditions FAR 52.236-3 – Site Investigations and Conditions Affecting the Work FAR 52.236-9 – Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements FAR 52.236-21 – Specifications and Drawings for Construction

BASIS OF AWARD

The Government will conduct a source selection using the Best Value Continuum Tradeoff Process defined at FAR Part 15.1. The Contracting Officer (CO) will obligate and award a contract to the offeror who submits a proposal the Source Selection Authority (SSA) determines conforms to solicitation requirements; is fair and reasonable; and provides the best value to the government considering all evaluation factors combined as detailed below.

The Government may accept other than the lowest priced proposal when the perceived benefits of a higher priced proposal merit the price differential.

Additionally, pursuant to FAR 52.215-1(f), Contract Award, contained herein:

The Government may reject any or all proposals if such action is in the Government’s interest.

The Government may waive informalities and minor irregularities in proposals received.

The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the CO later determines them to be necessary.

TECHNICAL EVALUATION CRITERIA:

FACTOR 1 – Technical Approach FACTOR 2 – Project Experience FACTOR 3 – Management Approach FACTOR 4 – Schedule FACTOR 5 – Key Personnel Experience FACTOR 6 – Past Performance FACTOR 7 – Small Business Participation FACTOR 8 – Price

Factors 1-7 are listed in descending order of importance. All evaluation factors other than price, when combined are approximately equally important to price.

FACTOR 1 - Technical Approach Technical Approach – Technical approach is your means and methods to complete a technical aspect of the required work in this solicitation.

Approach to Critical Contract Requirements: Describe your approach to successfully accomplish the work identified in this solicitation to include the rehabilitation of the exterior portions of the various building included as part of this solicitation.

Logistics, Coordination, Process: Describe logistics for material delivery, staging, installation and disposal (hazardous and non-hazardous materials), including long lead items given the limited site access and areas available for construction activities.

Risk Mitigation: Submit a risk analysis identifying critical issues, potential problems, and/or areas of concern with recommended solutions. Include strategies to manage project risks such as weather and working around unforeseen site conditions, material lead times, and work force.

Natural, Cultural or Historic Resources: Describe your approach to for protection and preservation of natural/cultural/historic resources as required in the solicitation, including but not limited to requirements in the Construction Drawings and Construction Specifications and in accordance with the HPTC Treatment Guidelines and the Secretary of the Interior’s Standards for the Treatment of Historic Properties (2017).

Teaming Experience: Describe your experience as a prime contractor working with the proposed team (key personnel and key subcontractors) on historic preservation type properties. Prime contractor experience is experience as a general contractor managing multiple subcontractors on projects you self- performed at least 40% of the cost of the contract, excluding materials.

Remote Work: Describe your experience with construction at remote sites withdifficult access, in extreme environmental conditions under limited constructionseasons similar to the scope, magnitude and complexity of this solicitation.
Historic Preservation: Describe your experience with construction/rehabilitation ofhistoric features in accordance with the Secretary of Interior’s Standards for theTreatment of Historic Properties (2017) in accordance with HPTC TreatmentGuidelines.

FACTOR 2 - Project Experience (Project Experience Form)

Management approach is the organizational structure and business processes to manage, control, and oversee your firm’s operations.

Organizational Chart: Submit an organizational chart identifying the project team with major subcontractors and key personnel identifying specific roles, responsibilities and lines of authority. For key subcontractors, submit a signed letter of commitment from the subcontractor indicating their role in the project, its resources and its intent to enter into a subcontract with the Offeror. Describe prior project experience working together and how the proposed project team will enhance and ensure a well-coordinated and successful outcome for this project.

Capacity: Submit a written narrative of your firm’s capabilities and assets that are available for this project. Indicate existing capacity to perform this work concurrent with existing ongoing projects. Describe your firm’s resources and equipment that will be used for the work on this project.

Coordination: Describe the proposed coordination with the project owner (National Park Service) and other (State, City, Local) regulatory entities to complete work within all parameters of the solicitation Safety/Quality Control: Submit a general management approach narrative to maintaining and managing project safety, quality control, cost management and schedule management. Address how these general management procedures will be applied specifically to the scope, location, and schedule of this project.

FACTOR 3 - Management Approach

Submit your proposed construction schedule for THIS SPECIFIC PROJECT showing completion within the required period of performance contained in this solicitation with accompanying schedule narrative. Submit your schedule in MS Project Gantt Chart format; for evaluation purposes only assume a Notice to Proceed date of March 3, 2025; and include specific activities required for this project and a clear critical path with major milestones and applicable predecessor activities. In your accompanying narrative (limited to five (5) pages, explain schedule logic, critical path activities and key considerations and constraints.

FACTOR 4 - Schedule

Submit resumes for key personnel as identified in Section H of this solicitation and listed below. All personnel proposed are subject to substitution requirements contained in this solicitation. There is no preprinted form for this submittal.

• Project Manager

• Superintendent

• On-Site Quality Control Specialist

• On-Site Safety Specialist

FACTOR 5 - Key Personnel Experience

Submit Past Performance information for the same projects submitted under Project Experience (Factor 2) using the attached Past Performance Questionnaire. Information may be regarding the Offeror’s firm and/or its proposed subcontractors performing key trades and other construction activities. Subcontractor past performance will only be considered if it correlates to the work the subcontractor will be performing on this requirement. Submittal process for the Past Performance FACTOR 6 - Past Performance

FACTOR 7 – Small Business Participation All Offerors (Other than small businesses) shall submit a Small Business Participation Document that addresses the evaluation criteria in the Small Business Factor contained in Section M of this solicitation.

Standard Form (SF)1442 will be reviewed for completeness Amendment Acknowledgement will be reviewed for timely and proper acknowledgement

SECTION B PRICE SCHEDULE

SF 24 BID BOND

SECTION K REPRESENTATIONS AND CERTIFICATIONS (entire section)

GENERAL REFERENCES

SUBCONTRACTING PERCENTAGE WORKSHEET (all Offerors) SUBCONTRACTING PLAN (only required for large business)

VOLUME II

Business and Price Proposal

VOLUME II

Business and Price Proposal Contract Price Schedule

Base Scope

Optional Scope

Direct all questions to the CO who requests that they be submitted in writing via email to both the CO, Vicki Freese-Supler, vicki_l_freese-supler@nps.gov, and the BC, Jason Longshore, jason_longshore@nps.gov

Questions and answers will be issued by written amendment posted as an amendment to the solicitation. Offerors are required to fill out and sign the acknowledgment of amendments received (SF1442 Section 19) and include this when submitting our offer on the Form 1442.

Responses to questions that may be stated during the pre-solicitation site visit do not change the Solicitation document unless a formal Amendment has been issued.

For all other interested vendors not able to attend this pre-proposal site visit, an amendment will be provided which will include this presentation and sign in sheet.

The deadline for questions related to this solicitation: October 18, 2024, 2:00 MT.

All Offers are due on October 28, 2024, 2:00 MT SOLICITATION: Important Information

Thank You For Your Interest in This Project E X P E R I E N C E Y O U R A M E R I C A

National Park Service U.S. Department of the Interior image2.jpeg image3.jpeg image4.jpeg image5.jpeg image6.jpeg image7.jpg image8.png image9.jpeg image10.jpeg image11.jpeg image12.jpeg image13.jpeg image14.jpeg image15.jpeg image16.jpeg image17.jpeg image18.jpeg image19.jpeg image20.jpeg image21.jpeg image22.jpeg image23.jpeg image24.jpeg image25.jpeg image26.jpeg image27.jpeg image28.jpeg image29.png image30.jpeg image31.jpeg image32.jpeg image33.jpeg image34.jpeg image35.jpeg image36.jpeg image37.jpeg image38.png image39.png image40.png image41.png image42.png image43.png image44.png image45.png image46.png image47.png image48.png image49.png image50.png image51.png image52.png image53.png image54.png image55.png image56.png image57.png image58.png image59.png image60.png image61.png image1.jpeg

File details come from the government source that posted it. Updated .