This document is an amendment to a solicitation for the YELL 307127 - Rehabilitate Historic Structures project. The key details are:
The amendment extends the proposal due date to November 4, 2024 at 2:00 pm MT. It provides the questions and answers received to date, as well as revised construction specifications and drawings. Specifically, it removes work associated with Building 83 and provides an updated Section J and Mortar Sample Log. The agency is the Department of the Interior National Park Service National Office. The original solicitation number is 140P2024R0177. All other terms and conditions of the solicitation remain unchanged.
View the file
Other files
Show all 46
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P2024R0177 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PDS
Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div
09/25/20240002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
09/24/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
YELL 307127 - Rehabilitate Ft. Yellowstone Structures
The purpose of this amendment is to provide the following items:
1. To extend the date for receipt of proposals to November 4, 2024 at 2:00 p.m. MT.
2. To provide for the Questions and Answers received to date.
3. To provide for the following amended Construction Specifications:
a. Remove Construction Specification 01 10 00 Summary of Work and replace with
Construction Specification 01 10 00 Summary of Work dated October 3, 2024.
b. Remove Construction Specification 01 31 00 Project Management & Coordination and replace with Construction Specification 01 31 00 Project Management and Coordination dated
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Vicki Freese-supler
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140P2024R0177/0002
October 3, 2024.
c. Remove Construction Specification 01 35
91 Historic Preservation Treatment Procedures and replace with Construction Specification 01 35 91
Historic Preservation Treatment Procedures dated
October 3, 2024.
d. Remove Construction Specification 01 50
00 Temporary Facilities and Controls and replace with Construction Specification 01 50 00
Temporary Facilities and Controls dated October
3, 2024.
4. To provide revised construction drawings removing all references to work associated with
Building 83. Remove Construction Drawings and replace with Construction Drawings - September 5, 2024 Rev 01.
5. To provide for an updated Section J.
6. To provide for the Mortar Sample Log.
7. To provide the
Standards-Guidelines-Archeology-Historic
Preservation.
All other terms and conditions of the solicitation remain unchanged and in full force and effect.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
# Question: Answer Amendment No.:
1 Please clarify whether the Stable Street staging area shown on Sheet 00-G006 is available for the duration of the project.
Sheet 00-G006 is available for the duration of the project. This has been changed in the updated Sheet 00-G006.
2 Please clarify whether Building 83 is included in this project.
Any work associated with Building 83 his hereby deleted from this project. No work is required at Building 83.
3 Please clarify whether re-pointing of the exterior foundation walls is required all the way down to the top of the footings, as is stated on the Exterior Demolition Elevation sheets (Notes 7 and 8), or only as deep as the bottom of the perimeter gravel bed excavations, as is shown on the "perimeter gravel bed at (e) foundation details," like on 06-A801.
Re-point in accordance with "sequence of installation" shown on the detail you referenced.
Ignore the reference to the required depth of re-pointing on the Exterior Demolition Elevation sheets.
4 What structural upgrades are required at the walls and roofs of Buildings 2 and 3, as referenced in the Summary of Work for each of these buildings?
There are no wholesale upgrades required to the walls and roofs of these buildings. Ignore these references in the Summaries of Work and complete the work described in the remainder of the sheets associated with these buildings.
5 Can Site Superintendent function as the safety specialist?
No. No dual-hatting. 2
6 If possible to open the past performance period to at least 10 years
Yes. 2
7 Could we receive clarification regarding the paint preparation on the chimneys prior to repainting? Will they be fully abated and stripped to bare masonry prior to painting, or will they be prepared and encapsulated with new paint?
To clarify, existing paint at brick masonry chimneys will not be fully removed prior to repainting. The existing paint will be prepared and cleaned to receive new paint based on the “Degree of Surface Degradation” as defined in Section 09 03 91, 3.9 Surface-Preparation Schedule. Likely, there will be different surface preparations for different conditions. Contractors should bid on an “average” condition.
8 Spec 01 35 91, para 1.4 mentions that there will be a Historic Preservation Treatment Specialist. It also states that this person’s qualifications will meet 36 CFR Part 61.
However, there are no qualifications listed in 36 CFR Part
61. This CFR references “Procedures of State, Tribal, and Local Government Historic Preservation Programs.”
Replace Specification 01 35 91 in the CDs with the 01 35 91 provided with this amendment. The new spec achieves the following:
1. Better defines the role of the Historic Preservation Treatment Specialist, and reduces the time-on-site requirement; and
9 Is it a requirement to salvage metal roof tiles? Deletes the requirement to salvage metal roof tiles.
They do not need to be salvaged.
10 Spec 01 35 23, para 1.4 B calls for a Site Safety Supervisor. Can this role also be filled by the same person as the Site Superintendent?
No. 2
11 Can one person serve as the SSHO, CQC and Superintendent? If not, please clarify which roles can be combined so that the total number of field managers on site can be determined.
No. 2
12 All around each house, there were numerous borrows seen for chipmunks and other animals. Please clarify who will be responsible for their removal. Once captured, did NPS want them released or handled by an exterminator?
The contractor is not responsible for capturing and disposing of rodents that are encountered during the performance of the site work.
13 01 57 23- Temp SWPP. Please clarify who is responsible for the NPDES permit fees.
Per Spec 01 31 00 (1.9)(A)(1), the Contractor is responsible for obtaining permits, which includes the payment of permit fees.
Revised Spec 01 31 00 (1.9)(C)(9) has been changed to read as follows: "Stormwater Pollution Prevention Permit - No permit anticipated, as improvements will occupy less than one acre of area."
An Under-an-Acre Pollution Prevention Plan (UPPP) as described in Spec 01 57 23 is anticipated.
14 What type of historic mortar analysis is required? E.g., Petrographic, X-Ray Diffraction, X-Ray Fluorescence, Scanning Electron Microscopy. How many mortar test samples are required per building? Please identify which parts of building the tests should be taken from? E.g., Chimney, foundation, etc.
Mortar analysis was completed for each building in August 2021. "Custom Mortar Matching Reports" by U.S. Heritage Group are included in Appendix C of the Project Specifications. Mortar mix designs listed in 04 03 00 of the Project Specifications are the same mortar mix designs proposed by U.S. Heritage Group. Attached is the Mortar Sample Log indicating where samples were taken. No additional mortar analysis is required.
15 Will archaeological and Cultural monitors be provided? The Park will be providing the archeological and cultural resources monitors.
16 What is the NTP date for planning purposes? Assume an NTP date of 03/03/25. 2 17 Who is responsible for snow removal in staging areas The contractor is responsible for snow removal within the staging areas.
18 Can the paint removal be done onsite? Location of paint removal is at the discretion of the contractor, however all federal, state and municipal guidelines are applicable, regardless of location.
19 ½” plywood added. Will now be created a 1/2” gap between the window and the trim. (see below sketch) How do we fill the void? We assume that NPS wants to salvage and reuse the existing trim and jamb. Hence, we will need to put in a filler piece. Will that be acceptable
The existing trim and jamb must be salvaged and reused to the greatest extent possible. However, existing sheathing (assumed to be true 1x) will be removed and replaced with 1/2" plywood sheathing and 1/4" furring strips. There is no net gain in sheathing thickness.
20 Spec 07 31-16-3 Field conditions 1.8A states not to install metal shingles when windchill <45degrees? This is unnecessarily restrictive and will limit the ability to have the work done. Can this be change to above 35 degrees ambient. I don’t understand the relevance of wind chill, either, unless the concern is that the workers will be too cold to do a good job.
For all components noted in 1.8.A, Contractor must comply with manufacturer's installation instructions.
21 Please clarify for the areas where we are to apply to paint to existing materials, are we to scrape down to a sound surface, or will we have to remove the existing paint 100% to the bare material.
Refer to 06 03 12 – 3.5 Paint Removal. Remove existing paint to bare substrate.
22 If there is a combination of scraping and full removal, please clarify which areas those would apply.
Refer to 06 03 12 – 3.5 Paint Removal. Remove existing paint to bare substrate.
23 Sheet 02-A901, why does only 4 openings show ‘exterior trim’ with level 1 repair? Why are the other windows shown as N/A? On the elevations, there does not seem to be any difference in these windows.
The exterior trim repair level for 2.N1.04, 2.N1.05, 2.N1.06, and 2.N3.01 should be “N/A.” The reason “N/A” is noted for all exterior trim, is because these windows are set into a stone masonry wall and do not have exterior trim.
24 Will electrical service be available at any of the staging areas shown on Sheet 00-G006?
There is an electric service available at the staging area located due east of Buildings 7 and 8, and northeast of Building 12.
25 Do you want all paint removed, down to bare wood, from all the window/door components regardless of needed repairs? Does paint need to be removed to bare wood only when necessary to perform repairs? Loose paint can be removed, and stable existing paint can be encapsulated.
Refer to Specification Sections 08 03 14 Historic Treatment of Wood Doors, and 08 03 52 Historic Treatment of Wood Windows, and 09 03 91 Historic Treatment of Plain Painting.
26 Will the contractor have to pay for gate entrance fees? No. The park will be providing access passes for all contractor personnel.
27 What is the retainment expectation for siding? See Specification Section 02 41 19 Selective Demolition for table showing assumed amount of salvageable siding.
28 Will wood shingles on building 2 and 3 be removed/ restored? Clarify scope of wood shingle siding throughout.
Wood shingles at Buildings 2 and 3 are to remain and will be repainted. Wood shingles at Buildings 4- 8, 10-12, and 30-33, will be removed and replaced in kind with new shingles. See Specification section 07 31 29-2, 2.1.A. Shingles and Shakes.
29 Is there matching stone available for use in masonry repairs?
Yes, replacement stone is available in the Yellowstone National Park stockpile. See Specification section 04 03 00-6 Historic Treatment For Masonry – 2.3.B.1. Feldspathic Sandstone:
Coordinate with Contracting Officer to obtain replacement material from Yellowstone National Park stockpile.
30 The siding on the dormers on Buildings 30-33 consists of shingles. Is there any scope associated with these shingles?
The intention is to remove the existing shingles and then replace them, per Detail 2 on Sheet 30-A803 (for example).
31 Buildings 30 to 33, Floor Plan Notes 9 and 10 say to salvage stair parts and skirt trim. Is that realistic?
See Specification Section 06 03 12 Historic Wood Repair. Subsection 3.8 Repair Procedures lists three levels of repair that correspond to Keynotes 22, 23 and 24 on the A100 Existing/Demo Exterior Elevation drawing sheets. If the removal of wood components causes damage beyond a Level 2 Repair, then a Level 3 wood repair (replacement in-kind) is acceptable.
32 "Repair spalling" is vague. Please list criteria where spalling needs to be repaired and methods of repair that will be acceptable.
For bidding purposes, spalling stone will be repaired with a masonry unit dutchman. See Specification section 04 03 00 - Historic Treatment of Masonry.
Subsection 3.7.B outlines the repair procedures for a dutchman installation.
33 "Repair stone delamination" is vague. Please list criteria where spalling needs to be repaired and methods of repair that will be acceptable.
For proposal submission purposes, delaminated stone will be repaired with a masonry unit dutchman. See Specification section 04 03 00 - Historic Treatment of Masonry. Subsection 3.7.B outlines the repair procedures for a dutchman installation.
34 Temporary facilities - What size storage container can we place on the site? How many storge containers can we bring on site?
Storage container size limited by extents of staging area.
35 Can we have a storage container on Officer’s Row if we have it blocked visually with temp fencing and screens?
Not prohibited by the contract, but YELL should be consulted. The Park requires at least one lane be provided for vehicle traffic to pass through the area.
36 Where can we place our work trailer? Can one be placed at Officer’s Row? Work trailer = job office?
Work trailer can be placed in area designated as staging location behind the Officer Row housing.
See Sheet 00-G006.
37 Are we permitted to use the public toilets in lieu of bringing in temp toilets?
No. The contractor must provide their own temporary toilet facilities, please reference Construction Specification 01 50 00 (Section 3.2(e).
38 Spec 06 03 12-6, para 3.3 E.1&2 states to remove landscape covering at the end of each work day. Can we use a breathable cover and pull it off only on the weekends.
No. 2
39 Spec 07-31-16-2 , para-1.6 mock ups , states to construct an 8’x8’ roofing mockup. Can that be 4’x4’ on the ground?
No. Mockup must be as denoted in the specification. 2
40 Please clarify that this a lead in construction project, not a lead abatement project.
Lead abatement is the responsibility of the contractor. Refer to 02 83 00 – Lead-Based Paint Stabilization, Component Removal, and Soil Removal. Refer to Appendix B: Hazardous Materials Inspection Report, Tetra Tech, Inc., August 2021.
41 Also do we need to itemize OH&P, PM/Superintendent/Labor rates, etc. on the price schedule?
Not on the price schedule but this information may be included in the narrative portion of the Volume II submission
42 Could spray insulation be used in the roof/ walls, to address concerns about construction time?
Use of spray foam insulation is not permitted unless approved by the Contracting Officer.
43 Are chimneys to be painted? Yes, only if they are currently painted. 2 44 Can we get a two week extension for receipt of proposals?
The proposal due date is extended to November 4, 2024 at 2:00 p.m. Mountain time.
45 Which lanes do we use to enter the Park? If entering the Park through the Gardiner entrance gates, all contractors shall utilize the two gates reserved for visitors with the name of their company denoted on their truck for identification purposes.
At no time are contractors to utilize the employee only gate.
46 what are the work hours for the project? Normal workhours are 7:00 a.m. to 6:30 p.m.
Monday through Friday. No noisy work before 8:00 a.m. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the contracting officer.
47 Is signature required on the price schedule No - signature is required on the SF 1442 2 48 Do we need to itemize OH&P, PM/Superintendent/Labor rates, etc. on the price schedule?
No - this information should be included in the narrative portion of Volume II submission.
YELL - 307127 01 11 00 - 1
051121 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. Work Sequencing
3. Contractor Use of Site
4. Public Use of Site
5. Occupancy Requirements for Buildings
6. Conduct of Operations
7. Work Restrictions
8. Special Construction Requirements
9. Additional Reports
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Fort Yellowstone National Historic Landmark District, Mammoth, Wy, Yellowstone National Park.
B. The Work consists of:
1. Exterior rehabilitation of 17 historic buildings, including hazardous materials abatement of lead and asbestos, roof repair and replacement, siding replacement, window and door restoration, chimney repair and stabilization, porch repair, masonry repair and cleaning, structural improvements, radon mitigation, and stormwater drainage. The buildings contain a total of 32 dwelling units that serve as housing for park staff. All structures are part of the Fort Yellowstone National Historic Landmark District.
C. Project will be constructed under a single prime contract.
1.3 WORK SEQUENCING
A. Contractor to provide Sequencing Plan and Schedule showing proposed sequencing of building rehabilitations in conformance with Yellowstone National Park, “Rehabilitate Exteriors of Historic Fort Yellowstone Buildings” project. See “Final Construction Phasing Plan” included at the end of this section for anticipated phasing of building construction. Each building grouping rehabilitation phase is to be completed prior to commencement of subsequent phase, except as follows: (1) simultaneous construction of Phases 2A and 2B is allowed and (2) simultaneous construction of Phases 3 and 4 is allowed. Within Phases 1 and 2A, upon Contracting Officer approval of required mockups, commence construction at smaller wood frame Buildings (8 and 9) and progress to the more complex, multistory wood frame Buildings (4-7) along Officer’s Row. Include in Sequencing Plan subsequent work Phase 2B (Buildings 10 and 11), Phase 3 (Buildings 12 and 14), and Phase 4 (Buildings 30, 31, 32, and 33). Buildings 2 and 3 along Officer’s Row are not specifically associated
YELL - 307127 01 11 00 - 2
with any phase. They shall be included in the overall Sequencing Plan either simultaneous with the last group of buildings the Contractor is working on, or after all other buildings have been completed.
B. Contractor shall assume that all units rehabilitated during a single phase as identified in the “Final Construction Phasing Plan” will remain unoccupied for the duration of construction.
C. Sequencing Plan to be reviewed and approved by the Contracting Officer prior to commencement of work. Include in Sequencing Plan:
1. Schedule of construction for building phase groupings indicated in 1.3A. Include associated sitework areas in schedule and plan identifying approximate areas of disturbance with each building grouping.
2. Proposed use of staging areas, access roads, and parking areas at each building grouping.
3. Methods for limiting building exposure to weather during construction work. Indicate safeguards for use during severe weather conditions.
4. Methods for limiting disruption to normal operations of areas adjacent to work areas.
Include description of limiting roadway traffic and contractor use of parking areas.
D. Contractor to incorporate Sequencing Plan as submitted into overall Project Schedule required per Section 01 31 00.
1.4 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of site for construction operations. Limit use of premises to areas within the Construction limits indicated on drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limit site disturbance, including earthwork and clearing of vegetation, to 40 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter; 15 feet beyond primary roadway curbs and main utility branch trenches; and 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.
B. Storage of Materials: Confine storage of materials to staging and storage area shown on plans.
1. Store items for reinstallation in a dry and secure place. Provide Conex boxes for security and material protection.
2. Salvaged items:
a. Clean and repair salvaged materials to functional condition adequate for intended reuse.
b. Pack or crate items after cleaning. Identify contents of containers.
c. See Section 01 35 91 Historic Preservation Treatment Procedures for additional requirements for salvage of historic building materials.
3. Store sensitive products in weathertight, climate-controlled enclosures in an environment favorable to product.
4. For exterior storage, place on sloped supports above ground.
5. Protect materials from damage or deterioration due to construction operations, weather, precipitation, humidity, temperature, sunlight and ultraviolet light, dirt, dust, and other contaminants.
6. Cover materials subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of materials.
7. Prevent contact with material that may cause corrosion, discoloration, or staining.
YELL - 307127 01 11 00 - 3
8. Provide equipment and personnel to store material by methods to prevent soiling, disfigurement, or damage.
9. Arrange storage of materials to permit access for inspection. Periodically inspect to verify materials are undamaged and are maintained in acceptable condition.
10. Storage areas to remain orderly, neat, and free of debris, trash, and waste materials.
Provide daily cleanup of work areas and securing of loose materials.
C. Staging of Materials:
1. Staging area: Provide a fenced area with entry and exit control.
2. Potential locations for staging areas. See Drawings for additional location information:
a. Roadway to the west of Officer’s Row. Coordinate with Contracting Officer for specific boundaries and closure requirements.
b. Parking area north of Building 12 and Barracks Street.
c. Soap Suds Row on west side of Buildings 30-33.
d. Overflow parking to east of chapel.
3. Upon completion of project, rehabilitate the staging area(s) and repair any damage to (as noted but not limited to):
a. Irrigation
b. Plantings
c. Roadways
d. Sidewalks not scheduled to be replaced within the limits of work boundary.
e. Provide photo inventory of staging areas before contractor occupation and after final completion of work. Provide to Contracting Officer for review and approval.
D. Parking: Confine parking to staging area.
E. Stockpiling: Confine stockpiling to staging area.
F. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones. Place fence at dripline of Cottonwood trees designated for protection.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer (CO) and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
G. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.
1. Maintain clearance at roads for fire emergency vehicles at all times. Do not impede on width of roadways.
H. Construction Camp: Establishment of a camp within park will not be permitted.
I. Provide housing for construction workers outside of Park. Workers typically stay in Gardiner, MT.
YELL - 307127 01 11 00 - 4
J. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1. Deliveries allowed only between the hours of 8 a.m. and 5 p.m. all days.
K. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.
L. Use of explosives is not allowed.
M. Work Under Other Contracts: Cooperate with separate contractors so work on those contracts may be carried out smoothly, without interfering or delaying work under this Contract. Coordinate Work of this Contract with work performed under separate contracts.
1. A project to replace the heating systems of Fort Yellowstone Buildings 4, 5, 6, 7 and 8 will take place from approximately November 2024 to October 2025. Work will include (1) installation of buried propane tanks between Buildings 4 and 5, (2) construction at Buildings 4, 5, 6, 7 and 8 to accommodate new heating systems and (3) installation of buried service lines from the tanks to the heating system.
1.5 PUBLIC USE OF SITE
A. The buildings designated for rehabilitation within a single phase as indicated in the “Final Construction Phasing Plan” will be closed to the public during construction.
1.6 CONDUCT OF OPERATIONS
A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 3 business/calendar days in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.7 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7 a.m. to 6:30 p.m., Monday through Friday, except when otherwise indicated.
1. Early Morning Hours: No noisy work before 8:00 am.
B. Existing Utilities
YELL - 307127 01 11 00 - 5
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than seven business days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Restrict planned utility interruptions to a maximum of four (4) hours.
D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within 25 feet of entrances, operable windows, or outdoor air intakes. Tobacco use and vaping is restricted to designated areas,
1.8 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by NPS will be used for purposes of managing communication and documents during construction stage.
1. See Section 01 31 00 "Project Management and Coordination" for requirements on using Project Website.
B. The park will be open during the following events and holidays, work will not take place within the project limits without permission from the Contract Officer:
1. Federal Holidays (Memorial Day, 4th of July, Labor Day)
1.9 REHABILITATE EXTERIORS OF HISTORIC FORT YELLOWSTONE BUILDINGS
PHASING PLAN
A. Phasing Plan indicating required building groupings organized into rehabilitation phases is attached for contractor reference at the end of Section 01 11 00 – Summary of Work.
1.10 ADDITIONAL REPORTS – SEE APPENDIX AT END OF SPECIFICATIONS
A. Fort Yellowstone Condition Assessment, Hennebery Eddy Architects, November 2021.
B. Hazardous Materials Inspection Report, Tetra Tech, Inc., August 2021.
C. Custom Mortar Matching Report, U.S. Heritage Group, August 2021.
D. Fireplace Level 2 Inspections Report, Big Sky Chimney, January 2023.
E. Radon Assessment Report, Tetra Tech, January 2023.
F. Portable XRF Study of Fort Yellowstone National Park (Paint Composition Analysis), Built Environment Evolution, March 2023.
YELL - 307127 01 11 00 - 6
G. In case of conflict between report and drawings or specifications, drawings and specifications govern.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
YELL – 307127 01 31 00 - 1
012721 PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. Customer Relationship Management (CRM) Software provided by NPS
7. Project Meetings
8. Environmental Coordination
9. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction B. Construction Permits – Contractor Provided C. Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
YELL – 307127 01 31 00 - 2
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Contractor's Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of Contract Documents or standard printed data. Include following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, mechanical, civil, and irrigation systems.
b. Indicate dimensions shown on Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer (CO) for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to radon vent piping.
e. Indicate required installation sequences.
2. Sheet Size: At least 8-1/2 by 11 inches but no larger than 22 by 34 inches.
3. Number of Copies: Submit two opaque copies of each submittal. Contracting Officer will return one copy.
4. Refer to individual Sections for Coordination Drawing requirements for Work in those
Sections.
YELL – 307127 01 31 00 - 3
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Floor Plans and Reflected Ceiling Plans: Show architectural, structural, mechanical, plumbing, fire-protection, fire-alarm, and electrical elements. Show locations of visible ceiling-mounted devices. Supplement plan drawings with section drawings where required to adequately represent the Work.
2. Structural Penetrations: Indicate penetrations and openings required for all disciplines.
3. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, and angles.
4. Review: Contracting Officer will review coordination drawings to confirm Work is being coordinated; details of coordination are Contractor's responsibility. If Contracting Officer determines coordination drawings are not prepared in scope or detail, or are otherwise deficient, Contracting Officer will inform Contractor, who shall make changes and resubmit.
5. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 "Submittal Procedures."
C. Coordination Digital Data Files: Prepare coordination digital data files according to:
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
2. File Submittal Format: Submit or post coordination drawing files using Portable Document Format (PDF) file format.
3. Contracting Officer will furnish Contractor one set of digital data files (PDF) of Drawings for use in preparing coordination digital data files.
a. Contracting Officer makes no representations as to accuracy or completeness of digital data files as they relate to Drawings.
b. Digital Data Software Program: Drawings are available in Autodesk Revit and PDF.
D. Division 1 documents: The following items shall be submitted a minimum of one week prior to Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for Pre- Construction Conference.
1. Letter designating Project Superintendent
2. Construction Schedule
3. A Comprehensive Schedule of Values
4. Accident Prevention Plan
5. A List of Subcontractors for this project
6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
7. Certificates of Insurance or SF1413 for Contactor and all Subcontractors
8. Waste Management Plan
9. Quality Control Plan
10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP)
11. Indoor Air Quality (IAQ) Management Plan
12. Historic Preservation Treatment Plan (HPTP)
13. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit
b. Agency(ies) with Jurisdiction issuing the permit
c. Information required from Government to complete permit application
YELL – 307127 01 31 00 - 4
E. Provide items listed to Contracting Officer before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of Contract Documents, Contractor shall prepare and submit an RFI utilizing form created on CRM Software.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract
Time or Contract Sum, Contractor shall state impact in RFI.
8. Contractor's signature
9. Requested date for response
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in Contract Documents.
e. Requests for adjustments in Contract Time or Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
YELL – 307127 01 31 00 - 5
2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.
3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or Contract Sum. All contract changes will be processed following terms and conditions of contract.
1.6 PROJECT COMMUNICATION
A. Use CRM software for communication throughout contract period on:
1. Project directory
2. Project correspondence
3. Meeting agendas and minutes
4. Contract modifications forms and logs
5. RFI form and processing
6. Task and issue management
7. Photo documentation
8. Baseline schedule, schedule updates and calendar management
9. Submittal form and processing
10. Payment coordination documentation
11. Drawing and specification document hosting, viewing, and updating
12. Online document collaboration
13. Reminder and tracking functions
14. Archiving functions
15. Notification of submittal and RFI statuses and current responsible party
16. Permits and addendums
B. Some documents are not suitable to be shared using the CRM software. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using CRM software and shall be coordinated with Project team as appropriate.
C. Submit to Contracting Officer a list of employees who will need access to the website. Users will receive an invitation to register from Department of Interior (DOI). Once registered on DOI website, user will be given access to CRM software.
D. All users will be required to have the following software packages:
1. Internet Explorer version 11 or later.
2. Adobe Acrobat Professional (Pro) version 11 or later.
1.7 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. Meeting agenda will include the following as a minimum:
1. Roles & Responsibilities / Lines of Authority
2. Park rules and regulations
3. Jobsite Safety
4. Resolution of comments on required Division 1 documents
YELL – 307127 01 31 00 - 6
5. Coordination of Subcontractors
6. Labor law application
7. Modifications
8. Payments to Contractor
9. Payroll reports
10. Contract time
11. Liquidated damages
12. Contractor Performance Evaluation
13. Display of Hotline posters
14. Notice to proceed
15. Correspondence procedures
16. CRM software
17. Acceptance/rejection of work
18. Progress meetings
19. Submittal procedures
20. NPS Final Accessibility Inspection
21. Environmental requirements
22. Permit requirements
23. As-constructed drawings/operation and maintenance (O&M) manuals.
24. Saturday, Sunday, holiday and night work.
25. Reference materials
26. Value engineering
27. Schedule of Values
B. Progress Meetings: Contracting Officer will schedule weekly meetings with Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:
a. Approval of minutes of previous meetings
b. Submittal status
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)
h. Construction Schedule update (provide updated Critical Path Method (CPM)).
i. Status of Project Record Drawings and O&M manuals.
j. Other business relating to work.
k. Permit requirements
C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.
YELL – 307127 01 31 00 - 7
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting. Advise Contracting Officer of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:
a. Contract Documents
b. Options
c. Related RFIs
d. Related Change Orders
e. Purchases
f. Deliveries
g. Submittals
h. Review of mockups
i. Possible conflicts
j. Compatibility requirements
k. Time schedules
l. Weather limitations
m. Manufacturer's written instructions
n. Warranty requirements
o. Compatibility of materials
p. Acceptability of substrates
q. Temporary facilities and controls
r. Space and access limitations
s. Regulations of agency(ies) with jurisdiction
t. Testing and inspecting requirements
u. Installation procedures
v. Coordination with other work
w. Required performance results
x. Protection of adjacent work
y. Protection of construction and personnel
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.
1.8 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate on-site party responsible for overseeing Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project; familiar with environmental
YELL – 307127 01 31 00 - 8
regulations applicable to construction operations; demonstrated experience with local, municipal, and state regulatory requirements.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of Waste Management Plan (WMP).
c. Implementation of Indoor Air Quality (IAQ) Management Plan.
d. Implementation of Storm Water Pollution Prevention Plan (SWPPP).
e. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.
f. Training for Contractor personnel in accordance with position requirements.
g. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements
2. Regulatory Requirements
3. Indoor Air Quality (IAQ) Management
4. Noise and Acoustics Management
5. Temporary Storm Water Pollution Prevention Environmental Management
6. Construction Waste Management
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on project site. Training shall include:
1. Overview of environmental issues related to building industry.
2. Overview of environmental issues related to Project.
3. Review of site-specific procedures and management plans:
a. Construction Waste Management
b. Indoor Air Quality (IAQ) Management
c. Noise and Acoustics Management
d. Temporary Storm Water Pollution Prevention
4. Pollution Prevention (P2) practices: Submit evidence of
a. Soil remediation
b. Hazardous materials
c. Individual developing plans
5. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Contractor 40 CFR (Code of Federal Regulations) employee training records upon request of Contracting Officer.
D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, IAQ Management Plan, and Storm Water Pollution Prevention Plan.
YELL – 307127 01 31 00 - 9
1.9 PERMITS
A. General:
1. Permits and Responsibilities: Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying…