This is a Price Breakout spreadsheet for the Bureau of Land Management Shoshone Field Office Replacement project, detailing a comprehensive construction project with both base and optional line items. The base schedule includes 13 line items covering critical construction phases such as mobilization, site preparation, erosion control, demolition, excavation, structural fill, field office construction, site utilities, landscaping, exterior concrete work, pavements, and fencing, with each line item currently showing zero cost.

The optional schedule provides additional construction elements including pavement and striping, gravel driving surface, landscaping enhancements, a pre-engineered steel structure (cabana), light poles, and casework. The project is associated with Solicitation Number 140L0625R0002 for the Shoshone Wildland Fire Operations and Field Office, under the Department of the Interior Bureau of Land Management National Office. The price breakout document appears to be a template or draft pricing document, with placeholder line items awaiting specific cost inputs for the construction project.

View the file

Other files

File Type Posted
Sol_140L0625R0002_Amd_0008.pdf PDF
B08_Attachment_19_Revised_Final_Specifications_8-7-25_0007.pdf PDF
B08_Attachment_20C_Revised_Final_Drawings_20250804_Part3_0007.pdf PDF
B08_Attachment_20D_Revised_Final_Drawings_20250804_Part4_0007.pdf PDF
B08_Attachment_20A_Revised_Final_Drawings_20250804_Part1_0007.pdf PDF
B08_Attachment_20E_Revised_Final_Drawings_20250804_Part5_0007.pdf PDF
B08_Attachment_20B_Revised_Final_Drawings_20250804_Part2_0007.pdf PDF
Sol_140L0625R0002_Amd_0007.pdf PDF
B08_Attachment_18_Q_A_4_25R0002_0007.pdf PDF
Sol_140L0625R0002_Amd_0006.pdf PDF
B08_Attachment_17_J_A_140L0625R0002_0005.pdf PDF
Sol_140L0625R0002_Amd_0005.pdf PDF
B08_Attachment_16_Q_A_3__25R0002_0004.pdf PDF
Sol_140L0625R0002_Amd_0004.pdf PDF
Sol_140L0625R0002_Amd_0003.pdf PDF
B08_Attachment_15_Past_Perf_Questionnaire_UPDATED_0002.docx DOCX document
B08_Attachment_14_Q_A_2__25R0002_0002.docx DOCX document
Sol_140L0625R0002_Amd_0002.pdf PDF
B08_Attachment_12_Q_A_1_0001.pdf PDF
B08_Attachment_13_Site_Visit_Sign-In_Sheet_0001.pdf PDF
Sol_140L0625R0002_Amd_0001.pdf PDF
B08_Attachment_1B_Shoshone_Drawings_8-14.pdf PDF
B08_Attachment_2B_Revised_Specs_012000_Nov2024.pdf PDF
B08_Attachment_9_Wage_Determination.pdf PDF
B08_Attachment_8_Limitations_on_SubK_Breakout.xlsx XLSX spreadsheet
B08_Attachment_1D_Shoshone_Drawings_59-111.pdf PDF
B08_Attachment_1C_Shoshone_Drawings_15-58.pdf PDF
B08_Attachment_1E_Shoshone_Drawings_112-124.pdf PDF
Sol_140L0625R0002.pdf PDF
B08_Attachment_1A_Shoshone_Drawings_1-7.pdf PDF
B08_Attachment_4_Geotech_Report.pdf PDF
B08_Attachment_7_ACM_Report.pdf PDF
B08_Attachment_5_Clarifications.pdf PDF
B08_Attachment_6_Idaho_Lead-Based_Paint_Debris_Fact_Sheet.pdf PDF
B08_Attachment_11_SF1442_Completion_Instructions.pdf PDF
B08_Attachment_10_Past_Perf_Questionnaire.docx DOCX document
B08_Attachment_2A_Specifications.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Price Breakout

Bureau of Land Management
Shoshone Field Office Replacement
Price Breakout
BASE SCHEDULE
Line Item No.DescriptionEstimated QuantityUnitUnit CostTotal
BUILDING:
1Mobilization & Construction Management1LS$ - 0
2Erosion Control and Storm Water Pollution Prevention1LS$ - 0
3Construction Staking1LS$ - 0
4Select Demolition1LS$ - 0
5Site Clearing and Grubbing, Excavation, and Preparation1LS$ - 0
6Site Rock Removal60BCY$ - 0
7Structural Fill1LS$ - 0
8Field Office Construction1LS$ - 0
9Site Utilities - Excluding Irrigation1LS$ - 0
10Landscaping - Irrigation Only1LS$ - 0
11Exterior Concrete Work (e.g. walkways, bollards, curbs, and gutters)1LS$ - 0
12Pavements - Excluding SCHEDULE A1LS$ - 0
13Fences and Gates1LS$ - 0
Total Base Schedule$ - 0
OPTIONAL ITEMS:
O1SCHEDULE A - Pavement and Striping1LS$ - 0
O2Gravel Driving Surface - Wareyard1LS$ - 0
O3Landscaping - Planting, Pavers, Site Furnishing, and Receptacles1LS$ - 0
O4Pre-Engineered Steel Structure (Cabana) and Foundation2EA$ - 0
O5Light Poles and Luminaires1LS$ - 0
O6Casework1LS$ - 0
Total Optional Schedule$ - 0