This document is a project manual (Division 01 specifications) for the Death Valley National Park project to rehabilitate water and wastewater systems at Furnace Creek and Cow Creek areas. The project involves comprehensive infrastructure improvements, including constructing new and rehabilitating existing water treatment facilities, wastewater systems, lift stations, and associated infrastructure across multiple project sites. Key components include building new Reverse Osmosis (RO) treatment buildings, upgrading lagoon systems, replacing water and wastewater piping, installing new generators and SCADA systems, and performing site improvements.

The project is structured with a base contract and nine optional elements, allowing flexibility in project scope. The base contract covers extensive work at both Furnace Creek and Cow Creek areas, encompassing demolition, new construction, piping installation (both trench and directional drilling), system upgrades, and site restoration. Optional elements include additional water and wastewater piping in campground areas, water reservoir improvements, and specific site-specific infrastructure enhancements. The work will be performed under a single prime contract, with careful considerations for environmental protection, wildlife preservation, and minimal disruption to park operations, particularly around campground areas.

View the file

Other files

File Type Posted
B09_Amd11_-_B08_Attach3_-_WD_CA20260020_Mod2_0011.pdf PDF
B09_Amd10_-_QR55_Attach_Drawing_00-C8_27_Jan2026_0010.pdf PDF
B09_Amd10_-_QR55_Attach_Drawing_01-C4_38_Jan2026_0010.pdf PDF
B09_Amd10_-_QR55_Attach_Drawing_01-C4_42_Jan2026_0010.pdf PDF
Sol_140P2025R0082_Amd_0009.pdf PDF
B09_Amd8_-_Spec_33_11_13_-_POTABLE_WATER_SUPPLY_WELLS_0008.pdf PDF
B09_Amd8_-_Spec_08_33_22_-_ALUMINUM_ROLLING_OVERHEAD_DOORS_0008.pdf PDF
B09_Amd8_-_Spec_46_33_11_-_CHEMICAL_FEED_-_LIQUID_SYSTEMS_0008.pdf PDF
B09_Amd8_-_Drawing_02-X1_1_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_02-C7_5_Dec2025_0008.pdf PDF
B09_Amd8_-_Drawing_00-C_19_Dec2025_0008.pdf PDF
B09_Amd8_-_Drawing_00-C3_15_Dec2025_0008.pdf PDF
B09_Amd8_-_Drawing_00-C3_18_Dec2025_0008.pdf PDF
B09_Amd8_-_Drawing_00-G1_2_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_01-C1_22_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_01-C1_67_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_01-C4_42_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_02-C2_22_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_02-C6_7_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_02-X1_2_Jan2026_0008.pdf PDF
B09_Amd8_-_QR22_Attach_Drawing_02-C5_64_Jan2026_0008.pdf PDF
Sol_140P2025R0082_Amd_0008.pdf PDF
B09_Amd8_-_Spec_33_31_05_-_MANHOLE_LINING___REHABILITATION_0008.pdf PDF
B09_Amd8_-_Spec_33_31_11_-_GRAVITY_SEWER_PIPELINE___MANHOLE_INSTALLATION_0008.pdf PDF
B09_Amd8_-_Spec_33_32_00_-_WASTEWATER_PUMPING_STATIONS_0008.pdf PDF
B09_Amd8_-_Spec_43_41_43_-_POLYETHYLENE_CHEMICAL_TANKS_0008.pdf PDF
B09_Amd8_-_Drawing_02-C5_33_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_Coversheet_00_DEVA_318717_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_01-C4_38_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_00-C3_20_Dec2025_0008.pdf PDF
B09_Amd8_-_Drawing_01-C1_29_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_01-C1_31_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_01-C1_42_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_01-C3_1_Dec2025_0008.pdf PDF
B09_Amd8_-_Drawing_01-C3_3_Dec2025_0008.pdf PDF
B09_Amd8_-_Drawing_01-G1_15_Jan2026_0008.pdf PDF
B09_Amd6_-_QR_No36_Attach1_-_06_05_2023_DEVA_0006.pdf PDF
Sol_140P2025R0082_Amd_0006.pdf PDF
B09_Amd6_QR_Tracker_-_DEVA_318717_0006.xlsx XLSX spreadsheet
Sol_140P2025R0082_Amd_0004.pdf PDF
B09_Amd4_QR_Tracker_-_DEVA_318717_0004.xlsx XLSX spreadsheet
Sol_140P2025R0082_Amd_0003.pdf PDF
Sol_140P2025R0082_Amd_0002.pdf PDF
B09_Amd1_-_Brand_Name_J_A_DEVA_318717_Redacted_0001.pdf PDF
B09_Amd1_-_Construction_Admin_Camp_QA_(only)_DEVA_318717_0001.pdf PDF
B08_Attach3_-_WD_CA20250020_Mod15.pdf PDF
B08_Attach7_-_PPQ.docx DOCX document
B08_Attach8_-_General_References.doc DOC document
B08_Attach2b_-_Drawings_DEVA_318717_Jan2025.pdf PDF
B08_Solicitation_Body_-_v13_Sept2025_Final.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEATH VALLEY

NATIONAL PARK

REHABILITATE WATER AND WASTEWATER SYSTEMS AT FURNACE

CREEK AND COW CREEK AREAS

DEVA

PMIS NO. 318717

CONSTRUCTION DOCUMENTS

PROJECT MANUAL

DIVISION 1

NATIONAL PARK SERVICE

JANUARY 20242025

DEVA 318717 TOC-1

REHABILITATE WATER AND WASTEWATER SYSTEMS AT

FURNACE CREEK AND COW CREEK AREAS

JANUARY 2025

TABLE OF CONTENTS

DIVISION 01: GENERAL REQUIREMENTS

SECTION TITLE

00 01 07 SEALS AND SIGNATURES

01 11 00 SUMMARY OF WORK

01 26 01 CONTRACT MODIFICATION PROCEDURES

01 27 00 DEFINITION OF CONTRACT LINE ITEMS

01 31 00 PROJECT MANAGEMENT AND COORDINATION

01 32 16 CONSTRUCTION SCHEDULE

01 32 33 PHOTO DOCUMENTATION FOR HISTORIC PRESERVATION

01 33 23 SUBMITTAL PROCEDURES

01 35 05 ENVIRONMENTAL PROTECTION AND SPECIAL CONTROLS

01 35 13.22 ARCHAEOLOGICAL PROTECTION

01 35 23 SAFETY REQUIREMENTS

01 35 91 HISTORIC PRESERVATION TREATMENT PROCEDURES

01 40 00 QUALITY REQUIREMENTS

01 42 00 REFERENCE STANDARDS

01 50 00 TEMPORARY FACILITIES AND CONTROLS

01 57 19 NOISE AND ACOUSTICS MANAGEMENT

01 57 23 TEMPORARY STORM WATER POLLUTION PREVENTION

01 67 00 PRODUCT REQUIREMENTS

01 73 40 EXECUTION

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 77 00 CLOSEOUT PROCEDURES

01 78 23 OPERATION AND MAINTENANCE DATA

01 91 14 TOTAL BUILDING COMMISSIONING

DEVA – 318717 01 11 00 - 1

SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work phases.

3. Work under other contracts.

4. Government Furnished Materials.

5. Contractor use of premises.

6. Public use of site.

7. Occupancy requirements for buildings.

8. Work Restrictions.

9. Special Construction Requirements.

10. Soils Investigation Report.

11. Additional Reports.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Furnace Creek and Cow Creek areas within Death Valley National Park, California.

Three miles north of the Furnace Creek Visitor Center is the Cow Creek Service Road and Maintenance Facilities where the Contractor can meet with NPS Park staff.

B. The Work consists of the following:

1. Base Contract: The Work includes the following as shown:

a. Furnace Creek RO Building - Includes new restroom, HVAC system, building envelopes, chemical storage room, propane generator, minor upgrades to process/equipment, replace SCADA equipment, rewrite PLCs, rewrite HMIs, and new Starlink connection to master SCADA.

b. Furnace Creek Pipe Vault - Includes but not limited to, concrete patching, metal rehab, pipe and valve replacement.

c. Furnace Creek Lagoon & Headworks - Includes new lagoon cell, new headworks screen, new aerators, docks, power to lagoons, a new water line to lagoon, new meter and vault, new septage receiving pad.

d. Furnace Creek Sitework - Includes erosion repairs, grading and drainage improvements, and new fencing and gate in the Furnace Creek area.

e. Furnace Creek Demolition - Includes removing the existing lift station including asphalt, concrete, and gravel removal in the Furnace Creek area.

f. Furnace Creek Water – Piping in Trenches - Includes new water mains and service lines in Furnace Creek area via open trench excavation.

g. Furnace Creek Water – Directional Drilling – Includes new water mains and service lines in Furnace Creek area via horizontal directional drilling.

DEVA – 318717 01 11 00 - 2

h. Furnace Creek Water – Appurtenances - Includes valves, water meters, pipe fittings, and reinstalling existing fire hydrants in the Furnace Creek area.

i. Furnace Creek Wastewater – Piping in Trenches - Includes new wastewater piping and service lines installed by open trench excavation in the Furnace Creek area.

j. Furnace Creek Wastewater – CIPP - Includes pipe lining of existing mains and service lines in the Furnace Creek area.

k. Furnace Creek Wastewater – Appurtenances - Includes manholes, cleanouts, connections to existing lines in the Furnace Creek area.

l. Cow Creek RO Treatment Building - Includes new RO building, relocating air monitoring equipment, reusing treatment equipment, HVAC system, new restroom, new propane generator, and reuse SCADA equipment with new Starlink connection to master SCADA.

m. Cow Creek Lift Station - Includes new wet well, building, pumps, controls, electrical, HVAC system, new 15,000-gallon overflow tank, propane generator, and new SCADA equipment with PLCs, HMIs, and new radio connection to master SCADA.

n. Cow Creek Pool Filtration - Includes new building, moving the existing treatment equipment, new piping, electrical, and HVAC system, and new SCADA equipment with new radio connection to master SCADA.

o. Cow Creek Sitework - Includes repairing erosion areas in the Cow Creek area.

p. Cow Creek Demolition - Includes demolishing the existing lift station, RO building, and Coyote Loop lift station.

q. Cow Creek Water – Piping in Trenches - Includes new water mains and service lines in Cow Creek area via open trench excavation.

r. Cow Creek Water - Appurtenances - Includes valves, water meters, and pipe fittings in the Cow Creek area and work at Nevares Spring Well Site.

s. Cow Creek Wastewater – Piping in Trenches - Includes new wastewater mains and service lines installed by open trench excavation in the Cow Creek area.

t. Cow Creek Wastewater – CIPP - Includes pipe lining of existing mains and service lines in the Cow Creek area.

u. Cow Creek Wastewater - Appurtenances – Includes manholes, cleanouts, connections to existing lines in the Cow Creek area.

v. Coyote Loop Wastewater Gravity Line – Includes wastewater mains and services, pipe lining and appurtenances in the Coyote Loop area of Cow Creek.

w. Texas Springs Drainage Channel - Includes constructing a drainage channel at the

Texas Springs Campground.

x. Furnace Creek Water Piping at CA 190 - Includes water piping and appurtenances along CA 190.

y. Old Ghost Road Wastewater - Includes wastewater mains and services, pipe lining and appurtenances along Old Ghost Road at Cow Creek.

z. Wastewater Force Main from Cow Creek Lift Station to Furnace Creek System at

Highway 190 - Includes force main replacement and appurtenances for pressure sewer line along CA 190 from Cow Creek lift station to Furnace Creek Wastewater at Furnace Creek Campground.

aa. Wastewater at Furnace Creek CG – Includes wastewater mains and services and appurtenances in Furnace Creek Campground.

2. Options: The work includes the following as shown:

a. OPTION A – Cow Creek Water Piping Coyote Loop – Includes water main and service piping and appurtenances in the Coyote Loop area at Cow Creek.

DEVA – 318717 01 11 00 - 3

b. OPTION B – Furnace Creek Water Piping Furnace Creek CG– Includes water main and service piping and appurtenances in Furnace Creek Campground.

c. OPTION C – Furnace Creek Water Piping RO to Texas Springs CG – Includes water main and service piping and appurtenances from the RO Building to the Texas Springs Campground.

d. OPTION D – Wastewater from Cow Creek RO Building to Upper Housing - Includes wastewater main from Cow Creek RO Building to the Upper Housing area.

e. OPTION E - Furnace Creek Wastewater Piping Sunset CG - Includes wastewater main replacement, pipe lining, and appurtenances for sewer lines in the Sunset Campground.

f. OPTION F - Furnace Creek Water Piping Sunset CG – Includes water main and service piping and appurtenances in Sunset Campground.

g. OPTION G - Furnace Creek Water Piping FC Wells to RO Plant – Includes water main and service piping and appurtenances extending from wells to the RO Building.

h. OPTION H - Water Reservoir Improvements – At Furnace Creek, includes replacing hatch and internal stairs, and at both sites includes new security fencing.

i. OPTION I – Cow Creek Wastewater at Cow Creek Administration – Includes wastewater main and service piping, pipe lining and appurtenances for the Cow Creek Administration and Maintenance area.

C. Project will be constructed under a single prime contract.

1.3 WORK UNDER OTHER CONTRACTS

A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.

B. Concurrent Work: Government has awarded separate contract(s) for the following construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract.

1. FY26 - Rehabilitate, Reconfigure, and Upgrade Mission 66 Homes in Death Valley - PMIS 343688.

a. This project would rehabilitate 24 facilities, including 22 in the Cow Creek housing area. The project would include work on sewer laterals on Skyline and Old Ghost Roads. It would increase flow into sewers upon completion of the project and compete for laydown space during construction

2. Caltrans Bike Path Construction Project

C. Future Work: Government may award separate contract(s) for the following additional work to be performed at site after Substantial Completion. Completion of that work will depend on successful completion of preparatory work under this Contract.

1. N/A

1.4 CONTRACTOR USE OF SITE

A. General: Contractor shall have full use of the areas designated in the Plans for construction operations during the construction period. Contractor's use of designated areas is limited by the Government's

DEVA – 318717 01 11 00 - 4

right to maintain public access, provide public safety, and perform work or to retain other contractors on portions of Project.

1. Limits: Confine construction operations to the disturbance limits as indicated on the construction drawings.

B. Campground Closures

1. The Contractor shall not close more than one campground at one time.

2. Furnace Creek Campground closure requires a minimum of six (6) months notice due to reservation schedules, with group site reservations extending up to one (1) year in advance.

Thirty (30) days notice for the first come first serve campgrounds during the traditional camping season, defined as October 15th through April 15th. This includes Texas Spring and Sunset Campground.

3. The Contractor shall coordinate with the Owner to manage visitor impacts during closures, including reallocating staffing to accommodate increased visitor activity in alternate campgrounds.

4. For partial closures, portable restrooms and handwashing stations shall be provided if services are interrupted. Potable water is not required unless service outages exceed one (1) week, in which case water buffaloes may be provided.

5. Furnace Creek Campground:

a. Complete closures are preferred; however, partial closures of southern sites: loop 56 through 114 and loop 115 through 150 may be allowed based on construction needs.

Each loop may be closed separately or together.

b. Construction must adhere to campground quiet hours.

c. Full closures, if required, are preferred at the start of the operating season (October

15 to April 15).

6. Texas Springs Campground:

a. Full closures are preferred early in the season.

b. Partial closures may be implemented, keeping certain areas open while work continues in other sections.

c. Erosion control work may allow partial closures and should be coordinated with water and sewer construction to avoid simultaneous service disruptions.

7. Sunset Campground:

a. Closures should avoid the period of October 15 to December 30 due to scheduled events.

b. Closures are recommended after President’s Day, when visitor numbers decrease.

C. Storage of Materials: Confine storage of materials to the designated staging areas. Staging Plan to be submitted for storage area if multiple projects overlap.

D. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with

Contracting Officer and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

DEVA – 318717 01 11 00 - 5

6. The Furnace Creek Inn is located in the Death Valley Historic District, listed on the National Register of Historic Places. The Inn is also considered a cultural landscape with character defining features. The utmost care and craftsmanship must be employed when impacting any character defining elements as a result of the Work. All work must be conducted in accordance with the Secretary of the Interior's Standards for the Rehabilitation.

7. Work will be occurring in close proximity to the historic inn. The contractor shall work with the park representative to field identify and mark the extent of features that exist within the limits, or in proximity of the work. The areas will include a buffer zone to ensure maximum protection of the feature.

8. All workers will be provided with a site orientation that identifies the historic and cultural resources prior to commencing work.

9. No work permitted in the Nevares springs area between March and October for bighorn sheep lambing season.

E. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government's employees, the public and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

F. Construction Camp: Establishment of a camp will not be permitted. Nearest lodging options are in Furnace Creek Ranch, Furnace Creek Inn, Beatty, Nevada and Pahrump, Nevada.

G. Road Closures: contractor to consult NPS Death Valley Alerts and Conditions website for information on any road closures.

1. https://www.nps.gov/deva/planyourvisit/conditions.htm#:~:text=Updated%209/21/2024% 2010:16%20am%20PDT.%20Road%20Status.%20%E2%80%94%20Open%20Roads.#:~ :text=Updated%209/21/2024%2010:16%20am%20PDT.%20Road%20Status.%20%E2%8 0%94%20Open%20Roads.

H. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on Park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

All trucks and equipment must have invasive species inspections performed upon entering the Park scheduled 7 days prior to arrival on site.

1. Heavy equipment access should be carefully considered and all loads entering and exiting the Park shall be covered to ensure wildlife and visitor safety.

1.5 PUBLIC USE OF SITE

A. The Cow Creek area is closed to the public. However, there are many Park employees and employees of Park partner groups that frequent the area for work and access their residences. The Furnace Creek area is open to the public during construction.

https://www.nps.gov/deva/planyourvisit/conditions.htm https://www.nps.gov/deva/planyourvisit/conditions.htm https://www.nps.gov/deva/planyourvisit/conditions.htm https://www.nps.gov/deva/planyourvisit/conditions.htm

DEVA – 318717 01 11 00 - 6

B. Signage and barricade may be necessary to detour and provide safety to visitors and Park staff and is required to be included as part of the approved traffic control plan.

1.6 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Partial Government Occupancy: Government will occupy some of the existing buildings adjacent to the water/wastewater/site work construction area. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage.

Perform the Work so as not to interfere with Government’s operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).

1.7 CONDUCT OF OPERATIONS

A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.8 WORK RESTRICTIONS

A. Contractor working hours shall generally be limited to 6:00 a.m. to 6:00 p.m., Monday through Friday, excluding federal holidays and any single workday between a holiday and a weekend (e.g., the Friday after Thanksgiving). Exceptions are noted as follows:

1. Maintenance Business Hours: Maintenance hours are Monday through Thursday, 6:00 a.m.

to 4:30 p.m. The Contractor shall schedule all meetings, deliveries, inspections, hot work, non-routine work, or other work requiring the presence of Park staff during these hours.

2. Housing Area Working Hours: In housing areas, Contractor working hours shall be limited to 8:00 a.m. to 5:30 p.m.

3. Weekend and Holiday Hours: Weekend and holiday work may not be performed without prior consent from the Contracting Officer (CO). Submit requests a minimum of 48 hours in advance for CO approval.

4. Early Morning and Evening Hours: Work outside standard hours will be allowed only with prior approval of the CO. Submit requests a minimum of 48 hours in advance for CO approval.

DEVA – 318717 01 11 00 - 7

5. Night Work: Night work will not be permitted in Park staff housing or public areas. Any night work in more remote areas must be approved by the CO. Submit requests a minimum of 48 hours in advance for CO approval.

6. Noise-Intensive Activities: Activities such as rock screening, crushing, and similar operations shall be coordinated with the CO at least 72 hours in advance.

7. Quiet Hours and Conflicts: Where working or quiet hours are specified in the specifications or Park policies, the Contractor shall honor the more stringent hours.

B. Existing Utilities

1. Existing Utilities

a. Notify Contracting Officer and utility companies of proposed locations and times for excavation.

b. Contractor shall notify CO about any unforeseen conditions and damage of unknown utilities.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, Contractor shall notify CO and get authorization prior to repairing utility. An equitable adjustment will be made in accordance with the Changes clause of the Contract.

4. Any disruption to operations or utilities at Xanterra Properties, and other entities will be coordinated with the Park liaison and Park's tribal liaison at least three weeks in advanced.

Service interruptions and tie ins could potentially occur during off-peak times or at night to minimize inconvenience. This includes work around the Inn, the Ranch, Timbisha Village utilities and access road, the school, Caltrans, the History Association, the airport, and any other entities. Coordination with the park's Tribal Liaison will occur for any planned work affecting the tribe. Impacts to schedule and cost are anticipated to be slight since there are work arounds

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than two (2) days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. Hours for Utility Shutdowns: The time and duration of the temporary utility outage must be approved in writing by the Contracting Officer or their representative.

D. Blasting: No blasting in the park will be allowed as part of this contract.

E. Migratory Bird Treaty Act (MBTA) Protected Species:

1. Recommendations and training would be provided to construction contractors working on-site to prevent and mitigate any potential harm and to protect resident and migratory nesting bird species.

2. To the extent practicable, vegetation removal or modification would be done outside of the nesting season (January–July). Pre-construction surveys for active migratory bird nests would be conducted by an authorized biologist within the Nevares Springs and lagoon areas at least 2 weeks prior to any construction activities occurring within the nesting season.

DEVA – 318717 01 11 00 - 8

The survey area would encompass the species-specific buffers listed within the table below.

If an active migratory bird nest is discovered within the survey area during the nesting season (January–July), a buffer prohibiting ground-disturbing construction using equipment that produces noise ≥ 85 dB at 17 m and any vegetation removal or modification would be implemented following nest buffer guidelines provided by the USFWS and other scientific literature and listed by species in the table below. If buffers cannot be implemented, noise abatement methods may be utilized to further reduce potential impacts to nesting birds. If an active nest buffer is unknown, a qualified biologist would determine an appropriate buffer distance.

Common Name Scientific Name Active Nest Buffer (feet)

Nesting Habitat Description within Analysis Area

Lucy's Warbler Leiothlypis luciae 1501 tree cavities, partial crevices in tree bark or banks

Black-chinned Sparrow

Spizella atrogularis 150 understory/thickets

Le Conte's Thrashe Toxostoma lecontei 150 trees/shrubs, open scrub Costa's Hummingbird Calypte costae 100 trees/shrubs

1. Nest buffer corresponds with distances applied for other tree-nesting passerines provided by USFWS (Pacific Gas and Electric Company 2015; USFWS and NPS 2023)

F. Nonsmoking: Smoking is not permitted or within 25 feet of building entrances, operable windows, or outdoor air intakes.

G. Open Trenches:

1. Open Trench Protection and request that the contractor check the cuts for wildlife and then cover the trenches at the end each workday to prevent wildlife entrapment.

2. The length of trench permitted to be open at any time would be limited when, in the opinion of the DEVA project manager, such limitation would be necessary for public safety, and would be less than 400 feet.

3. All trenches and excavations left open overnight would be protected with fencing, concrete barriers, signage, or any other measures required to protect public safety.

H. Desert Tortoise Protection:

1. Exercise utmost care to prevent injury or death to desert tortoises, a threatened species protected by law. This reptile is susceptible to crushing by automobile or foot traffic. It is illegal to disturb a tortoise or its habitat in any way. Vehicle parking must occur on previously disturbed areas. All tortoise injuries must be reported to the Park as soon as possible.

1.9 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Construction Software: A project construction software administered by the NPS using Project Team, will be used for purposes of managing communication and documents during the construction stage.

1. Project Team software will be used for the following functions:

a. Project directory.

b. Project correspondence.

c. Meeting agendas and minutes.

d. Contract modifications forms and logs.

DEVA – 318717 01 11 00 - 9

e. RFI form and processing.

f. Task and issue management.

g. Photo documentation.

h. Baseline schedule, schedule updates and calendar management.

i. Submittal form and processing.

j. Drawing and specification document hosting, viewing, and updating.

k. Online document collaboration.

l. Reminder and tracking functions.

m. Archiving functions.

n. Notification of submittal and RFI statuses and current responsible party.

o. Permits and addendums

2. See Section 01 31 00 for additional requirements about construction coordination, submittals, RFIs, and project meetings

B. Hazardous Material:

1. Hazardous material is not anticipated, but if encountered, hazardous materials are to be removed and disposed of in accordance with state and local requirements. According to the Great Basin Unified Air Pollution Control District, a written form/notification of demolition is required prior to removal operations. The company filing the form/notification must be registered with Cal/OSHA to perform asbestos-related work in California and is subject to the requirements of the National Emission Standards for Hazardous Air Pollutants.

Materials will be removed, bagged, and disposed of at the US Ecology facility in Beatty, Nevada.

2. A hazardous spill plan shall be developed, detailing actions to be taken in the event of a spill, notification procedures, and preventive measures. Preventive measures include proper placement of refueling facilities, storage, and handling of hazardous materials.

3. A spill prevention and pollution control program shall be implemented, including procedures for hazardous material storage and handling, spill containment, cleanup, and reporting. Refueling and other hazardous activities shall be restricted to designated, non-sensitive areas.

4. All leaks, spills, or releases of fuel, transmission fluid, brake fluid, or other hazardous materials must be reported immediately to the designated safety officer. The contractor is responsible for spill material removal and disposal at an approved off-site landfill and shall notify the appropriate federal agency if required.

5. Fueling of vehicles and equipment shall occur away from water sources. A contingency plan for controlling petroleum product spills during the project shall be developed, and absorbent pads and containment booms shall be stored on-site for spill response.

6. Any spills of hazardous materials or fuel must be cleaned up immediately to prevent contamination of ground or surface waters. Construction equipment shall be regularly inspected for leaks of fuel, lubricants, and other chemicals.

C. Other special construction requirements may be located within the Division 2-49 Specifications, or the construction drawings.

D. Structural Special Instructions

1. Special inspection and structural observation requirements that are listed here are not intended to conflict with CH. 17 of the IBC.

2. Special inspections are required for concrete and wood construction as defined in IBC section 1705.

3. Continuous and periodic special inspections to follow IBC 1705 & CH. 17.

DEVA – 318717 01 11 00 - 10

4. The contractor shall employ a third party registered design professional to perform structural observations in structures assigned to SDC D, E, or F when one of the conditions of section

1704.6.1 & 2 of the IBC are met.

5. The contractor shall notify the structural observer 48 hours in advance of required structural observations for scheduling purposes. Failure by the contractor to comply, may result in removal of any subsequent work for observation.

6. Field testing of concrete is required.

7. A statement of structural tests and inspections is included in the construction documents.

1.10 SOILS INVESTIGATION REPORTS

A. Refer to Section 02 06 13 – Geotechnical Report

1.11 ADDITIONAL REPORTS

A. Sanitary Sewer CCTV Inspection Reports

B. A copy of these reports are available to all plan holders with this package upon request.

C. If conflicts occur between the report and Drawings or Specifications, the Drawings and Specifications govern.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

DEVA – 318717 01 11 00 - 11

This page was intentionally left blank

DEVA – 318717 01 26 01 - 1

CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager, Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

DEVA – 318717 01 26 01 - 2

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:

1) Social Security

2) Medicare

3) Workers Compensation– Policy and company calculation to be made available.

4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.

5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.

DEVA – 318717 01 26 01 - 3

6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.

Contractor may utilize the government provided Contractor Estimate Form, (https://www.nps.gov/dscw/upload/PayEstimateForm_withSample_7-27-17.xlsx) or http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank

DEVA – 318717 01 26 01 - 4

their own form, provided that it contains the same information and level of detail as the Gov’t provided form.

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.

Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.

Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

DEVA – 318717 01 26 01 - 5

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.

Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10% Profit………………….8.00%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

DEVA – 318717 01 26 01 - 6

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 01 26 01

DEVA – 318717 01 27 00 - 1

DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

C. Incidentals on this project include, but are not limited to, mobilization/demobilization, traffic control, training, commissioning and start-up, removal and disposal of hazardous materials encountered, trenching in “hard dig” areas, and discovering and handling unexpected archaeological/cultural artifacts encountered.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item No. 1 - Furnace Creek RO Building

1. This item consists of rehabilitating the existing RO water treatment building at Furnace

Creek including, but not limited to, sitework, new building envelope improvements, new building interior improvements, new HVAC system, upgrades to processing equipment and piping including removing chemical storage tanks/piping and replace with sodium hypochlorite generation skid, new onsite generator and propane tank on concrete pads, new electrical extensions, lighting, and appurtenances, new water and sanitary waste piping, and upgrades to the SCADA system.

2. Measurement for payment will be on a lump sum basis as a single item of work.

3. Payment will be made at the contract lump sum price.

B. Contract Line Item No. 2 - Furnace Creek Pipe Vault

1. This item consists of rehabilitating the Furnace Creek Pipe Vault including, but not limited to, new concrete walls, replacing interior framing and adding new deck with concrete topping, improving the steel flooring, improving interior piping/plumbing, appurtenances, and SCADA; adding an HVAC system, and improving electrical and lighting.

DEVA – 318717 01 27 00 - 2

C. Contract Line Item No. 3 - Furnace Creek Lagoon & Headworks

1. This item consists of rehabilitating the Furnace Creek lagoon system including, but not limited to: (1) Extending power to the lagoon system; (2) Installing floating docks with concrete pier and walkway in each lagoon; (3) Installing an electric distribution panel structure with sunshade structure; (4) Installing an in-channel mechanical screen system and sunshade structure; (5) Installing mechanical surface aerators; (6) Increasing berm height and armoring the final lagoon cell embankments; (7) Constructing a flow metering manhole; (8) Installing a sewage dump station with a bar screen; (9) Installing a new water service to headworks and new ground monitoring wells.

D. Contract Line Item No. 4 - Furnace Creek Sitework

1. This item consists of site/civil-related sitework at Furnace Creek including, but not limited to, installing a new gate and fencing around the perimeter of the RO Plant and water storage tank, replacing existing water towers, installing new groundwater monitoring wells, fortifying existing “low spots” along the access road to prevent erosion, installing rip-rap around Furnace Creek wells, improving storm drainage management using a culvert and rip-rap-lined channels, improving earthwork grading by cutting, filling, and blending; and installing new rip-rap blankets near pipe discharge locations (e.g. water tank drain line).

E. Contract Line Item No. 5 - Furnace Creek Demolition

1. This item consists of the demolition of the existing sewage pump station in the Furnace

Creek Campground, including, but not limited to: (1) Removing the existing wet well, filling the wet well, pumps, controls, control roof, and fencing; (2) Restoring the site to a natural condition; (3) Demolition and removal of the grease trap at the HQ/VC; (4) Removal of all existing above-ground RPZs (with all locations to be called out); (5) Removal of all existing PRVs (with all locations to be called out); (6) Demolition of the existing lift station in the Furnace Creek Campground area.

F. Contract Line Item No. 6 - Furnace Creek – Water Systems

1. Generally, this item includes piping in trenches, directional drilling, new water piping along

CA 190, and appurtenances related to the water systems at Furnace Creek. More specifically, this item includes, but is not limit to, (1) installing new HDPE water distribution piping in the Furnace Creek area via open trench excavation and horizontal directional drilling; (2) replacing and connecting water service piping. The work includes, but is not limited to, trench excavation; access and receiving pit excavation, bedding; pipe;

DEVA – 318717 01 27 00 - 3

warning tape; tracer wire; backfill; compaction and compaction testing; surface restoration;

asphalt and concrete patching; cleaning and testing; and loading and hauling excess spoil material off-site.

2. Installing new water system appurtenances includes, but is not limited to the following: (1) gate valves and boxes; (2) pipe fittings; (3) air/vacuum valves and boxes; (4) resetting fire hydrants; (5) ties into existing piping system; (6) pressure reducing valves (PRVs); (7) transition devices; (8) strainers; (9) combination air and vacuum valves; (10) duckbill check valves; (11) reduced pressure principle (RPZ) backflow preventers; (12) pipe adapters; (13) pipe couplings; (14) flange connections; and (15) pipe supports.

3. Measurement for payment will be on a lump sum basis as a single item of work.

4. Payment will be made at the contract lump sum price.

G. Contract Line Item No. 7 - Furnace Creek – Wastewater Systems

1. This item includes, but is not limited to, (1) installing new PVC wastewater collection and service piping in the Furnace Creek area via open trench excavation; (2) installing new cured-in-place piping (CIPP) piping (trenchless). The work includes, but is not limited to, trench excavation; excavation of access pits; cleaning; CCTV inspection; liner installation;

curing; bedding; pipe; warning tape; tracer wire; concrete encasement; backfill; compaction and compaction testing; surface restoration; cleaning and testing; and loading and hauling excess spoil material off-site.

2. Installing new wastewater system appurtenances includes, but is not limited to the following: removing existing manholes; rehabilitating existing manholes; installing new concrete manholes; cleanouts; fittings; and all other wastewater system appurtenances.

H. Contract Line Item No. 8 - Cow Creek RO Treatment Building

1. This item includes, but not limited to, constructing a new water treatment building at Cow

Creek to replace the existing building. The work includes, but is not limited to, site clearing, demolishing & removing existing RO building elements, foundation, walls, roof, exterior and interior building envelope, doors and windows, interior and exterior finishes, new

HVAC system, new onsite generator and propane tank on concrete pads, new electrical extensions, lighting, and appurtenances, new SCADA system, communication tower, reusing existing RO treatment unit, new sodium hypochlorite generation skid, plumbing, pump, process piping, domestic water connection and distribution, sanitary waste connection and distribution, and loading and hauling excess spoil material off-site.

DEVA – 318717 01 27 00 - 4

I. Contract Line Item No. 9 - Cow Creek Lift Station

1. This item includes, but not limited to, constructing a new sewage lift station at Cow Creek to replace the existing lift station. The work includes, but is not limited to, foundation, walls, roof, exterior and interior building envelope, doors and windows, interior and exterior finishes, new HVAC system, new onsite generator and propane tank on concrete pads, new wet well and sewage pumps, new electrical extensions, lighting, and appurtenances, upgrades to the SCADA system, plumbing, process piping, domestic water distribution, sanitary waste distribution, and loading and hauling excess spoil material off-site.

J. Contract Line Item No. 10 - Cow Creek Pool Filtration

1. This item includes, but not limited to, constructing a new Pool Filtration building at Cow

Creek. The work includes, but is not limited to, foundation, walls, roof, exterior and interior building envelope, doors and windows, interior and exterior finishes, HVAC system, pool treatment equipment, domestic water connection and distribution, sanitary waste connection and distribution, storm drainage, concrete paving at entrance, electrical, controls, demolishing the existing building, loading and hauling excess spoil material off-site, and restoration of site.

K. Contract Line Item No. 11 - Cow Creek Sitework

1. This item includes, but not limited to, site improvements for the Cow Creek Reverse

Osmosis Plant, Pool Filtration Building, and the Cow Creek housing area. Improvements at the Plant include all labor, material, equipment, and incidentals for installing a new chain-link fence with…