B08_Attach_16_NPS_Constructability_Checklist_DRAFT.xlsx
XLSX spreadsheet 32 KB Posted
- Attached to
- GATE 225953 - Rehab Well No. 4 Sandy Hook NJ
- Solicitation number
- 140P2022R0044
About this file
This document is a constructability checklist for a federal design-build project to replace an existing water well at Sandy Hook Park in New Jersey. The project involves permitting and construction of a new water well, procurement of an emergency generator, and related equipment. Key details include a recommended 18-month contract performance period to accommodate design, permitting for the well and generator, equipment purchasing, well drilling, construction, testing, startup and commissioning. The solicitation is issued by the National Park Service Gateway National Recreation Area for well replacement and upgrades at Sandy Hook Park in New Jersey, under solicitation number 140P2022R0044. The checklist identifies various project requirements and considerations for permitting, site access, staging, submittals, demolition, construction and closeout to ensure they are addressed in the contract documents.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Template
| NPS Constructability Checklist | ||||
| National Park Service (NPS) - Denver Service Center (DSC) | 3-20-18 | ||||
| For instructions, see Instructions tab below. | ||||
| Date: | 22-Feb-22 | Project Title: | Replace Water Well No. 4 at Sandy Hook | |
| Park: | GATE | Completed By: | Vik Desai/Ed Whatley | |
| PMIS: | 225953 | DBB or DB: | DB | |
| Item Number | Project Issues | SD Comments | ||
| Schematic Design | DD or RFP Comments |
Design Development (DBB) OR Request for Proposal (DB) CD or RFP Resolution Construction Documents (DBB) OR Request for Proposal (RFP)
| PROJECT INTRODUCTION | |||
| 1 | ANY NON-TYPICAL CONTRACT LINE ITEMS OR MISCELLANEOUS CONTRACT CONCERNS | The well construction is non-typical and will require permitting and close coordination with NJDEP during test well drilling, production well drilling and water quality testing. | |
| 2 | RECOMMENDED CONTRACT LENGTH; SEASONAL BREAKS IN CONTRACT; IDENTIFY CONTRACT TIMING ISSUES THAT NEED TO BE ADDRESSED; IDENTIFY SPECIFIC PHASING REQUIREMENTS | The design, permitting and construction of the well and procurement of the generator are the main items to be fast-tracked. |
We suggest 18 months to accommodate design, permitting, equipment purchasing, well drilling, construction, testing, startup, final permit to operate.
| PERMITTING & COMPLIANCE | |
| 3 |
External Permit or Approval LIST REQUIRED GOVERNMENT FURNISHED PERMITS AND APPROVALS: List by Agency-Type: Example: USACE-CWA404 NWP18. Include contact, and phone number. NJDEP Minor Modification to the Water Allocation Permit NJDEP Permit to Operate a Water Well Decommissioning Plans for Well 4 and Well 3.
External Permit or Approval LIST REQUIREMENTS FOR GOVERNMENT FURNISHED PERMITS: Include inspections, meetings, close out requirements, and drawings. Prior to well development and construction, the Minor Modification Permit application is submitted.
Prior to issuing the permit to operate, well capacity testing and results of water quality sampling must be submitted to NJDEP and Wells 4 and 3 must be satisfactorily decommissioned.
External Permit or Approval LIST REQUIRED CONSTRUCTION CONTRACTOR FURNISHED PERMITS AND APPROVALS Required:
- Minor Modification to the existing Water Allocation Permit (NJDEP)
- Well Construction Permit (NJDEP)
- Well Operation Permit (NJDEP)
- Soil Erosion and Sediment Control Plan Certification
- Approval of Decommissioning Plans for Well 4 and Well 3.
Potentially Needed:
- Waters of the US and Wetlands Individual or General Permit (NJDEP)
- Construction in Floodplain Individual or General Permit (NJDEP)
- Water Quality Certification (NJDEP)
- Stormwater Management Permit (NJDEP) External Permit or Approval DESCRIBE WHERE AND HOW PERMIT REQUIREMENTS ARE INCLUDED IN DESIGN PACKAGE: For each permit, describe requirement, specification (section and paragraph) and/or drawing number. Permit list is included in Section 2.2.1 of the DB RFP.
The BDR contains reference information for the DB Contractor for each permit.
| 7 | ||||
| Internal Compliance | IDENTIFY COMPLIANCE REQUIREMENTS: | |||
| SHPO, NEPA, EA: List requirement, status, and date or expected date. | NPS GATE staff is to complete the required compliance. | |||
| 8 | ||||
| Internal Compliance | COMPLETE ALL APPROVALS: Director's, DAB, Congressional Funding issues, estimate within available funds? Adequate time to complete work within project and funding constraints? | GATE/DSC is to achieve the required approval. | ||
| 9 | ||||
| General | IDENTIFY REQUIRED SPECIAL INSPECTIONS: List inspecting or approving organization and reason required. | NJDEP will be required to witness pump testing, water quality testing and well commissioning. | ||
| STAGING AND MOBILIZATION | ||||
| 10 | IDENTIFY AREAS FOR STAGING INCLUDING AREAS FOR PRIME, SUBS, MATERIAL, AND PARKING; IDENTIFY AREAS FOR CONSTRUCTION CAMP IF APPLICABLE: | |||
| List drawing number(s) showing staging area(s). | Staging area is shown on Sheet G1.2. | |||
| 11 | IDENTIFY TEMPORARY UTILITIES AVAILABLE FOR CONSTRUCTION: List drawing number or specification section that indentifies available utilities-electrical, phone, non-potable and potable water, sanitary-provider, meter needed, and responsible cost party. | Available existing utility information (based on NPS provided GIS and historic plans) is provided on the drawings. | ||
| 12 | IDENTIFY CONSTRUCTION LOGISTICS: List drawing numbers that show traffic control, access restrictions, work hour restrictions, bridges, features, other. | Relevant Construction Logistic information is included in the D-B documents, Section 2.1.4, "Other Project Specific Concerns". | ||
| 13 | IDENTIFY IMPACTS TO PARK AND VISITOR OPERATIONS: List drawing number(s) or specification section(s) that identifies impacts (e.g. Visitor Impacts, Neighborhood-Urban Impacts, Detours, Closures). | Construction area is not located within areas typically visited by the park visitors. | ||
| 14 | IDENTIFY SITE ACCESS ISSUES: List drawing number(s) or specification section(s) that identify issues (e.g. remote and road type constrained sites, weather closure restrictions, road and bridge load limits, road and tunnel height restrictions, crane and helicopter requirements). | Site access is shown on Sheet C1.1. | ||
| SUBMITTALS | ||||
| 15 | LIST MATERIAL SUBMITTALS ON CRITICAL PATH; | |||
| FOR DESIGN-BUILD (DB), LIST MATERIAL SUBMITTALS REQUIRING GOVERNMENT APPROVAL | Steel Casing |
Precast building (including hardware for doors and the roof hatch) Emergency Generator Fuel tank Control panels 16 LIST LONG LEAD ITEMS; MATERIAL AND EQUIPMENT AVAILABILITY CONCERNS, SPECIAL DELIVERY REQUIREMENTS Steel Casing Emergency Generator Fuel tank Control panels
Precast Building: 2-10 weeks for submittals (depends on MFR); 12-14 weeks for production & delivery
| 17 | LIST OF SOLE SOURCE MATERIALS AND GOVERNMENT FURNISHED MATERIALS OR EQUIPMENT | N/A | |
| SITE LAYOUT / RESOURCE PROTECTION | |||
| 18 | TYPES OF RESOURCE PROTECTION REQUIRED: List where and how requirements are included in design package. | NPS GATE staff is to complete the compliance. E&S measures are shown on the site plans. | |
| 19 | ACCURATE SURVEY DATA ON PLANS: BMs, TBMs, TOPO | Topographic survey is to be performed by the DB contractor. Existing information included within the Draft SD drawings are based on GIS and historic plans. | |
| 20 | PRELIMINARY SITE INVESTIGATION COMPLETE, EXISTING CONDITIONS VERIFIED AND INCLUDED IN PACKAGE | Yes. Topographic survey is to be performed by the DB contractor. | |
| 21 | CONSTRUCTION LIMITS CLEARLY SHOWN AND DEFINED FOR BOTH ACCESS AND CONSTRUCTION: List where and how requirements are included in design package. | Limits of construction are shown on the Schematic Design plans. | |
| 22 | SPECIAL SIGNAGE REQUIREMENTS: Describe and list where requirements are included in design package. | N/A | |
| 23 | LIST WORK SAFETY CONCERNS, LOCATION, AND NEEDS: Include Height, Weather, Animal, Aerial, Public Accessibility, Security, Confined Space, Pathologic, Atmospheric, and others. | N/A | |
| DEMOLITION | |||
| 24 | ALL EXISTING UTILITIES LOCATED AND ACCURATELY SHOWN: Describe where shown. | Available existing utility information (based on GIS and historic plans) is provided on the drawings. | |
| 25 | TEMPORARY SYSTEMS REQUIRED: Identify for Park or Public: Access, power, water, sanitary, covered access, exhibit relocation, movement assistance, accessibility. | Temporary services are identified in Section 2.3.9 and include electricity, water and sanitary facilities. | |
| 26 | SALVAGE, RECYCLING, STORAGE, AND DISPOSAL REQUIREMENTS: Who is removing salvageable equipment and where requirements are included in design package? | N/A | |
| 27 | NOISE / DUST / SAFETY CONCERNS FOR PUBLIC OR ENVIRONMENT: Describe where included in design package. | Construction area is not located within areas typically visited by the park visitors. | |
| 28 | CONSTRAINTS ON MEANS AND METHODS: Blasting, Burning, Tidal, Weather, Public Accessibility, Existing structures/features, Holidays and Seasonal, Permitting, other. | No blasting allowed. | |
| 29 | HAZARDOUS MATERIAL CONSIDERATIONS DEMO METHODS AND DISPOSAL STATE AND LOCAL REQUIREMENTS: Describe hazardous materials being addressed, how, and where in design package. | Hazardous Materials Survey for Well #4 building was performed and the report is included in the DB package. | |
| 30 | ARCHEOLOGICAL MONITORING REQUIREMENTS: Describe what is needed and where in design package. Identify who provides monitor. | Park is to complete the compliance. Any requirements will be included within the DB package. | |
| CONSTRUCTION | |||
| 31 | MATERIAL, EQUIPMENT, LABOR AVAILABILITY FOR REMOTE SITES: Describe issues and where included in design package. | N/A | |
| 32 | SITE ACCESS RESTRICTIONS TO CONSTRUCTION OPERATIONS IF DIFFERENT OR MORE SUBSTANTIAL THAN ITEMS 12 AND 14 | N/A | |
| 33 | ANTICIPATED WEATHER CONSIDERATIONS, CONSTRUCTION SEASON, OPTIMUM TIME TO ADVERTISE, RECOMMENDED CONTRACT LENGTH | Recommend to advertise as soon as possible. Weather is not a consideration as winters are generally mild. However, ideally the work completed during spring and summer will allow the contractor to take advantage of longer days and more favorable weather. | |
| 34 | PARK / CONCESSION IMPOSED RESTRICTIONS INCLUDED IN DESIGN PACKAGE AND IMPACTS ON SCHEDULE & COST | N/A | |
| 35 | DESCRIBE FULL SCOPE OF WORK FOR LOCAL UTILITY COMPANIES AND CONSTRUCTION CONTRACTOR FOR EACH UTILITY | Electrical service is being relocated to be accessible to JCP&L outside of the fenced area. Existing utility pad mount transformer to remain. New conduit pathway to be provided from pad mount transformer to new utility meter. Cabling from transformer to meter be provided by JCP&L. | |
| 36 | DESCRIBE DISRUPTION REQUIREMENTS FOR UTILITY CONNECTIONS, CLOSURES, AND MAXIMUM ALLOWABLE INTERRUPTIONS: Describe where addressed in design package. | N/A | |
| 37 | SPECIFIC PHASING REQUIREMENTS: Detail what and where where provided in design package. | N/A | |
| 38 | DESCRIBE SPECIALIZED MATERIALS/INSTALLATION METHODS CERTIFICATIONS/TRAINING REQUIREMENTS; DETAIL GOVERNMENT REQUIRED SPECIALTY SERVICES OR INSPECTIONS: List requirements. | N/A | |
| 39 | COORDINATION WITH PARK OR CONCESSIONAIRE ON BENEFICIAL OCCUPANCY: Grand opening, fixed completion dates, etc. | N/A | |
| 40 | ADJACENT or CONCURRENT CONTRACTS COORDINATION / OVERLAPS ON CONCURRENT OR FUTURE CONTRACTS | N/A | |
| 41 | VALUE ENGINEERING POTENTIAL | Not anything of significance. | |
| PROJECT CLOSEOUT | |||
| 42 | TRAINING REQUIREMENTS, CERTIFICATIONS SPECIFIED | Operator training will be required for the well system, controls, SCADA system and generator. | |
| 43 | OPERATION & MAINTENANCE (O&M) REQUIREMENTS | O&M Manuals will be required for the well system, controls, SCADA system and generator. | |
| 44 | LIST PERMITS NEEDING CLOSURE AND POINTS OF CONTACT: Describe requirement; include specification and/or drawing location for each. | The Well Operation Permit (NJDEP) is required to begin using the well and will include NJDEP's acceptance of pump testing, water quality sampling and decommissioning of Existing Wells 3 and 4. | |
| 45 | POST CONSTRUCTION REQUIREMENTS | Contractor's 1-year Warranty / Correction Period. | |
| 46 | LIST LONG TERM MAINTENANCE NEEDS AND LOCATION IN THE DESIGN PACKAGE. | Incorporation of Well 6 into the overall water system O&M, Section 2.3.17 Project Close-Out. |
Penetrations at EPDM roof; in Precast Building specifications.
&8&K01+016NPS Constructability Checklist, 3-20-18 | page &P of &N
Instructions
| INSTRUCTIONS FOR NPS CONSTRUCTABILITY CHECKLIST |
| Introduction - Use the NPS Constructability Checklist as a tool to inspire, document, track, and record project issues as discussed and resolved throughout preparation of Design Development (DD), Construction Documents (CD), and Request for Proposal (RFP) documents. The end result is a completed checklist that identifies project issues and provides the background to complete contract documents (primarily Division 01 Specifications). |
| Title Block - Enter Date, Park, PMIS Number (Project Management Information System), Project Title, Completed By, and if DBB or DB (Design-Bid-Build (DBB) or Design (DB)) in appropriate row. |
| Project Issues Column - Typical constructability issues are listed under Project Issues. Insert additional issues as needed to cover project issues not listed. If issues are listed that do not apply, insert N/A. |
Project issues are organized to coincide with award and construction phasing of a project. They are organized under headings typically used as summary headings in a project schedule. If these project issues have significant impact on time, impacts should be shown in a projected construction schedule developed during design. This is an effective way to accomplish construction planning, develop realistic expectations, and account for time and cost implications of project issues.
| Schematic Design (SD) Column - Complete necessary research to gain full understanding of project issues that will need to be considered. Explain specific issue in general for each project issue. |
| Design Development (DD) or Request for Proposal (RFP) Comments Column - Develop necessary in-depth research to gain full understanding of project issues that will need to be considered. Explain specific issue in general for each project issue. |
| Construction Documents (CD) or Request for Proposal (RFP) Resolution Column - Develop strategy on how each project issue will be resolved contractually. Indicate how it will be resolved. Refer to specification or drawing where information is contained. Be as complete as possible. Be specific with language needed to describe a constraint, requirements for specific phasing, potential impacts to cost and schedule, etc. |
| General - After completing this checklist, make sure resolution to project issues have been incorporated into CDs / RFPs. The Park, Project Manager (PM), and others may be responsible for some items and this should be so noted. |