This document contains questions and answers regarding Solicitation Number 140P2022R0044 for the Rehab Replace Well No. 4 project at Sandy Hook, New Jersey, within the Gateway National Recreation Area. The solicitation seeks design-build services for replacement of the existing well and associated infrastructure. Key details include that the design package is at the 35% schematic level, with native CAD files to be provided to the awardee. The National Park Service will identify laydown areas and locations for test pumping and cuttings disposal. Resumes must be submitted for five key personnel positions, and the prime contractor must submit the project experience and past performance questionnaires. Clarification was provided on dual-hatting roles and qualifications for quality and safety positions.

View the file

Other files

File Type Posted
B09_Attach_21_Request_for_Information_DRAFT_(1)_0004.pdf PDF
Sol_140P2022R0044_Amd_0004.pdf PDF
B09_Attach_24__Sheet_C1_1_Revision_0003.pdf PDF
B09_Amend_03_RFIs_0003.pdf PDF
B09_Attach_25_Cert_of_Vaccination_Form_Revised_0003.pdf PDF
Sol_140P2022R0044_Amd_0003.pdf PDF
B09_Attach_21_Request_for_Information_DRAFT_0002.docx DOCX document
B09_Attach_20_Pre-Proposal_Conf__Attendee_List_0002.docx DOCX document
Sol_140P2022R0044_Amd_0002.pdf PDF
B09_Attach_19_GATE_Well_PreProposal_Conf_0002.ppt PPT presentation
B09_Attach_23_Project_Experience_Form_0002.docx DOCX document
B09_Attach_22_Schematic_Design_Plans_Revision_0002.pdf PDF
B09_Amend_02_Attachments_0002.pdf PDF
B09_Amend_01_PreProposal_Conf_0001.pdf PDF
Sol_140P2022R0044_Amd_0001.pdf PDF
B08_Attach_3_Vaccination_Certification_Notification_.pdf PDF
B08_Attach_4_Certification_of_Vaccination_Form.pdf PDF
B08_RFP_140P2022R0044.pdf PDF
B08_Attach_10_Schematic_Design_Tech_Requirements.pdf PDF
B08_Attach_16_NPS_Constructability_Checklist_DRAFT.xlsx XLSX spreadsheet
B08_Attach_8_Discussions_Permitting_Agencies.pdf PDF
B08_Attach_2_Davis_Bacon.pdf PDF
B08_Attach_13_Existing_Photos.pdf PDF
B08_Attach_6_Geologic_Survey___Drilling_Approach.pdf PDF
B08_Attach_9_Schematic_Design_Plans.pdf PDF
Sol_140P2022R0044.pdf PDF
B08_Attach_17_PPQ.docx DOCX document
B08_Attach_14_Existing_System_Drawings.pdf PDF
B08_Attach_18_LmtOnSubconRpt.xlsx XLSX spreadsheet
B08_Attach_15_Well_5A_Raw_Water_Test_Report.pdf PDF
B08_Attach_1_SOS.pdf PDF
B08_Attach_7_Existing_Permit_Authorizations.pdf PDF
B08_Attach_5_Basis_of_Design.pdf PDF
B08_Attach_11_Hazardous_Materials_Survey.pdf PDF
B08_Attach_12_Geotechnical_Report.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Information

RFP 140P2022R0044

GATE Well No. 4 June 27, 2022

Attendee
Email
1.
I would like to schedule a site visit to this location 1st week in June. Can you advise who I should coordinate with?
A virtual pre-proposal conference was held to discuss solicitation requirements. See Attachment 19 for slide deck. After the short list has been made for Phase 2, we are anticipating an on-site visit.
2.
I downloaded the Sandy Hook project. I went through the package and could not find the bid sheet/checklist for submittal. Are you able to direct me to the correct part for this information?
Please refer to the Instructions section of the solicitation, which is Section L. That starts on page 40. You’ll want to pay special attention to pages 46-48 and 50-51 as it relates to detailed criteria for Phase 1. For Phase 1, do not submit any pricing information.
3.
Is it permissible to dual hat the on-site QC and Safety position?
It permissible to dual hat QC and Safety positions.
4.
Can site superintendent also perform safety manager duties and/or Quality manager duties?
The Site Superintendent may dual hat the Safety or Quality Control positions, if qualified. Note: one person cannot fulfill all three roles.
5.
Will A/E representative be approved to be quality manager?
An Offeror may submit their A/E for the quality position. Any candidate should have demonstrated quality control experience. Please review instructions and evaluation criteria for Factor 2.

Note: Offeror may not subcontract with draft design firm or subcontractors who produced the 35% plans.

6.
In Section H of the RFP The Key personnel are listed as the following:

PM, Job-site Superintendent, QC Manager, Safety Manager and DoR .

In Factor 2 Key Personnel on page 47 of 52 it states to Submit resumes for key personnel as identified in Section H of this solicitation and listed below, PM, Superintendent, On-site QC Specialist, On-site Safety Specialist and DoR.

Please confirm if for the QC and Safety Positions that you want resumes for the QC and Safety Managers not the On-site specialists.

Key Personnel have been revised in Section H and in Section L, Factor 2, so that they match; as follows:

· Project Manager

· On-site Superintendent

· On-site Quality Control Specialist

· On-Site Safety Specialist

· Designer of Record (NJ License)

Resumes should be submitted for all five positions.

7.
With regard to the submittal of Key Personnel for Factor #2, and Safety Information for Factor #3, please clarify whether or not this information is required only from the General Contractor, or are the Proposed Subs also required to submit the same information regarding their Key Personnel and Safety Records.
The prime should submit selected key personnel for all 5 positions who are subject to substitution requirements and ultimately responsible for their allocated role. It is expected key personnel attended weekly progress meetings. The prime may select internally or subcontractors for these roles. Submit only 1 person for each of the 5 roles, and/or indicate if someone will dual-hat. Note: dual-hat submissions should reflect qualifications for both roles.

Factor 3 safety submission is required of the prime contractor only.

8.
The solicitation for this project references to two separate forms that need to be submitted in Phase 1. It states that these forms are attached; however, we cannot locate them. Please direct us to where they can be found, or please upload/issue these forms for bidders use. They are: Under Section “L”:

Factor 1 – Project Experience Form Factor 4 - Past Performance Questionnaire The project experience form is Attachment 23 and the past performance questionnaire is Attachment 17.

9.
It would be appreciated if additional clarification can be provided on the use and filling-out of the Questionnaires that are to be submitted for Factor #1 and for Factor #4.

Is only the General Contractor required to fill-out both of these forms?

Are all of the proposed Subcontractors to fill-out both of these forms?

The project experience factor and past performance factor should work in tandem. The prime may submit up to 5 projects maximum for project experience. Each project should have its own form. The same project should be reflected in past performance. A prime may chose any combination of projects to get to 5, such as projects from the prime, or A/E projects, or subcontractor projects. Please review the submission and evaluation criteria in sections L & M for those factors, as that is how the submissions will be evaluated.

Prime Offeror should be filling out the entirety of the project experience form and submitting it with their Phase 1 package due on July 1.

Prime Offeror should be filling out the top portion (Sections A & B) of the past performance questionnaire and sending it to their client to finish and submit to contracting.

10.
Will additional RFI’s be allowed after the Phase I selection and site visit?
Yes.
11.
Will weekend and or holiday work be allowed on site for continuous drilling operations?
If the Contractor wishes to work on the Weekend or on a Federal Holiday they must request such in writing to the Contracting Officer 72 hours in advance of the Weekend or Holiday. The CO may approve or decline the request.
12.
The set of drawings that were provided with this Solicitation only contains ten drawings (Sheets #1 – 10). However, the Drawing Index on Sheet #1 of 22 includes 22 drawings, and the numbering of the drawings also indicates that there are 22 drawings in the set of drawings. It would be appreciated if the missing drawings were made available to the Bidders as soon as possible.
Attachment 22_Schematic Design Plans contains the full set; 24 pages.
13.
At what level are the current design drawings? 35%, 50%?
The current Design Package is at the Schematic Design level, 35%.
14.
Please confirm our assumption that the abbreviation of “UGE” on Drawing C1.1 means Underground Electric.
YES, UGE does stand for Underground Electric. See updated Sheet C1.1 as Attachment 24. Exact layout of these utilities is to be designed by the DB contractor.
15.
Will NPS provide full electronic versions of the preliminary design native CAD files to awardee?
The Awarded Contractor will receive CADD Files after the award has been made.
16.
Are there any designated laydown and storage areas for construction contractors? If yes please designate on drawings.
These areas will adjacent to the site and identified in the Pre-Construction Meeting. Randolph Road is approx. 15'-0" wide X up to 200'-0" available of paved surface that is available for storage.
17.
Will NPS provide schematic drawings and as builts for all existing electrical, SCADA and telemetry systems including equipment specifications and current integrators that have programmed those units?
NPS will provide available copies – not all items listed may be available. Please review Attachment 14 for existing system drawings.
18.
Has the project site been cleared of all environmental restrictions by NPS and associated federal agencies to allow full clearing and grubbing of the site within the construction boundaries?
The Compliance for the two (2) Construction Areas delineated on the provided site map is under way. It is anticipated that all Compliance Documents will be completed prior to the Construction Notice To Proceed (NTP) being issued.
19.
What is the allocated timeframe for NPS to review each design phase and submittals for approval or rejection? 5 days, 10 days?
Please review deliverables schedule in the Scope of Services document, pages 8 and 9.
20.
Will all generators and removed equipment be scraped and salvaged by contractor? Besides telemetry equipment as noted on drawings.
Yes.
21.
Will NPS allow cuttings to be spread level on site or in designated area within the park site?
Yes, this area will be identified in the Pre-Construction Meeting.
22.
Where will test pumping water production be displaced on site?
Adjacent to site on the east side - this area will be identified in the Pre-Construction Meeting.