This document contains questions and answers regarding Request for Information solicitation number 140P2022R0044 from the National Park Service for rehabilitation of Well Number 4 at Sandy Hook, New Jersey. The solicitation involves a two-phase selection process, with the first phase being a shortlisting of offerors based on qualifications. Key details include that a virtual pre-proposal conference will be held, with an anticipated on-site visit occurring after shortlisting for phase two. Resumes should be submitted for project manager, superintendent, on-site quality control specialist, on-site safety specialist, and director of recovery as identified in Section H and Section L, factor 2. Additionally, the full set of 24 schematic design plans has been made available in Attachment 9 after an offeror noted only 10 of 22 drawings were previously provided.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Information
RFP 140P2022R0044
GATE Well No. 4 June 13, 2022
| Attendee |
| 1. |
| I would like to schedule a site visit to this location 1st week in June. Can you advise who I should coordinate with? |
| A virtual pre-proposal conference is scheduled to discuss solicitation requirements. After the short list has been made for Phase 2, we are anticipating an on-site visit. |
| 2. |
| I downloaded the Sandy Hook project. I went through the package and could not find the bid sheet/checklist for submittal. Are you able to direct me to the correct part for this information? |
| Please refer to the Instructions section of the solicitation, which is Section L. That starts on page 40. You’ll want to pay special attention to pages 46-48 and 50-51 as it relates to detailed criteria for Phase 1. For Phase 1, do not submit any pricing information. |
| 3. |
| Is it permissible to dual hat the on-site QC and Safety position? |
| Under review |
| 4. |
| In Section H of the RFP The Key personnel are listed as the following: |
PM, Job-site Superintendent, QC Manager, Safety Manager and DoR .
In Factor 2 Key Personnel on page 47 of 52 it states to Submit resumes for key personnel as identified in Section H of this solicitation and listed below, PM, Superintendent, On-site QC Specialist, On-site Safety Specialist and DoR.
Please confirm if for the QC and Safety Positions that you want resumes for the QC and Safety Managers not the On-site specialists.
Key Personnel have been revised in Section H and in Section L, Factor 2, so that they match; as follows:
| 5. |
| The set of drawings that were provided with this Solicitation only contains ten drawings (Sheets #1 – 10). However, the Drawing Index on Sheet #1 of 22 includes 22 drawings, and the numbering of the drawings also indicates that there are 22 drawings in the set of drawings. It would be appreciated if the missing drawings were made available to the Bidders as soon as possible. |
| Attachment 9_Schematic Design Plans has been revised to include the full set; 24 pages. |