B08_Attach_01_GRCA_318719_North_Rim_TWWTP_t_Project_Manual_20260610.pdf

PDF 19 MB Posted

Attached to
GRCA 318719_Temporary WWTP at North Rim Federal contract opportunity
Solicitation number
140P2026R0075
Issued by
Department of the Interior National Park Service National Office

About this file

This is a Project Manual containing construction specifications and requirements for the installation of a Temporary Wastewater Treatment Plant (WWTP) at Grand Canyon National Park's North Rim, designated as GRCA 318719. The 100% final design document, prepared by HDR (Project No. 10414450) and dated June 10, 2026, is sealed and signed by six licensed Professional Engineers covering various specification divisions.

The project scope encompasses five primary Contract Line Items (CLINs): (1) Site work, utilities, septage receiving, screening, and two lift stations with grading, concrete pads, and security fencing; (2) Two conditioned storage containers and a mobile wastewater lab with HVAC systems; (3) A complete membrane wastewater treatment system including an equalization tank, two MBR treatment units rated at 45,000 gallons per day each, UV disinfection, and related equipment; (4) Startup, commissioning, six months of operations with a licensed Arizona Grade 3 operator, winterization, and shutdown; and (5) End-of-season tank pumping and biosolids removal. The work must be phased to achieve Arizona Department of Environmental Quality (ADEQ) approval to operate by June 1, 2027, with site work and utilities completed before membrane unit mobilization and security fencing installed post-commissioning. The contract includes extensive administrative requirements covering project management, construction scheduling using Critical Path Method with monthly updates, submittal procedures, environmental protection and storm water pollution prevention, safety protocols, coordination with concurrent contractors performing fire recovery operations and infrastructure rehabilitation, and compliance with National Park Service rules. Tree removal is restricted to September 1 through March 31 to protect nesting birds, vehicle traffic on State Route 67 is typically impassable from December 7, 2026 through April 1 due to snow, and contractor work hours are generally 6 a.m. to 6 p.m. Monday through Friday with restrictions on utility interruptions and public access impacts.

View the file

Other files for this federal contract opportunity

Other files attached to GRCA 318719_Temporary WWTP at North Rim, newest first.
File Type Posted
GRCA_318719_NR_TWWTP_Spec_Addm_1_0006.pdf PDF
Sol_140P2026R0075_Amd_0006.pdf PDF
Other_Updates_22_July_2026_0006.pdf PDF
E602-E602_0006.pdf PDF
E601-E601_0006.pdf PDF
Solicitation_140P2026R0075_Temp_WWTP_Q_and_A_July_15__2026_0005.pdf PDF
Sol_140P2026R0075_Amd_0005.pdf PDF
Sol_140P2026R0075_Amd_0004.pdf PDF
Q_and_A_dated_July_10_2026_0004.pdf PDF
GRCA_318719_North_Rim_GIR_20250811_0004.pdf PDF
Sol_140P2026R0075_Amd_0003.pdf PDF
Pre_Bid_Site_Visit_June_23_2026_Attendee_List_0002.pdf PDF
Sol_140P2026R0075_Amd_0002.pdf PDF
GRCA_318719_Temporary_WWTP_Pre-Bid_Map_0001.pdf PDF
Sol_140P2026R0075_Amd_0001.pdf PDF
B08_Attach_05_Solit_PSP_Vol_I_Exp_REQD.pdf PDF
B08_Attach_06_Solit_PSP_Vol_II_LmtOnSubcontracting_REQD.xlsx XLSX spreadsheet
B08_Attach_02_GRCA_318719_NR_TWWTP_Final_CD_20260610_Part3.pdf PDF
B08_Attach_02_GRCA_318719_NR_TWWTP_Final_CD_20260610_Part1.pdf PDF
B08_Attach_03_AZ20260056_dated_May_18_2026.pdf PDF
B08_Attach_02_GRCA_318719_NR_TWWTP_Final_CD_20260610_Part2.pdf PDF
B08_140P2026R0075.pdf PDF
Sol_140P2026R0075.pdf PDF
B08_Attach_02_GRCA_318719_NR_TWWTP_Final_CD_20260610_Part4.pdf PDF
B08_Attach_04_Contract_Price_Schedule_TWWTP_-_Blank_Only.xlsx XLSX spreadsheet
B08_Attach_07_Solit_PSP_Vol_I_PastPerf_REQD.pdf PDF
B08_Attach_08_Solit_PSP_Vol_II_BidBond.pdf PDF
B08_Attach_9_Solit_PSP_Vol_II_Equals_RELEASED_v1_25Feb25.pdf PDF
B08_Attach_10_Solit_PSP_Vol_II_GenRefs.pdf PDF
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Grand Canyon National Park, National

Park Services (Federal)

GRCA 318719 North Rim Temporary Wastewater

Treatment Plant

Construction Documents

Project Manual

100% Final

6/10/2026

HDR Project No. 10414450

This page intentionally left blank.

GRCA - 318719 00 01 07 - 1

100% Final SEALS AND SIGNATURES

00 01 07

SEALS AND SIGNATURES

Owner Name: Grand Canyon National Park, National Park Services (Federal)

Project Name: GRCA 319719 North Rim Temporary Wastewater Treatment Plant

Engineer: HDR

Chris Carpenter, PE

License No. 85332

The seal and signature to the left applies to the following Specifications divisions and sections of this project manual:

• Division 01 (except Section 01 40 00.A and 01 81 33)

• Division 02

• Division 10

• Section 33 32 13

• Sections 40 05 00, 40 05 07, 40 05 23, 40 05 25, 40 05 31, 40 05 51, 40 05 57, 40 05 59, 40 05 62, 40 05 63, 40 05 64, 40 05 66

• Division 41

• Division 43

• Division 46.

Juan Coronado, PE

License No. 85509 The seal and signature to the left applies to the following Specifications divisions and sections of this project manual:

• Section 01 40 00.A

• Division 03

• Division 05.

GRCA - 318719 00 01 07 - 2

Josie Brainard, PE

License No. 85305 of this project manual:

• Section 01 81 33

• Division 27

• Sections 40 61 13, 40 61 21, 40 61 43, 40 62 05, 40 63 43, 40 66 05, 40 67 00, 40 67 63, 40 68 63, 40 78 00.

Richard McKinley, PE

License No. 85788 of this project manual:

• Division 06

• Division 07

• Division 08

• Division 09.

Adam Putman, PE

License No. 65133 of this project manual:

• Division 22

• Division 23

• Section 40 42 00.

GRCA - 318719 00 01 07 - 3

Tou Vang, PE

License No. 75014 of this project manual:

• Division 26

• Section 40 41 13.

Gregory Young, PE

License No. 75262 of this project manual:

• Division 31

• Division 32

• Division 33 (except Section 33 32 13).

Engineer’s seal and signature does not apply to the documents that comprise Division 00, Bidding and

Contracting Requirements.

It is a violation of applicable laws and regulations governing professional licensing and registration for any person, unless acting under the direction of the licensed and registered design professional(s) indicated above, to alter in any way the Specifications in this project manual.

END OF SEALS AND SIGNATURES

GRCA - 318719 00 01 10 - 1

100% Final TABLE OF CONTENTS

TABLE OF CONTENTS

DIVISION 01 — GENERAL REQUIREMENTS

01 11 00 - SUMMARY OF WORK NPS

01 26 01 - CONTRACT MODIFICATION PROCEDURES

01 27 00 - DEFINITION OF CONTRACT LINE ITEMS

01 31 00 - PROJECT MANAGEMENT AND COORDINATION

01 32 16 - CONSTRUCTION SCHEDULE

01 32 33 - PHOTO DOCUMENTATION

01 33 23 - SUBMITTAL PROCEDURES

01 33 23.A - SUBMITTAL LIST

01 35 05 - Attach A - Biological Assess-Equip Types

01 35 05 - Attach B - SOP 8213-007 Invasive Plant 5-17-12 Revision

01 35 05 - ENVIRONMENTAL PROTECTION AND SPECIAL CONTROLS NPS

01 35 05.A - SPILL INCIDENT REPORT TEMPLATE

01 35 10 - TEMPORARY WASTEWATER TREATMENT MANAGEMENT PLAN

01 35 13.22 - ARCHEOLOGICAL PROTECTION

01 35 15 - DISCHARGE EMERGENCY RESPONSE PLAN

01 35 23 - SAFETY REQUIREMENTS

01 35 73 - DELEGATED DESIGN PROCEDURES

01 35 91 - HISTORIC PRESERVATION TREATMENT PROCEDURES

01 40 00 - QUALITY REQUIREMENTS

01 40 00.A - STSI - PA1

01 42 00 - REFERENCE STANDARDS

01 50 00 - TEMPORARY FACILITIES AND CONTROLS

01 57 19.12 - NOISE AND ACCOUSTICS MANAGEMENT

01 57 23 - TEMPORARY STORM WATER POLLUTION PREVENTION

01 61 03 - EQUIPMENT - BASIC REQUIREMENTS

01 67 00 - PRODUCT REQUIREMENTS

01 71 21 - SPECIALTY ENGINEERING REQUIREMENTS

01 73 20 - OPENINGS AND PENETRATIONS IN CONSTRUCTION

01 73 29 - CUTTING AND PATCHING

01 73 40 - EXECUTION

01 73 60 - CONSTRUCTION CAMPS

01 74 19 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 75 10 - CHECKOUT AND START-UP PROCEDURES FOR WASTEWATER TREATMENT

FACILITIES

01 77 00 - CLOSEOUT PROCEDURES

01 78 23 - OPERATION AND MAINTENANCE DATA

01 78 23.A - CLOSEOUT OPERATION MAINTENANCE REQUIREMENTS

01 79 00 - DEMONSTRATION AND TRAINING

01 79 00.A - DEMONSTRATION AND TRAINING REQUIREMENTS TABLE

01 81 10 - WIND, SNOW AND SEISMIC DESIGN CRITERIA

01 81 13 - SUSTAINABLE DESIGN REQUIREMENTS FOR NON-LEED™ PROJECTS

01 81 33 - CYBER SECURITY REQUIREMENTS

DIVISION 02 — EXISTING CONDITIONS

02 41 00 - DEMOLITION

DIVISION 03 — CONCRETE

03 01 30 - REPAIR AND REHABILITATION OF EXISTING CONSTRUCTION

GRCA - 318719 00 01 10 - 2

03 05 05 - CONCRETE TESTING AND INSPECTION

03 11 13 - FORMWORK

03 15 19 - ANCHORAGE TO CONCRETE

03 21 00 - REINFORCEMENT

03 31 30 - CONCRETE MATERIALS AND PROPORTIONING

03 31 31 - CONCRETE MIXING, PLACING, JOINTING, AND CURING

03 35 00 - CONCRETE FINISHING AND REPAIR OF SURFACE DEFECTS

03 41 33 - PRECAST AND PRESTRESSED CONCRETE

DIVISION 05 — METALS

05 50 00 - METAL FABRICATIONS

DIVISION 06 — WOOD, PLASTICS, AND COMPOSITES

06 10 00 - ROUGH CARPENTRY

DIVISION 07 — THERMAL AND MOISTURE PROTECTION

07 21 00 - BUILDING INSULATION

07 84 00 - FIRESTOPPING

07 92 00 - JOINT SEALANTS

DIVISION 08 — OPENINGS

08 70 00 - FINISH HARDWARE

DIVISION 09 — FINISHES

09 22 16 - NON-STRUCTURAL METAL FRAMING

09 29 00 - GYPSUM BOARD

09 91 00 - ARCHITECTURAL PAINTING

DIVISION 10 — SPECIALTIES

10 50 00 - TEMPORARY LAB TRAILER

DIVISION 22 — PLUMBING

22 05 03 - PIPE AND PIPE FITTINGS - PLUMBING SYSTEMS

22 05 23 - GENERAL-DUTY VALVES FOR PLUMBING PIPING

22 05 29 - HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

22 20 00 - PLUMBING FIXTURES AND EQUIPMENT

22 33 15 - INSTANTANEOUS ELECTRIC SAFETY SHOWER WATER HEATERS

DIVISION 23 — HEATING VENTILATING AND AIR CONDITIONING

23 05 48 - VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT

23 05 93 - HVAC SYSTEMS - BALANCING AND TESTING

23 74 36 - REFRIGERANT PIPING SYSTEM

23 80 00 - HVAC - EQUIPMENT

DIVISION 26 — ELECTRICAL

26 05 00 - COMMON WORK RESULTS FOR ELECTRICAL

26 05 13 - MEDIUM VOLTAGE CABLE

26 05 19 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

26 05 26 - GROUNDING AND BONDING

26 05 33 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

26 05 43 - ELECTRICAL - EXTERIOR UNDERGROUND

26 05 48 - ELECTRICAL SEISMIC RESTRAINT SYSTEMS

26 05 73 - UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL SYSTEMS

26 08 13 - ACCEPTANCE TESTING

26 09 13 - ELECTRICAL METERING DEVICES

26 09 16 - CONTROL EQUIPMENT ACCESSORIES

26 12 19 - DISTRIBUTION TRANSFORMERS

26 13 23 - SECTIONALIZING EQUIPMENT

26 22 13 - LOW-VOLTAGE DISTRIBUTION TRANSFORMERS

26 24 13 - SWITCHBOARDS

GRCA - 318719 00 01 10 - 3

26 24 16 - PANELBOARDS

26 27 26 - WIRING DEVICES

26 28 00 - OVERCURRENT AND SHORT CIRCUIT PROTECTIVE DEVICES

26 28 02 - COORDINATED POWER SYSTEM PROTECTION

26 28 16 - SAFETY SWITCHES

26 29 23 - VARIABLE FREQUENCY DRIVES - LOW VOLTAGE

26 36 00 - TRANSFER SWITCHES

26 41 13 - LIGHTNING PROTECTION SYSTEM

26 43 13 - SURGE PROTECTION DEVICES FOR LOW-VOLTAGE ELECTRICAL POWER

CIRCUITS

26 50 00 - INTERIOR AND EXTERIOR LIGHTING

DIVISION 27 — COMMUNICATIONS

27 10 00 - STRUCTURED CABLING

DIVISION 31 — EARTHWORK

31 10 00 - SITE CLEARING

31 22 00 - SITE GRADING

31 23 00 - EARTHWORK

31 23 33 - UTILITIES - TRENCHING AND BACKFILLING

31 25 00 - SOIL EROSION AND SEDIMENT CONTROL

DIVISION 32 — EXTERIOR IMPROVEMENTS

32 15 40 - CRUSHED STONE SURFACING

32 31 13 - CHAIN LINK FENCE AND GATES

32 91 13 - FINISH GRADING

32 92 21 - NATIVE GRASS SEEDING

DIVISION 33 — UTILITIES

33 05 31.11 - POLYVINYL CHLORIDE GRAVITY SEWER PIPE

33 05 33.23 - HIGH DENSITY POLYETHYLENE (HDPE) PIPE

33 05 61 - CONCRETE MANHOLES

33 16 33 - HYDROPNEUMATIC TANKS

33 31 11 - GRAVITY SEWER PIPELINE AND MANHOLE CONSTRUCTION

33 32 13 - PACKAGE SEWAGE PUMPING STATION

DIVISION 40 — PROCESS INTERCONNECTIONS

40 05 00 - PIPE AND PIPE FITTINGS - BASIC REQUIREMENTS

40 05 07 - PIPE SUPPORT SYSTEMS

40 05 25 - PIPE - PREFABRICATED, INSULATED AND JACKETED

40 05 31 - PIPE - PLASTIC

40 05 51 - COMMON REQUIREMENTS FOR PROCESS AND UTILITY VALVES

40 05 57 - ACTUATORS FOR PROCESS VALVES AND GATES

40 05 59 - FABRICATED STAINLESS STEEL SLIDE GATES

40 05 61 - GATE VALVES

40 05 62 - PLUG VALVES

40 05 63 - BALL VALVES

40 05 64 - BUTTERFLY VALVES

40 05 66 - CHECK VALVES

40 41 13 - HEAT TRACING CABLE

40 42 00 - PIPE, DUCT AND EQUIPMENT INSULATION

40 61 13 - PROCESS CONTROL SYSTEM GENERAL REQUIREMENTS

40 61 21 - PROCESS CONTROL SYSTEM TESTING

40 61 43 - SURGE PROTECTION DEVICES FOR INSTRUMENTATION AND CONTROL

EQUIPMENT

40 62 05 - COMPUTER SYSTEM HARDWARE AND ANCILLARIES

40 63 43 - PROGRAMMABLE LOGIC CONTROLLERS

40 66 05 - NETWORK EQUIPMENT

GRCA - 318719 00 01 10 - 4

40 67 00 - CONTROL SYSTEM EQUIPMENT PANELS AND RACKS

40 67 63 - UNINTERRUPTIBLE POWER SUPPLY

40 68 63 - CONFIGURATION OF HMI SOFTWARE AND REPORTS

40 78 00 - PANEL MOUNTED INSTRUMENTS

DIVISION 41 — MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 22 13 - CRANES

DIVISION 43 — PROCESS GAS AND LIQUID HANDLING, PURIFICATION AND STORAGE

EQUIPMENT

43 21 00 - PUMPING EQUIPMENT - BASIC REQUIREMENTS

43 23 31.29 - PUMPING EQUIPMENT - VERTICAL INLINE CENTRIFUGAL PUMPS

DIVISION 46 — WATER AND WASTEWATER EQUIPMENT

46 07 53 - PACKAGED WASTEWATER TREATMENT EQUIPMENT

46 21 40 - MECHANICALLY CLEANED SCREENS-IN CHANNEL AUGER

GRCA - 318719 01 11 00 - 1

100% Final SUMMARY OF WORK NPS

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents

2. Work Phases

3. Work Under Other Contracts

4. Government-Furnished Materials

5. Contractor Use of Site

6. Public Use of Site

7. Occupancy Requirements for Buildings

8. Conduct of Operations

9. Work Restrictions

10. Special Construction Requirements

11. Soils Investigation Report

12. Additional Reports

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: The project is generally located at Grand Canyon National Park on the North

Rim. The project areas and associated project volumes are as follows:

1. North Rim: Temporary Wastewater Treatment Plant

a. North Rim Developed District – Wastewater Treatment Plant. An administrative area located within the south-west corner of the developed district adjacent to the

National Park Service North Rim Helibase.

B. The scope of work:

1. Treatment System and Supporting Site Work and Utilities

1) The item consists of grading and utilities installation in support of 90,000gpd mem-brane wastewater treatment package system that includes: 1) Equalization tank with aeration and pumping system to MBR treatment units; 2) two MBR treatment units rated 45,000gpd per/unit with influent screening, chemical dosing and pump-ing system for disposal, lightening protection system, covered conditioned mem-brane basins for winterization of cartridges; 3) treated effluent break tank and ultra-violet (UV) disinfection system.

2) MBR Treatment Units

a) Wastewater treatment units, basis of design Cloacina MPAC-R Generation 3, enclosed and partially conditioned to allow for winterization in-place of mem-brane cartridges. Remote chemical feed system (conditioned storage contain-ers), lightening protection system, custom exterior finish: performance criteria per treatment unit

(1) Minimum Daily Flow (MIN): 9,000gpd, 6.3gpm

(2) Maximum Daily Flow (MDF): 45,000gpd, 31.3gpm

3) Site grading provides for an estimated 63cy of excess cut to be stockpiled onsite, concrete pads for EQ tank and two MBR treatment units with crushed rock finish

GRCA - 318719 01 11 00 - 2

for remainder of the operational site within the fenceline. Security fencing with multiple access gates.

4) Utilities - Locate existing utilities for connection of new utilities to include:

a) Water: Dedicated service lateral with RPZ backflow device and meter.

b) Power: Dedicated power service to include a manual transfer switch for backup generator power, generator provided by others (NIC).

c) Sanitary: Septage receiving manhole; mechanical screening auger; two pack-age lift stations: 1) Influent Lift Station, 2) Filtrate Lift Station; and overflow laterals.

2. Conditioned Storage and Lab

1) Two 40ft long shipping containers outfitted as conditioned space for chemical stor-age and injection system, spare parts, and winter storage of membrane treatment unit cartridges. Includes fully conditioned space (HVAC) for year-round (sum-mer/winter) operations. The Hypochlorite and Caustic Rooms will have a dedicated split system and an electric unit heater to maintain the required space-temperature setpoint. An instant electric water heater will be provided to supply tepid water to the emergency shower fixtures. The Citric Room will have an electric unit heater for space heating and an instant electric water heater supplying tepid water to the emergency shower fixture in the room. Underground chemical piping from chemi-cal storage to package units. Lighting and switch package. Shipping containers with be CSC certified and meet ISO 668.2020 and ISO 1496 standards.

2) One approximately 50ft long mobile wastewater certified conditioned lab with wa-ter, sewer, and power connections.

3. Commissioning and Operations

1) Commissioning: Responsible for coordination with Arizona Department of Envi-ronmental Quality (ADEQ) for start-up and commissioning for approval to operate, issued by ADEQ.

2) Operations: Provide licensed Arizona Grade 3 Wastewater Treatment Contract Op-erator for commissioning and operations of the wastewater treatment plant for six

(6) months to include winterization and shut down of the plant in November; hous-ing provided at no cost on the North Rim (less than ten minutes’ drive from the wastewater treatment plant). Duty schedule includes 40 hours per week for a five day week to include one weekend day. The onsite utilities operator will shadow the operator for part of the week and operate the system under the direction of the con-tract operator the two days off for the contract operator.

4. Tank Pumping and Biosolids Removal: Pump and dispose off-site at end of first operating season:

1) EQ Tank: Pump the equalization tank at the end of the first operating season, esti-mated 20,000 gallons.

2) Two MBR Treatment Units: Pump the primary treatment unit tank at the end of the first operating season, estimated 53,100 gallons.

3) Lift station pumping: Influent Lift Station and Filtrate Lift Station, estimated 5,000 gallons.

4) Biosolids Removal: Removal of estimate 17,400 gallons of biosolids from wastewater treatment drying beds.

C. Project will be constructed under a single prime contract.

D. The Government has selected the following products and services as the basis of design for the package membrane treatment units

Cloacina – Portable Treatment Unit, 25MR50, Generation 3

Cloacina – Portable Equalization Tank with Integrated Pumping System, EQ-R IF70

GRCA - 318719 01 11 00 - 3

1.3 WORK PHASES

A. The Work shall be conducted with the following phasing approach for permit authority ADEQ approval to operate the Temp WWTP no later than June 1, 2027.

1. Site Work and Utilities

a. Site work and utilities connection to existing utilities, underground installation to mem-brane treatment site must be completed prior to mobilization of the membrane treatment units, conditioned storage units, and mobile lab.

2. Mobilization of Membrane Treatment Package Units, EQ Tank, Storage Containers, and lab

a. Mobilization of the membrane treatment package units and storage containers must be coordinated with site access for delivery and set up.

3. Startup and Commissioning

a. All utilities installed and connected to treatment system, storage containers, and lab.

4. Security Fencing

a. Security fencing must be installed post-commissioning of the system.

5. Tank Pumping and Biosolids Removal

a. End of first operating season before demobilization.

B. Tree removal shall occur between September 1 and March 31 to avoid bird nesting. Work outside this window may be requested and will require a NPS wildlife bird biologist to perform a nest survey. Surveys shall be conducted no more than five days prior to scheduled activity. If active nests or breeding behavior are detected during these surveys, no vegetation removal activities should be conducted until nestlings have fledged or the nest fails or breeding behaviors are no longer observed.

1.4 WORK UNDER OTHER CONTRACTS

A. General: Cooperate with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate Work of this

Contract with work performed under separate contracts.

B. Concurrent Work: Government has awarded separate contract(s) for the following construction operations at Project site. Those construction operations potentially will occur simultaneously with portions of work under this Contract.

1. Fire Recovery Operations: Hazard tree and debris removal from fire recovery operations on the North Rim and around the WWTP; estimated period of performance April 2026 thru

November 2028.

2. Rehabilitation of water, power, wastewater infrastructure damaged in fire; estimated period of performance May 2026 thru November 2026.

3. GRCA 318719 Rehabilitation of North Rim Infrastructure (LRF): Rehabilitation of the

North Rim and Inner-Canyon water and power system, estimated period of performance

June 2027 thru November 2030.

4. Replacement of SR67 from Gate to NR lodge: The construction approach for the SR 67 project has identified the need for a temporary asphalt batch plant with a preliminary loca-tion being identified as Marble Flats; estimated period of performance June 2027 thru No-vember 2028.

GRCA - 318719 01 11 00 - 4

1.5 CONTRACTOR USE OF SITE

A. Limits of Construction (LOC): Contractor shall have limited use of site for construction operations.

1. Limit use of premises to areas within the Limits of Construction indicated on drawings. Do not disturb portions of the site beyond these areas. The Contractor shall clearly delineate the boundary of the Limits of Construction (LOC) prior to commencing work using fencing, flagging or other approved methods. Delineation shall be maintained for the duration of construction and shall correspond to the LOC shown on the drawings. Erosion and sediment control features (silt fence, wattles, etc) may be used to satisfy this requirement where they are installed at the LOC boundary.

2. Contractor may request deviations from the Limits of Construction but approval is not guar-anteed. Generally, the approval process once all information has been provided is up to 90 days or longer if outside agency coordination is required.

B. Equipment and Material Staging: Confine storage of materials to staging areas shown on plans.

1. Equipment and material staging areas are intended for deliveries and storage of tools and equipment, material stockpiling, construction equipment parking, construction vehicle park-ing, construction administration trailers, and similar.

2. Confine stockpiling to equipment and material staging areas. Small stockpiles within limits of construction for use in localized trenching work is acceptable.

3. Areas within the limits of construction that are not designated for equipment and material staging shall not be used for this purpose.

4. Equipment and material staging areas should not be used for construction camps including camping units, trailer complexes for living areas, private vehicle parking, and similar.

C. Parking:

1. Private vehicles for construction personnel shall be parked at designated construction camps or outside the Park.

2. Parking for marked construction vehicles shall be limited to the following areas between

April 15 and November 30 (visitor season):

a. WWTP RV sites or inside the fenceline

D. Preservation of Natural and Manmade Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants with like species, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Provide temporary construction protection mats for all areas where construction may impact a wetland. All areas that are disturbed must be restored per Specification 01 35 05.

4. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with

Contracting Officer (CO) and remove agreed-on roots and branches that interfere with

GRCA - 318719 01 11 00 - 5

construction. Contractor shall follow Grand Canyon vegetation guidelines related to pruning and root cutting.

5. Do not fasten ropes, cables, or guys to existing trees.

6. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

E. Driveways and Entrances: Keep driveways, trails, and entrances serving NPS and concessionaire premises clear and available to Government employees, and emergency vehicles at all times.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

F. Construction Camp: Establishment of a camp will be permitted at WWTP, as shown on drawings and specified in 01 73 60 “Construction Camps”. Provide utilities as specified in Section 01 50

00 "Temporary Facilities and Controls". Adhere to park rules, animal deterrent policies, cleanliness policies, and return site to previous condition at completion of work.

G. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

1. State Route 67 is heavily used for visitor traffic and park operations. Contractor shall not impede flow of traffic for equipment and material deliveries at any time, unless otherwise approved by the Contracting Officer.

2. Contractor shall use the North Rim park entrance gate. Contractor personnel providing iden-tification of employment with the Contractor or in a marked vehicle are not required to pay

Park entrance fees. Contractor shall not use other entrance roads into the Park.

H. State Route 67 Restrictions: Contractor shall identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as required for use of State Route 67. Contractor shall be responsible for obtaining any permits with Arizona Department of Transportation and

Coconino County as required.

1.6 PUBLIC USE OF SITE

A. Contractor shall conduct operations to ensure the least inconvenience to public.

B. Road restrictions (one lane must be passable with traffic control) may be permitted, when required, upon specific approval of Contracting Officer for a maximum of 8 hours within a single day; within park boundaries.

C. The North Rim District will be closed or limited access to visitors due to limited utilities available to the North Rim District during post fire recovery operations. Those conditions will change over time and it is unknown the exact number of visitor services that will be active during construction activities of this contract. The WWTP location is administrative and thus expects minimal impact to construction activities under this contract as visitor services change to the district.

GRCA - 318719 01 11 00 - 6

1.7 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Partial Government Occupancy: Government will occupy premises during entire construc-tion period, with exception of areas under construction. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform

Work so as not to interfere with Government’s operations. Maintain existing exits, unless otherwise indicated.

2. Maintain access to existing walkways, corridors, and other adjacent occupied or used facili-ties. Do not close or obstruct walkways, corridors, or other occupied or used facilities with-out written permission from Contracting Officer.

1.8 CONDUCT OF OPERATIONS

A. Contractor shall conduct operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.

B. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.9 WORK RESTRICTIONS

A. On-Site Work Hours:

1. North Rim: Work on the North Rim shall be generally performed during the hours of 6 a.m.

to 6 p.m., Monday through Friday.

2. Night Work Hours: Work outside established work hours can be requested by contractor.

B. Work on Federal holidays may not be performed without prior consent from the CO. Submit requests 5 business days in advance of the work to the CO for approval.

C. Existing Utilities

1. Utility Locating:

a. Notify Contracting Officer and utility companies of proposed locations and times for excavation. NPS will not be responsible for clearance or locating NPS owned utilities. Contractor shall utilize a third party locator and potholing services as re-quired to clear utilities prior to excavation.

b. Contractor shall be responsible for locating and preventing damage to known utili-ties. If damage occurs, repair utility at no additional expense to the Government.

c. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

2. Maintenance of Utility Operations

a. North Rim Wastewater Collections and Treatment

1) North Rim wastewater collections and treatment shall remain operational between

April 1 and October 31 each year.

3. Existing Utility Interruptions:

GRCA - 318719 01 11 00 - 7

a. Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

b. Notify Contracting Officer not less than fourteen (14) days in advance of proposed utility interruptions.

c. Do not proceed with utility interruptions without Contracting Officer’s written per-mission.

d. Hours and length of Utility Shutdowns: 8 hours.

D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within

25 feet of entrances, operable windows, or outdoor air intakes.

1. Smoking is not permitted in buildings.

2. Due to concern of wildland fires, smoking is allowed only in a single designated outside area of no larger than 500 sf within designated construction staging areas. This area shall be clear of exposed vegetation and have adequate means for disposal of trash and flam-mable materials.

1.10 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Website: A project website administered by NPS will be used for purposes of managing communication and documents during construction stage.

1. See Section 01 31 00 "Project Management and Coordination" for requirements on using

Project Website.

B. The North Rim has a seasonal shutdown of visitor services that varies each year. Typically the shutdown to overnight visitors begins on October 15 and the shutdown to day visitors begins on

November 30. The North Rim typically reopens to visitor services on or around May 15.

C. Vehicle traffic is often impassable due to snow accumulation and other weather events on State

Route 67 from Jacob Lake to the North Rim Lodge and on other North Rim roadways from the first Monday of the first full week in December (December 7, 2026) through- April 1.

D. Hazardous Materials: Work is in proximity to damaged structures from the Dragon Bravo

Wildfire and contractor shall take reasonable action to reduce risk to employees while executing scope of work in this contract.

E. The Contractor shall not construct permanent structures or install permanent utilities at staging areas or Contractor camps unless specifically shown in the Contract Documents or authorized in writing by the Contracting Officer. Any proposal for permanent structures or utilities at these locations must be submitted to the Contracting Officer for review and acceptance prior to construction.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 01 11 00

GRCA - 318719 01 26 01 - 1

100% Final CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

1.1 SUMMARY

A. Section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating

General Conditions:

1. Project Manager (PM), Assistant Project Manager

2. Superintendent, Assistant Superintendent

GRCA - 318719 01 26 01 - 2

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

g. Construction camp supplies.

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General

Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a maximum 60-hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: The hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:

GRCA - 318719 01 26 01 - 3

1) Social Security

2) Medicare

3) Workers Compensation – Policy and company calculation to be made available.

4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.

5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.

6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General

Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.

Include as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Proposal be received in the format and within the time frame specified in the Request for

Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe

Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank

GRCA - 318719 01 26 01 - 4

government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.

3. Requests for extensions of contract time as a result of change must be justified with a Time

Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.

5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. Labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. No markup shall be applied to any material provided by NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for work being performed.

2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.

3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense

Schedule (use latest edition and applicable region)

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, http://www.nps.gov/dscw/publicforms.htm#CP___PAGEID=396735|

GRCA - 318719 01 26 01 - 5

and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.

6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army

Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.

8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit. Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in

FAR Part 31which have been applied to the specific type of work included in this project.

Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10%

Profit………………8.00%

2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

GRCA - 318719 01 26 01 - 6

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 01 26 01

GRCA - 318719 01 27 00 - 1

100% Final DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

1.1 SUMMARY

A. Section explains in general what is and is not included in a contract line item (CLIN).

B. If no contract line item exists for a portion of work, include costs in a related item.

C. Contract Line Item costs shall be developed such that individual Work Item prices, as defined in

Section 3.1, can be determined by the Contracting Officer.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item Number 1 (CLIN 1): Site Work, Utilities, Septage Receiving, Screening, Influent Lift Station, Filtrate Lift Station

1. This item consists of Work shown in drawings.

a. Utilities installation in support of the whole wastewater treatment system. Work includes power, water, sewer utilities, two lift stations (influent and filtrate), septage receiving manhole, mechanical screening, and finished effluent manhole.

b. All site grading, concrete pads, crushed rock, and security fence.

2. Measurement for payment will be in percentage complete.

3. Payment will be made at the contract lump sum price.

B. Contract Line Item Number 2 (CLIN 2): Two Storage Containers and Mobile Wastewater Lab

1. This item consists of Work shown in drawings

a. The item consists of two conditioned storage units and mobile lab, includes all equipment and interior mechanical systems. Exterior work within two feet of the units included; beyond two feet is part of CLIN 1 site utilities.

2. Measurement for payment will be in percentage complete.

3. Payment will be made at the contract lump sum price.

C. Contract Line Item Number 3 (CLIN 3): Membrane Package Treatment System with EQ and UV

Disinfection System

1. This item consists of Work shown in drawings.

a. Complete Integrated System Includes: 1) Equalization tank with aeration and pumping system to MBR treatment units; 2) Two (2) MBR treatment units rated

45,000gpd per/unit with influent screening, chemical dosing and pumping system for disposal, lightening protection system, covered conditioned membrane basins for

GRCA - 318719 01 27 00 - 2

100% Final DEFINITION OF CONTRACT LINE ITEMS winterization of cartridges; 3) Treated effluent break tank and ultraviolet (UV) disinfection system.

b. MBR Treatment Units

1) Wastewater treatment unit, basis of design Cloacina MPAC-R Generation 3, enclosed and partially conditioned to allow for winterization in-place of membrane cartridges. Remote chemical feed system (conditioned storage containers), lightening protection system, custom exterior finish with insulation package: performance criteria per unit

2) Minimum Daily Flow (MIN): 9,000gpd, 6.3gpm

3) Maximum Daily Flow (MDF): 45,000gpd, 31.3gpm

c. Spare parts package per manufactures recommendation, two year parts package.

2. Measurement for payment will be in percentage complete.

3. Payment will be made at the contract lump sum price.

D. Contract Line Item Number 4 (CLIN 4): Startup, Commissioning, Operate, Winter Shut Down

1. This item consists of Work shown in drawings.

a. Startup and Commissioning: Responsible for coordination with Arizona

Department of Environmental Quality (ADEQ) for start-up and commissioning for approval to operate, issued by ADEQ.

b. Operations: Provide licensed Arizona Grade 3 Wastewater Treatment Operator for commissioning and operations of the wastewater treatment plant for six months to include winterization and shut down of the plant in November; housing provided at no cost on the North Rim (less than ten minutes’ drive from the wastewater treatment plant).

c. Provide all chemicals and durables for six month operating season.

2. Measurement for payment will be in percentage complete.

3. Payment will be made at the contract lump sum price.

E. Contract Line Item Number 5 (CLIN 5): End Season Pumping and Off-Site Haul Off Disposal

1. This item consists of tank pumping and biosolids removal: Pump and dispose off-site at end of first operating season:

a. EQ Tank: Pump the equalization tank at the end of the first operating season, estimated 20,000 gallons.

b. One MBR Treatment Units: Pump the primary treatment unit tank at the end of the first operating season, estimated 26,550 gallons.

c. Lift station pumping: Influent Lift Station and Filtrate Lift Station, estimated 5,000 gallons.

d. Biosolids Removal: Removal of estimate 17,400 gallons of biosolids from wastewater treatment drying beds.

2. Measurement for payment will be in percentage complete.

3. Payment will be made at the contract lump sum price.

END OF SECTION 01 27 00

GRCA - 318719 01 31 00 - 1

100% Final PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination

3. Submittals

4. Coordination Drawings

5. Requests for Information (RFIs)

6. Project Website

7. Project Meetings

8. Environmental Coordination

9. Permits

B. Related Requirements:

1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.

2. Section 01 35 05 “Environmental Protection and Special Controls” for coordinating environmental requirements of the Contract.

3. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

4. Section 01 75 10 “Checkout and Start-up Procedures for Wastewater Treatment Facilities” for coordinating start-up requires at the North Rim WTP and related facilities.

5. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.

6. Section 01 79 00 “Demonstration and Training” for coordinating training requirements for

Government staff on new equipment.

1.2 DEFINITIONS

A. Agency with Jurisdiction: An Agency that has been granted legal authority over a location, action, or resource. This authority includes the ability to issue a permit or other legal permission document.

B. Construction Permits – Contractor Provided: Permits obtained by the Contractor based on the means and methods to conduct the work. Construction Permits are typically issued by the Agency to the Contractor and not to the National Park Service. Examples of typical Contractor Provided

Permits are: National Pollutant Discharge Elimination System (NPDES) Construction Permit

(ground disturbance), dewatering permit, permit for work in a roadway (with traffic management plan), temporary utility tap permit, etc.

C. Government Furnished Permits: Obtained by NPS, usually through the Architect/Engineer (A/E), during the design process and are usually concerned with impacts to resources protected by federal law. However, GF permits can include other permits that are obtained for the convenience of the

Government during design. GF permits are "furnished" to the Contractor in the Request for

Proposal (RFP) and as part of the final contract documents. The Contractor must comply with GF permit provisions.

http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm

GRCA - 318719 01 31 00 - 2

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.

5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:

1. Preparation of Contractor's Construction Schedule

2. Preparation of the Schedule of Values

3. Installation and removal of temporary facilities and controls

4. Delivery and processing of submittals

5. Progress meetings

6. Permit requirements

7. Pre-installation conferences

8. Project closeout activities

9. Commissioning activities

1.4 SUBMITTALS

A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .