B08__A07_Specifications_Lateral_73_IFC.pdf
PDF 3 MB Posted
- Attached to
- CRIP MC Checks and Lateral 73 Construction Federal contract opportunity
- Solicitation number
- 140A1626R0014
About this file
Summary: Project Manual - CRIP Lateral 73-36 Check 1 Replacement
This is a comprehensive Project Manual containing specifications and general conditions for the construction of a replacement check structure and headgate on the Colorado River Irrigation Project (CRIP) Lateral 73-36 in La Paz County, Arizona, located on the Colorado River Indian Reservation approximately 5.5 miles south of Poston. The project is administered by the Bureau of Indian Affairs Office of Trust Services. The work encompasses general construction activities including excavation, grading, and compaction; construction of a temporary bypass canal system to maintain irrigation operations during construction; demolition of the existing Check 1 structure and headgate; installation of a new permanent long-crested weir (LCW) with cast-in-place concrete, reinforcement, slide gates, walkways, railings, and riprap erosion control; installation of a precast headgate structure with stainless steel slide gate and glass-reinforced fiberglass pipe outlet; and site reclamation and restoration.
The specification document addresses 15 major bid items compensated on a lump-sum basis: Mobilization and Preparatory Work; Water Control, Temporary Bypass, and Construction Dewatering; Site Grading; Structure Excavation, Foundation Improvements, Bedding, and Backfill; Cast-in-Place Concrete; Cast-Iron Slide Gates and Appurtenances; Wooden Weir Crest; Precast Structural Concrete; Stainless Steel Slide Gate and Appurtenances; Pipe Railing, Walkways, and Miscellaneous Metals; Demolition; Glass Reinforced Fiberglass Pipe; Riprap; Roadway Surface Course; and Safety Features and Signage. The contractor must obtain all required permits, comply with environmental protection requirements including MBTA and stormwater management, manage irrigation operations to prevent interruption of water delivery, and coordinate work with annual canal dry-up periods (typically January for Main Canal, February for Lateral 73). Required submittals include detailed schedules of values, construction schedules using Critical Path Method, quality control plans, environmental compliance documentation, and shop drawings. The contractor is responsible for all temporary facilities, dewatering and water control, equipment cleaning, hazardous materials handling, archaeological resource preservation, and final site cleanup, with all costs included in the contract price.
View the file
Other files for this federal contract opportunity
Show all 31
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Manual for
CRIP Lateral 73-36 Check 1 Replacement La Paz County, Arizona
Bureau of Indian Affairs
Office of Trust Services – Division of Water and Power
Prepared By:
Project No. 4626.12494.01 J:\26\12494-01\81Specs\Lat73-36\_CoverPageSpecs.docx
Revised October 2025
ISSUED FOR CONSTRUCTION
CRIP Lateral 73-36 Check 1 Replacement SECTION 00 01 10 La Paz County, Arizona TABLE OF CONTENTS
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\00 01 10 - TOC.docx 00 01 10-1
TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACT REQUIREMENTS
00 01 10 Table of Contents
DIVISION 01 – GENERAL CONDITIONS
01 11 00 Summary of Work 01 12 16 Work Sequence 01 14 00 Work Restrictions 01 29 00 Payment Procedures 01 29 73 Schedule of Values 01 32 16 Construction Progress Schedule 01 33 00 Submittal Procedures 01 46 00 Quality Procedures 01 50 00 Temporary Facilities 01 57 20 Environmental Protection 01 57 90 Preservation of Archaeological Data 01 71 23.16 Construction Surveying 01 74 00 Cleaning and Waste Management 01 78 39 Project Record Documents
DIVISION 02 – EXISTING CONDITIONS
02 26 00 Hazardous Materials Assessment 02 41 00 Demolition
DIVISION 03 – CONCRETE
03 10 00 Concrete Forming and Accessories 03 20 00 Concrete Reinforcing 03 30 00 Cast-In-Place Concrete 03 41 00 Precast Structural Concrete 03 60 00 Grouting
DIVISION 05 – METALS
05 50 01 Miscellaneous Metal Fabrications 05 52 13 Pipe Railings
DIVISION 31 – EARTHWORK
31 00 00 Earthwork 31 05 19 Geosynthetics 31 11 00 Clearing and Grubbing 31 14 10 Topsoil Stripping 31 23 19 Dewatering and Water Control 31 37 00 Riprap
CRIP Lateral 73-36 Check 1 Replacement SECTION 00 01 10 La Paz County, Arizona TABLE OF CONTENTS
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\00 01 10 - TOC.docx 00 01 10-2
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 13 73 Concrete Joint Sealants
DIVISION 33 – UTILITIES
33 05 37 Glass Reinforced Fiberglass Pipe (GRFP)
DIVISION 40 – EQUIPMENT
40 05 59.23 Stainless Steel Slide Gates
END OF SECTION
CRIP Lateral 73-36 Check 1 Replacement SECTION 01 11 00 La Paz County, Arizona SUMMARY OF WORK
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 11 00 - Summary of Work.docx 01 11 00-1
GENERAL
SECTION INCLUDES
This section presents a summary of the principal components of work to be performed and specifications requirements for the Project.
LOCATION
The Project is located on the Colorado River Indian Reservation.
Work is located on and adjacent to the Colorado River Irrigation Project (CRIP) Sublateral 73-36 Check 1, 5.5 miles south of Poston, Arizona, at the intersection of Mark Road and 10th Avenue.
PRINCIPAL COMPONENTS OF WORK
General Construction:
1. Excavation, subgrade improvements, placing and compacting backfill materials, structural fill, pipe bedding/embedment, placing surface coarse aggregate, and finished grading.
2. Complete all work without interrupting irrigation activities as defined in Section 01 14 00
– Work Restrictions.
3. Appropriately manage stormwater runoff.
4. Remove water from work areas and prevent the flow of water into work areas.
Temporary Bypass:
1. Construct a temporary bypass canal/channel of earthen material to divert irrigation water from the work area.
2. Temporarily widen the existing access road as indicated in the Drawings.
3. Construct a temporary check structure to serve the function of Check 1 while the construction of its permanent replacement structure is underway. The temporary check will adequately check the water in Sublateral 73-36 for deliveries to Sublateral 73-36-7.
Long-Crested Weir:
1. Construct a new concrete long-crested weir (LCW) to serve as the permanent replacement structure for Check 1. The LCW and appurtenances include but are not limited to:
a. Cast-in-place concrete.
b. Reinforcement
c. Walkways
d. Slide gates
e. Gate coatings and finishes.
f. Manual hoists
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 11 00 - Summary of Work.docx 01 11 00-2
g. Fasteners and anchorage
h. Steel railings
i. Riprap erosion control
Headgate:
1. Furnish and install a new precast headgate structure and all appurtenances, including but not limited to:
a. Precast concrete headgate structure
b. Slide gate
c. Gate coatings and finishes.
d. Manual hoists
e. Fasteners and anchorage
f. Outlet pipe spanning from the headgate to Sublateral 73-36-7.
g. Precast concrete outlet headwall structure.
Demolition:
1. Demolish the existing Sublateral 73-36 Check 1.
2. Demolish the existing headgate and pipe that supplies Sublateral 73-36-7.
Site Reclamation:
1. Remove the temporary bypass, temporary check structure, and temporary access road widening. Restore the area west of the existing toe of embankment to the conditions indicated in the Drawings.
2. Install new signage and safety features.
SPECIFICATIONS REQUIREMENTS
Imperative statements in these specifications are Contractor requirements unless otherwise stated.
Where specifications are written in streamlined form, the words ‘shall be’ are included by inference where a colon (:) is used within the sentence or phrase.
DEFINITIONS
None.
ABBREVIATIONS/ACRONYMS
CRIP – Colorado River Irrigation Project
CRIT – Colorado River Indian Tribes
BIA – Bureau of Indian Affairs
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 11 00 - Summary of Work.docx 01 11 00-3
USBR – US Bureau of Reclamation
Lat. – Lateral or Sublateral
LCW – Long-Crested Weir
GRFP – Glass Reinforced Fiberglass Pipe
CFS – Cubic Feet per Second
QC – Quality Control
QA – Quality Assurance
ACM – Asbestos-Containing Material
LBP – Lead-Based Paint
PRODUCTS
Not used.
EXECUTION
Not used.
CRIP Lateral 73-36 Check 1 Replacement SECTION 01 12 16 La Paz County, Arizona WORK SEQUENCE
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 12 16 - Work Sequence.docx 01 12 16-1
This section describes the general work sequence anticipated as part of the work included in the Contract Documents. This work sequence outlines the general procedure of work within operational, environmental and property constraints and is intended to minimize the duration of irrigation operation impacts to the extent practicable. The intent is not to be prescriptive but rather to lay out the general sequencing requirements within which the Contractor can determine and employ their own best practices and means and methods.
RELATED SECTIONS
The following list of related specification sections is not intended to be all inclusive.
Section 01 14 00 – Work Restrictions
Section 01 57 20 – Environmental Protection
Section 01 57 90 – Preservation of Archaeological Data
GENERAL RESTRICTIONS
Complete all work without interruption to irrigation operations as defined in Section 01 14 00
– Work Restrictions.
Comply with the infrastructure removal requirements specified in Section 01 57 20 – Environmental Protection, specifically related to Wildlife and Threatened or Endangered Species Habitat Protection.
GENERAL WORK SEQUENCING AND PROJECT PHASING
Temporary Bypass:
1. Perform bank raises and widen the access road adjacent the location of the replacement long-crested weir (LCW) as indicated in the Drawings.
2. Isolate the temporary bypass work area by installing sheetpiles in the existing embankment at the temporary bypass entrance and exit.
3. Construct the temporary check structure and temporary bypass embankment.
4. Remove the sheetpiles placed in Step 2.
5. Construct cofferdams upstream and downstream of the replacement LCW work area to divert irrigation water to the temporary bypass.
Long-Crested Weir:
1. Perform excavation for the replacement LCW as defined in the Drawings.
2. Dewater, moisture condition, and maintain pumps and excavation sumps in the replacement LCW work area as required.
CRIP Lateral 73-36 Check 1 Replacement SECTION 01 12 16 La Paz County, Arizona WORK SEQUENCE
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 12 16 - Work Sequence.docx 01 12 16-2
3. Construct the replacement LCW, including all appurtenances defined in the Contract Documents.
4. Reshape the canal in the dewatered area as defined in the Drawings.
5. Removal of Temporary Bypass:
a. Remove the cofferdams upstream and downstream of the replacement LCW.
b. Rebuild the canal banks at the entrance and exit of the temporary bypass. Remove the temporary check structure. This may require additional sheetpiling; provide specifics in the Temporary Bypass and Check Plan submittal.
c. Remove the temporary bypass embankment and check. Reconstruct the original canal slopes and impacted access roads as shown in the Drawings.
Headgate Replacement:
1. Demolish and replace the Sublateral 73-36 Check 1 headgate and appurtenances.
2. Demolish the existing Sublateral 73-36 Check 1 weir and supporting concrete.
Final Site Reclamation and Grading
1. Complete the final site grading to the lines and grades indicated in the Drawings.
2. Install surface course aggregate on all new roadways and access roads.
3. Restore the area west of the existing toe of embankment to the conditions indicated in the Drawings.
PRODUCTS
Not used.
CRIP Lateral 73-36 Check 1 Replacement SECTION 01 14 00 La Paz County, Arizona WORK RESTRICTIONS
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 14 00 - Work Restrictions.docx 01 14 00-1
This section covers the restrictions for sequencing the work and maintenance of irrigation water.
RELATED SECTIONS
The following list of related specification sections is not intended to be all inclusive.
Section 01 12 16 – Work Sequence
Section 01 57 20 – Environmental Protection
Section 01 57 90 – Preservation of Archaeological Data
IRRIGATION REQUIREMENTS
The Colorado River Irrigation Project provides its water users with irrigation water year-round.
A stipulation of this Contract is that the irrigation canal shall remain operational outside of the dry-up periods to be scheduled by the BIA Representative.
1. The Lateral 73-36 temporary check and long-crested weir is intended to be constructed during a period of active irrigation. Depending on the timing of award, certain elements of work may fall within the annual dry-up period.
2. The Sublateral 73-36-7 headgate is intended to be constructed during the annual Main Canal dry-up.
Water to the Sublateral 73-36 check and Sublateral 73-36-7 headgate will be shut off as part of both the Main Canal and the Later 73 dry-up periods defined herein.
OWNERS REPRESENTATIONS
Typical Dry-up Schedule. CRIP schedules annual canal dry-up periods in the winter months to facilitate project maintenance. Although the exact dry-up dates vary from year to year, the typical schedule is:
1. The Main Canal is drawn down for a two-week period in January.
2. Lateral 73 is drawn down for a one-week period in February.
Expected 2026 Dry-up Schedule
1. Dates have not been established for the 2026 dry-up; however, the Contractor can expect the dry-up to follow the typical schedule defined herein.
Maximum Irrigation Flow Rates
1. BIA reports that the existing Sublateral 73-36 flow capacity upstream of Check 1 is 160 cubic feet per second (cfs).
2. BIA reports that the existing maximum flow rate conveyed by Sublateral 73-36-7 is 60 cfs.
CRIP Lateral 73-36 Check 1 Replacement SECTION 01 14 00 La Paz County, Arizona WORK RESTRICTIONS
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 14 00 - Work Restrictions.docx 01 14 00-2
SITE ACCESS
Provisions for site access are as defined in the Drawings.
ENVIRONMENTAL REQUIREMENTS
Environmental requirements (e.g., allowed timing of vegetation clearing) influence the allowed work sequence. Refer to Section 01 57 20 – Environmental Protection for specific requirements.
PRODUCTS
Not used.
CRIP Lateral 73-36 Check 1 Replacement SECTION 01 29 00 La Paz County, Arizona PAYMENT PROCEDURES
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 29 00 - Payment Procedures.docx 01 29 00 - 1
GENERAL
SECTION INCLUDES
For each bid item, the work will be measured and paid for on either a unit price basis or on a lump sum basis. The quantities provided in the descriptions of the bid items are estimates of the actual quantities of work only and are included solely for guidance in determining the probable cost of work. The actual quantities of work may differ from the quantity estimates provided. The quantities for measurement and payment for unit price bid items shall be as calculated to the neatlines shown on the Drawings. All labor, equipment, materials, and incidentals required to complete the work shall be considered subsidiary to that bid item and will not be paid for separately. The contractor agrees to make no claim for damages, loss of anticipated profits, or otherwise, due to differences between the actual work quantities and the quantity estimates provided.
Payment will be made only for each item included in the bid. No work will be paid for that is not completed in accordance with the Drawings and specifications and accepted by the BIA Representative. No labor, equipment, materials, or incidentals required to complete the work will be furnished by the BIA Representative.
The basis of measurement and payment for each bid item is described below. A general listing of bid items, accompanied by a brief summary of the work, is also provided. The summaries are not intended to completely describe all work. Refer to the Drawings and Specifications for detailed information on each bid item.
MEASUREMENT AND PAYMENT PROCEDURES
Item 1: Mobilization and Preparatory Work
a. This bid item includes, but is not limited to:
i. Furnishing, installing, and removing temporary fencing and construction markers around project work areas and other fencing/security.
ii. Establishing and removing the contractor's offices, buildings, and other facilities.
iii. Obtaining, complying with, and transferring permits.
iv. Installing and maintaining environmental controls for the duration of the construction Contract.
v. Providing required bonds and insurance.
vi. Preparing and maintaining the project schedule.
vii. Delivering and removing the contractor's equipment, supplies, and materials; maintaining the site for the duration of the construction Contract; and final site clean-up and demobilization.
viii. Preparing and securing approvals of submittals.
ix. Preparing record drawings.
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 29 00 - Payment Procedures.docx 01 29 00 - 2
x. General site maintenance and clean-up.
xi. Providing all other related and necessary labor, equipment, and materials to complete the work that are not accounted for in the other bid items.
b. Measurement and payment will be at the Contract lump sum price.
c. Ten (10) percent of the lump sum price will be paid at the time of the first monthly progress payment; an additional forty (40) percent will be paid when one-half of the original contract amount (excluding Mobilization and Preparatory Work) is earned. An additional thirty (30) percent will be paid when two-thirds of the original contract amount (excluding Mobilization and Preparatory Work) is earned. The remaining twenty (20) percent will be paid upon final acceptance of the project.
d. The Contractor may elect to present the BIA Representative with an alternate payment schedule based on a detailed schedule of values. Acceptance by the BIA Representative of the Contractor’s proposed alternate payment schedule is at the sole discretion of the BIA Representative.
Item 2: Water Control, Temporary Bypass, and Construction Dewatering
a. This bid item includes, but is not limited to:
i. Preparing, submitting, and updating Water Control and Dewatering Plans.
ii. Evaluating, designing, constructing, maintaining, replacing, and monitoring water control and dewatering measures.
iii. Constructing and maintaining a temporary bypass and temporary check to allow the CRIP irrigation water to be conveyed around the work zone.
iv. Furnishing and installing all materials, sediment basins, diversion measures, slope drains, check dams, cofferdams, pumps, dewater bags, earth embankments, sheet pile, wells, pipes, culverts, stream crossings, or other material necessary for water control.
v. Disassembly and demobilizing of cofferdams and other dewatering materials and equipment.
vi. Constructing and providing access on a temporary road around the construction zone as shown in the Drawings.
vii. Obtaining and complying with all required permits.
b. Measurement and payment will be at the Contract lump sum price.
c. Fifty (50) percent of the lump sum price for this item will be paid when the temporary check has been installed, cofferdams are in place to isolate the LCW work area, and water is actively flowing in the bypass channel. The remaining fifty (50) percent of the lump sum price for this item will be paid when water is flowing over the new LCW and the temporary check and bypass alignment have been removed and reclaimed.
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 29 00 - Payment Procedures.docx 01 29 00 - 3
d. The Contractor may elect to present the BIA Representative with an alternate payment schedule based on a detailed schedule of values. Acceptance by the BIA Representative of the Contractor’s proposed alternate payment schedule is at the sole discretion of the BIA Representative.
Item 3: Site Grading
a. This bid item includes, but is not limited to:
i. Clearing and grubbing within the construction limits shown on the Drawings.
ii. Grading of the project site surface to the neatlines shown on the Drawings.
iii. Grading and preparation of access roads to bottom of aggregate surface course.
iv. Topsoil replacement and grading.
v. Cleanup and disposal of remaining aggregate, disposal of excess concrete rubble not abandoned on-site, grading of waste materials from excavations, cleanup and disposal of waste concrete materials, and other incidentals to restore the site to pre-disturbance conditions.
b. Measurement and payment will be at the Contract lump sum price.
Item 4: Structure Excavation, Foundation Improvements, Bedding, and Backfill
a. This item consists of excavation and foundation improvements for cast-in-place concrete structures and slabs including the check structure and the precast headwall for Lateral 73-36-7 turn out.
b. This item includes, but is not limited to:
i. Excavation to the subgrade neatlines shown on the Drawings.
ii. Preparing, scarifying, moisture conditioning and compacting subgrade.
iii. Hauling, stockpiling, reusing, or wasting excess excavated material.
iv. Furnishing and installing stabilization geotextile.
v. Importing and placing structural foundation fill and pipe bedding materials.
vi. Structure backfill and embankment fill.
vii. Quality control testing of the placed materials
viii. All earthwork not included in other bid items.
ix. All labor, equipment, and materials necessary to meet compaction requirements shall be considered incidental.
c. Measurement and payment will be at the Contract lump sum price.
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 29 00 - Payment Procedures.docx 01 29 00 - 4
Item 5: Cast-in-Place Concrete
a. This item consists of furnishing and installing reinforced concrete to construct the LC73-36-7 check structure, operator walkways and other appurtenances.
b. This bid item includes, but is not limited to:
i. Furnishing all labor, equipment, and materials required for or incidental to the construction of cast-in-place concrete structures.
ii. Forming, reinforcement, embedments, concrete mix materials, installing, finishing, curing and protection, knockouts, saw cutting, chipping, doweling, bonding agents, water stops, joints, and all other incidentals.
iii. Quality control testing of cast-in-place concrete.
c. Measurement and payment will be at the Contract lump sum price.
Item 6: Cast-Iron Slide Gates and Appurtenances
a. This item consists of furnishing and installing cast-iron slide gates for the new
LCW.
b. This bid item includes, but is not limited to:
i. Furnishing all labor, equipment, and materials necessary for installing Contractor-furnished cast-iron canal gates, gate stem, gearboxes, and all other incidentals.
ii. This item also includes providing and installing all hardware and anchorage necessary for installation of Contractor-furnished Materials.
iii. This item also includes providing all labor, equipment, and materials necessary for field directed testing required by the BIA Representative.
c. Measurement and payment will be at the Contract lump sum price.
Item 7: Wooden Weir Crest
a. This item consists of installing Contractor-furnished wooden weir crest on top of the LCR at LC73-36-1.
a. This bid item includes, but is not limited to:
i. Furnishing all labor, equipment, and materials to fabricate and install the wooden weir crest conforming to the weir crest dimensions shown on the Drawings.
b. Measurement and payment will be at the Contract lump sum price.
Item 8: Precast Structural Concrete
c. This item consists of furnishing and installing reinforced concrete to construct the new L73-36-7 headgate structure, operator, and other appurtenances.
d. This bid item includes, but is not limited to:
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 29 00 - Payment Procedures.docx 01 29 00 - 5
i. Furnishing all labor, equipment, and materials required for or incidental to the construction of pre-cast concrete structures.
ii. Forming, reinforcement, embedments, concrete mix materials, installing, finishing, curing and protection, knockouts, saw cutting, chipping, doweling, bonding agents, water stops, joints, and all other incidentals.
iii. Quality control testing of pre-cast concrete.
e. Measurement and payment will be at the Contract lump sum price.
Item 9: Stainless Steel Slide Gate and Appurtenances
f. This item consists of furnishing and installing stainless steel slide gate for the new headgate outlet for L73-36-7.
g. This bid item includes, but is not limited to:
i. Furnishing all labor, equipment, and materials necessary for installing Contractor-furnished stainless steel slide gate, wall thimble, gearboxes, and all other incidentals.
ii. This item also includes providing and installing all hardware and anchorage necessary for installation of Contractor-furnished Materials.
iii. This item also includes providing all labor, equipment, and materials necessary for field directed testing required by the BIA Representative.
h. Measurement and payment will be at the Contract lump sum price.
Item 10: Pipe Railing, Walkways, and Miscellaneous Metals
a. This item consists of providing and installing the pipe railings and any other miscellaneous metals associated with the LC73-36-1 Check structure, and the new headgate for L73-36-7 inlet.
b. This bid item includes, but is not limited to:
i. Furnishing all materials, tools, equipment, and labor necessary to provide and install pipe railings, chain railings, weir crest brackets, bulkhead channels, and any other miscellaneous metals in accordance with the Contract Documents.
ii. Structural steel, bar grating, anchors, and fasteners.
iii. Supplying and installing any miscellaneous metal work not specifically included in another item is considered incidental to the pipe railings and miscellaneous metals.
c. Measurement and payment will be at the Contract lump sum price.
Item 11: Demolition
a. This bid item includes, but is not limited to:
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 29 00 - Payment Procedures.docx 01 29 00 - 6
i. Demolition, selective demolition, and disposal of all features designated for removal in the Contract Documents including existing concrete, rebar, steel, anchorage, reinforcement, slide gate, gate appurtenances, hoists, platforms, railings, and walkways.
ii. Legal disposal at an off-site facility.
iii. Salvaging any materials specifically identified in the Contract Documents as to be salvaged.
iv. Removal of loose material and any cleaning necessary or incidental to demolition.
v. Protection of existing structures and materials not designated for removal.
b. Measurement and payment will be at the Contract lump sum price.
Item 12: Glass Reinforced Fiberglass Pipe and Fittings
a. This item consists of furnishing, and installing GRFP as the outlet culvert for L73-36-7 headgate.
b. This bid item includes, but is not limited to:
i. Furnishing all materials, tools, equipment, and labor necessary to provide and install the glass reinforced fiberglass pipe described in the Specifications.
ii. Installing all joints and fittings as shown in the Drawings.
iii. This item also includes providing all labor, equipment, and materials necessary for video inspections and field directed testing required by the BIA Representative.
c. Measurement and payment will be at the Contract lump sum price.
Item 13: Riprap
d. This item consists of furnishing, and placing riprap as shown on the drawings.
e. This bid item includes, but is not limited to:
i. All labor, equipment, and materials necessary to install riprap armoring at the bypass channel, permanent check, and headgate as shown in the Drawings.
ii. Furnishing and installing stabilization geotextile.
f. Measurement and payment will be at the Contract lump sum price.
Item 14: Roadway Surface Course
g. This item consists of furnishing, placing, and compacting surface course aggregates to complete all access road improvements included in the work.
h. This bid item includes, but is not limited to:
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 29 00 - Payment Procedures.docx 01 29 00 - 7
i. Furnishing all labor, equipment, and materials associated with surfacing the access roads at the locations specified in the Construction Drawings.
i. Measurement and payment will be at the Contract lump sum price.
Item 15: Safety Features, and Signage
a. This item consists of furnishing and installing all bollards, and signage indicated in the Drawings.
b. This bid item includes, but is not limited to:
i. Furnishing all labor, equipment, and materials to provide signage, posts, and pipe bollards shown on the Construction Drawings.
c. Measurement and payment will be at the Contract lump sum price.
PRODUCTS
Not Used
EXECUTION
Not Used
CRIP Lateral 73-36 Check 1 Replacement SECTION 01 29 73 La Paz County, Arizona SCHEDULE OF VALUES
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 29 73 - Schedule of Values.docx 01 29 73-1
This Section defines the process whereby the Contractor will develop the Schedule of Values (lump sum price breakdown) for review and approval by the BIA Representative.
Monthly progress payment amounts for some bid items will be determined from the in-progress status (i.e., estimated percent complete) of the work features identified in Section 01 29 00 – Payment Procedures.
SUBMITTALS
Submit the following in accordance with Section 01 33 00 – Submittals.
Approval Submittals
1. 01 29 73-1, Schedule of Values
a. Prepare and submit a detailed Schedule of Values for every work feature within 30 days from the date of Award or 14 days prior to the Pre-Construction Meeting, whichever occurs first.
b. The schedule of values must be sufficiently detailed to determine appropriate monthly progress payments.
c. The BIA Representative will be the sole judge of acceptable numbers, details, and descriptions of values established.
d. Adjustments and Acceptance
i. During the Pre-Construction Meeting, the level of detail and value allocations will be discussed to determine if the Schedule of Values provides an acceptable level of detail to support interim progress payments for the work features. The CO’s review of the Schedule of Values submittal shall be returned to Contractor within 7 days following the Pre-Construction Conference.
ii. Make necessary adjustments to the level of detail and/or value allocation and submit a revised Schedule of Values within 7 Days from the date of receiving the CO’s review comments.
Informational Submittals
None.
PRODUCTS
Not used.
EXECUTION
CRIP Lateral 73-36 Check 1 Replacement SECTION 01 32 16 La Paz County, Arizona CONSTRUCTION PROGRESS SCHEDULE
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 32 16 - Construction Schedule.docx 01 32 16-1
This section covers the requirements for developing the baseline construction schedule and updating and maintaining the construction program.
REFERENCE STANDARDS
Associated General Contractors of America (AGC)
1. AGC Manual – Construction Planning and Scheduling Manual
DEFINITIONS
Schedule: Construction schedule using the Critical Path Method (CPM) of planning and scheduling a construction project. Activities are arranged based on activity relationships and network calculations identifying the “critical activities” that determine the earliest completion date.
Project Calendars: Cross reference between the number of workdays and calendar days. The project calendar serves as the basis for the day/date conversion and assigns workdays and non-workdays.
Resources: Equipment, labor or crews, materials, subcontractors, fabricators, manufacturers, and consultants.
SUBMITTALS
Submit the following in accordance with Section 01 33 00 – Submittals.
Approval Submittals
1. 01 32 16-1, Representative Information
a. Designation of authorized representative to develop and maintain the Construction Program. Representative shall be experienced in developing and maintaining construction schedules and knowledgeable of activities and progress on-site to develop and maintain accurate and reliable schedules.
2. 01 32 16-2, Baseline Schedule
a. Include:
b. Definition of project calendars.
c. Gantt Chart (bar chart) for project.
d. Narrative of the construction sequence.
e. Activity report including all logic constraints consisting of predecessors, successors, and constraint dates.
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 32 16 - Construction Schedule.docx 01 32 16-2
f. Table listing equipment, manpower, and material limitations used to produce baseline schedule.
3. 01 32 16-3, Updated Schedule
a. Include:
b. Updated activity and milestone schedule summary.
c. Definition of project calendars if revised from baseline calendars.
d. Gantt chart for project.
e. Narrative report specifically stating status of project.
i. If negative float exists, cite specific actions and conditions which caused the “behind schedule” condition and provide proposed course of action to complete the project within the specified delivery time.
ii. List of Contractor-initiated changes to the current schedule, including the reason for the change and any unresolved issues relating to the Construction Program. COR and Owner Representative reserve the right to reject Contractor-initiated changes to the approved schedule.
4. 01 32 16-4, Time Impact Analysis
a. Include:
b. Construction Program database with proposed revised activity and milestone data.
c. Proposed schedule revisions, specifically identifying changed or deleted activities and the impact on the completion date.
d. Narrative report explaining results and conclusions
e. Proposed schedule revisions, specifically identifying changed or deleted activities and the impact on the completion date.
f. Narrative report explaining results and conclusions.
Informational Submittals
None.
CONSTRUCTION SEQUENCE
Prepare construction schedules using CPM, under concepts and methods outlined in the AGC Manual.
1. Establish workday calendar(s) and use these in the schedule to translate the activity’s workday duration into calendar dates. Use calendar names unique for this project, do not use software default calendar names. Save calendars as project calendars, not global calendars.
2. Prepare schedule based on required sequence and interdependence of activities.
3. Prepare detailed activity network for accomplishing required work organized by Work Breakdown Structure (WBS).
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 32 16 - Construction Schedule.docx 01 32 16-3
4. Activities except “Award” shall have predecessor activities and activities except “Contract Complete” shall have successor activities.
5. Include dates for interim milestones, critical interface events for BIA Representative, time or seasonal constraints specified in the contract documents, and contract completion.
6. Include work to be performed by subcontractors.
7. Develop the Construction Program to account for seasonal weather conditions.
8. If activity codes are utilized, use unique activity code names assigned as project codes rather than global codes. Utilize the WBS, in lieu of activity codes, for general organization of the schedule.
9. Define activities to a level of detail to result in no single activity having a duration greater than 20 workdays, unless otherwise accepted by BIA Representative.
a. Durations for administrative activities (e.g., submittals and reviews, fabrication, manufacturing) or other specific activities identified in the contract will not be subject to the workday limitation.
10. Include activities for BIA Representatives review and approval. Assign submittal review activities to a 7-day calendar with durations as specified in Section 01 33 00 – Submittals.
Include activities for issuance of submittals, submittal reviews, and fabrication or manufacturing activities when work involves significant quantities, long lead times, is on the critical path, or as requested by the BIA Representative.
11. Include contract title, contract number, and Contractor’s name on each sheet of the Gantt chart.
12. For each activity on the Gantt chart, display identification number, activity description, planned duration, start date, finish date, total float, and calendar identification.
13. Include table of abbreviations used in the schedule, listed, and defined alphabetically.
14. Use durations in units of whole workdays.
15. Equate durations for BIA Representative reviews and other identified actions to the maximum number of calendar days specified in their respective paragraphs.
Baseline Schedule:
1. Represents Contractor’s as-planned approach to accomplishing the work. Does not include actual start dates, percent completes, or actual finish dates.
Updated Schedule:
1. Meet weekly with the BIA Representative at a location approved by the BIA Representative, to review progress. Establish dates that activities were started and completed, discuss remaining durations for each activity started but not yet completed.
a. Discuss schedule status and identify potential negative schedule impacts.
b. Submit revised schedule that accurately identifies actual start/finish dates, identifies corrective actions to recover schedule, or request approval to extend the construction schedule.
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 32 16 - Construction Schedule.docx 01 32 16-4
2. Provide a 3-week look-ahead schedule at weekly progress meetings.
3. Following receipt of an executed contract Modification, incorporate the activity data and logic relationships stipulated in the modification into the schedule for discussion at the next progress meeting.
4. The project schedule shall be updated and submitted to the BIA Representative for approval with the Contractor’s monthly progress payment.
5. Assign a unique project file name to each schedule update issued. Schedule updates shall be issued as a pdf and comply with the following file naming convention:
YYMMDD_CRIP Lateral 73-36 Check 1 Replacement Schedule Update.pdf
TIME IMPACT ANALYSIS
Provide a time impact analysis for contract changes, e.g., a change order, proposed modification, or value engineering change proposal, to support a claim or request for an equitable adjustment to the contract that involves a delay or accelerated schedule.
The BIA Representative may use the time impact analysis to determine if a time extension or reduction to the contract milestone dates is justified.
A time impact analysis is applicable whether the Contractor’s current schedule milestone dates are the same as, earlier, or later than those required under the contract.
Changes, additions, or deletions to activities, activity durations, or activity time frames will not automatically mean that an extension or reduction of contract time is warranted.
Time extensions for performance will be considered only to the extent that the Contractor’s current scheduled milestone dates exceed the contract milestone dates.
For each activity directly affected by a change or delay, include the current and proposed items:
1. Activity description
2. Types and quantities of major pieces of equipment, principal manpower, and pacing materials (materials that affect activity start, duration, or finish).
3. Activity duration.
4. A narrative containing the rationale used in developing the proposed logic relationships and activity data.
Float is not for the exclusive use by, or benefit of, either the BIA Representative or the Contractor.
Prepare a single time impact analysis for modifications issued after Notice to Proceed (NTP) and prior to approval of the baseline schedule. Submit the time impact analysis with the baseline schedule submittal.
Perform time impact analyses using data in the current, approved schedule at the time of the change or delay event.
1. Prepare proposed revised schedule and narrative description describing and highlighting where changes or delays are included.
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 32 16 - Construction Schedule.docx 01 32 16-5
2. Prepare summary comparing the results of two schedule analyses: One using current schedule data, and one using proposed schedule data incorporating the changes or delays.
a. Show contract milestone and activities whose periods of performance have shifted.
b. Base mathematical analyses on status of work and available float from the time the CO directs or proposes changes to the work, the Contractor submits a value engineering change proposal, or when a delay occurs.
REVIEW AND EVALUATION
Baseline Schedule:
1. Within 14 calendar days after receipt of baseline schedule:
a. BIA Representative will accept or reject the proposed baseline schedule.
b. If schedule is rejected, revise and resubmit within 7 calendar days following the date of rejection.
2. Do not proceed with onsite work, except for mobilization and survey, until baseline schedule has been accepted.
Updated Schedules:
1. The BIA Representative will require 7 calendar days after receipt of each monthly update to review and accept or reject the updated schedule.
2. If the updated schedule is rejected, revise, and resubmit updated schedule within 2 calendar days following the date of the rejection letter.
3. The BIA Representative will schedule a pre-submittal meeting with the Contractor’s representative to review a draft updated schedule prior to the Contractor submitting the monthly Updated Schedule. Contractor will be required to provide weekly schedules starting one week before Phase 2 and for the duration of Phase 2. Contractor and BIA Representative will conduct a pre-submittal meeting two days before each Updated Schedule is submitted.
Failure to include any element of the work in the schedule will not release Contractor from completing work required by the contract.
PRODUCTS
Not used.
CRIP Lateral 73-36 Check 1 Replacement SECTION 01 33 00 La Paz County, Arizona SUBMITTAL PROCEDURES
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 33 00 - Submittal Procedures.docx 01 33 00-1
GENERAL
SECTION INCLUDES
This section covers the requirements for submittals by the Contractor of descriptive information that will enable a determination of whether the Contractor’s proposed materials, equipment, and work methods are in general conformance to the design concept and in accordance with the specifications.
REQUIRED SUBMITTALS
Consists of:
Permits
Drawings
Product Data
Certifications
Manuals, Shop Drawings, and Specialized Tools
Samples
Test Reports
DEFINITIONS
Days: Calendar days.
Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
Submittal Types, as listed in Table 01 33 00A – List of Submittals:
A – Approval:
a. BIA Representative will accept or reject Approval submittals.
I – Informational:
a. The BIA Representative will acknowledge receipt and acceptance of these submittals.
b. The BIA Representative may request additional clarification, information, and/or documentation on the content of an informational submittal. If the BIA Representative arrives at different conclusions than described by the informational submittal, the BIA Representative may provide recommendations for Contractor’s consideration.
SUBMITTAL REQUIREMENTS
In case of conflict between requirements of this section and requirements included elsewhere
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 33 00 - Submittal Procedures.docx 01 33 00-2 in these specifications, requirements included elsewhere take precedence.
Submittal Letter of Transmittal:
Contract number.
Project name.
RSN.
List of documents/content included with the submittal.
Relevant discussion and/or information that the BIA should be aware of to effectively review and fully understand the submittal content.
Statement that the submittal has been reviewed and approved by the Contractor’s authorized representative.
Signature of Contractor’s authorized representative.
SUBMITTAL CONTENT
Provide a complete submittal package: Include all documentation and information necessary to satisfy the submittal requirements. If an incomplete submittal package is submitted for review, identify what elements are missing and the reason those elements were omitted. The BIA Representative reserves the right to reject partial submittals.
Product Data Sheets: For manufacturer data with multiple items, the elements being submitted for review shall be clearly identified.
Certifications:
Certifications by a registered professional: Signed and sealed by registered professional.
Manufacturer’s certifications: Signed by authorized representative of manufacturer.
SUBMITTALS PROCEDURES
Contractor shall review and approve all submittals prior to submitting them. Submittals without evidence of Contractor’s approval will be returned for resubmission.
Submittals shall be submitted electronically in portable document file (pdf) format through a web-based portal. Submittals that cannot be submitted electronically, such as material/product samples, shall be submitted to the BIA Representative. Note that in the case of product samples, four samples shall be submitted.
Distribution and review status of individual submittals shall be administered through the web-based portal.
Reviewed submittals and submittal disposition shall be returned/sent to the Contractor electronically in pdf format.
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 33 00 - Submittal Procedures.docx 01 33 00-3
REVIEW OF SUBMITTALS
Time Required:
Submittal review will require 28 days for review of each submittal or resubmittal, unless otherwise specified.
The review period for a submittal (or resubmittal) begins when a complete submittal package is received.
Time in Excess of Specified:
The BIA Representative may extend the contract completion date to complete work adversely affected by excess review time.
a. The time extension will be to the extent that excess review time caused delay to the contract completion date.
b. The time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.
c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending the time.
No time extension will be allowed if the Contractor fails to account for the specified review time in the project schedule.
Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work, however, no such delay shall be deemed to be a "suspension order" as the term is used in that clause.
Return of Submittals:
Submittals will be returned either approved, approved as noted, not approved, or acknowledging receipt.
For submittals not approved:
a. Revise and resubmit for approval.
b. Show changes and revisions.
c. Resubmit returned submittals within 28 days after receiving the comments.
d. In the resubmittal transmittal letter, describe how the submittal was revised and how comments on the initial (or previous) submission were addressed.
PRODUCTS
Not Used
Not Used
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 33 00 - Submittal Procedures.docx 01 33 00-4
THIS PAGE IS INTENTIONALLY LEFT BLANK
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 33 00 - Submittal Procedures.docx 01 33 00 -5
Table 01 33 00A – List of Submittals
Submittal No. Section Title Submittals Required When to Submit Type
01 29 73-1 Schedule of Values Schedule of Values Within 30 days from the date of Award A
01 32 16-1 Construction Progress Schedule
Representative Information At least 28 days before beginning on-site activities A
01 32 16-2 Construction Progress Schedule
Baseline Schedule At least 28 days before beginning on-site activities A
01 32 16-3 Construction Progress Schedule
Updated Schedule Within 7 days of change in schedule A
01 32 16-4 Construction Progress Schedule
Time Impact Analysis Within 7 days of change in schedule A
01 46 00-1 Quality Procedures Quality Procedures Plan At least 28 days before beginning on-site activities A
01 50 00-1 Temporary Facilities Traffic Control Plan At least 28 days before beginning on-site activities A
01 50 00-2 Temporary Facilities Temporary Facilities Plan At least 28 days before beginning on-site activities A
01 57 20-1 Environmental Protection Spread of Noxious Weed Prevention
At least 28 days before beginning on-site activities A
01 57 20-2 Environmental Protection Environmental Inspector Quals. At least 28 days before beginning on-site activities A
01 57 20-3 Environmental Protection MBTA Compliance At least 28 days before beginning on-site activities A
01 57 20-4 Environmental Protection USFWS Relocation Permit At least 28 days before beginning on-site activities A
01 57 20-5 Environmental Protection Stormwater Pollution Prevention Plan (SWPPP)
At least 14 days before beginning on-site activities I
01 57 20-6 Environmental Protection Environmental Inspection Results Within 7 days of test I
01 71 23.16-1 Construction Surveying As Built Survey Within 14 days of completion of on-site activities A
01 71 23.16-2 Construction Surveying Resume At least 14 days before beginning on-site activities I
01 71 23.16-3 Construction Surveying Control Survey Verification At least 7 days before beginning on-site activities I
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 33 00 - Submittal Procedures.docx 01 33 00 -6
Submittal No. Section Title Submittals Required When to Submit Type
01 71 23.16-4 Construction Surveying Completed and Reduced Survey Notes
Within 1 day of completed survey activity I
01 71 23.16-5 Construction Surveying Workday Survey Notes When requested by BIA Representative I
01 74 00-1 Cleaning and Waste Management
Waste Production and Disposal Records
Within 14 days of completion of on-site activities I
01 74 00-2 Cleaning and Waste Management
Hazardous Waste Disposal Certification
Within 14 days of completion of on-site activities I
01 78 39-1 Project Record Documents Final Record Drawings Within 14 days of completion of on-site activities A
02 41 00-1 Demolition Demolition Plan At least 14 days before beginning on-site activities A
03 10 00-1 Concrete Forming and Acc. Product Data At least 28 days before first placement A
03 10 00-2 Concrete Forming and Acc. Shop Drawings At least 14 prior to erection of formwork I
03 20 00-1 Concrete Reinforcing Product Data At least 28 days before first placement A
03 20 00-2 Concrete Reinforcing Piece Detail and Placement Drawings
At least 28 days before first placement A
03 20 00-3 Concrete Reinforcing Construction Joint Layout At least 28 days before first placement A
03 20 00-4 Concrete Reinforcing Material Test Reports At least 28 days before first placement A
03 30 00-1 Cast-in-place Concrete Materials and Product Data At least 28 days before first placement A
03 30 00-2 Cast-in-place Concrete Design Mixes At least 28 days before first placement
A
03 30 00-3 Cast-in-place Concrete Concrete Placement Plan At least 28 days before first placement A
03 30 00-4 Cast-in-place Concrete Qualification Data At least 28 days before beginning on-site activities I
03 30 00-5 Cast-in-place Concrete Material Certificates At least 28 days before beginning on-site activities I
03 30 00-6 Cast-in-place Concrete Material Test Reports At least 28 days before beginning on-site activities I
03 30 00-7 Cast-in-place Concrete Preconstruction Test Reports At least 28 days before beginning on-site activities I
\\dowl.com\j\Projects\26\12494-01\81Specs\Lat73-36\01 33 00 - Submittal Procedures.docx 01 33 00 -7
Submittal No. Section Title Submittals Required When to Submit Type
03 41 00-1 Precast Structural Concrete Product Data At least 28 days before fabrication A
03 41 00-2 Precast Structural Concrete Design Mixture At least 28 days before fabrication A
03 41 00-3 Precast Structural Concrete Shop Drawings At least 28 days before fabrication A
03 41 00-4 Precast Structural Concrete Qualification Data At least 28 days before first placement I
03 41 00-5 Precast Structural Concrete Material Certificates At least 28 days before first placement I
03 41 00-6 Precast Structural Concrete Material Test Reports With delivery I
03 41 00-7 Precast Structural Concrete Preconstruction Test Reports At least 28 days before fabrication I
03 41 00-8 Precast Structural Concrete Source Quality Control Reports At least 28 days before fabrication I
03 60 00-1 Grouting Product Data At least 28 days before first placement A
03 60 00-2 Grouting Manufacturer Instructions At least 14 days before first placement I
03 60 00-3 Grouting Manufacturer’s Certificate At least 14 days before first placement I
05 50 01-1 Miscellaneous Metal Fabrications
Shop Drawings At least 28 days prior to fabrication A
05 50 01-2 Miscellaneous Metal Fabrications
Grating Layout Drawings At least 28 days prior to fabrication A
05 50 01-3 Miscellaneous Metal Fabrications
Concrete Anchor Reports At least 14 days before beginning related work A
05 50 01-4 Miscellaneous Metal Fabrications
Welding Data At least 14 days before fabrication I
05 52 13-1 Pipe Railings Approved Drawings and Product Data
At least 28 days prior to fabrication A
31 00 00-1 Earthwork Aggregate Gradations, Classifications, and Moisture- Density Relationships
At least 28 days before first placement A
31…