B08__A05_Specifications_MC420_IFC.pdf

PDF 10 MB Posted

Attached to
CRIP MC Checks and Lateral 73 Construction Federal contract opportunity
Solicitation number
140A1626R0014
Issued by
Department of the Interior Bureau of Indian Affairs Central Office

About this file

This is a Project Manual and detailed specification document for the CRIP MC420 Check Replacement project located on the Colorado River Indian Reservation in La Paz County, Arizona, under the Bureau of Indian Affairs Office of Trust Services. The project involves demolition of the existing Main Canal Check 420 structure and construction of a new replacement with integrated radial gate, electrical systems, instrumentation, and process control capabilities.

The scope includes three phases: Phase 1 constructs the new off-line MC420 check structure, radial gate, control building, and electrical systems prior to canal drawdown; Phase 2 executes upstream and downstream canal tie-ins during a scheduled two-week January drawdown period; and Phase 3 completes demolition and site reclamation. Major work components encompass demolition of existing structures, excavation and earthwork with compaction testing requirements, reinforced concrete construction (estimated 4,500 psi strength), radial gate fabrication with cathodic protection and coating systems, stainless steel stop logs, electrical service installation (3-phase 208V), SCADA process control system integration with remote access capabilities, instrumentation including SonTek flow meters and water level sensors, gate hoist assemblies with position transmitters, and complete site revegetation. The specifications mandate single-source procurement for major equipment, extensive factory and field acceptance testing, detailed submittals with sealed professional engineer certifications, quality control testing with independent laboratories, and comprehensive operations and maintenance manuals. Contractor responsibilities include water control and dewatering throughout construction, environmental compliance with stormwater pollution prevention plans and migratory bird protection requirements, archaeological resource preservation, and coordination with ongoing irrigation operations to maintain water delivery outside the construction window.

View the file

Other files for this federal contract opportunity

Other files attached to CRIP MC Checks and Lateral 73 Construction, newest first.
File Type Posted
B08_Solicitation_140A1626R0014__Sections_D-M-REV_1_Apr_2026_0001.pdf PDF
B08_Q_A_Log_1_Apr_2026_0001.xlsx XLSX spreadsheet
B08__A05_Specifications_MC420_IFC-REV_1_Apr_2026_0001.pdf PDF
Sol_140A1626R0014_Amd_0001.pdf PDF
B08__A01_Pricing_Schedule-REV_1_Apr_2026_0001.pdf PDF
B08__A23_Solicitation_Questions_and_Answers_Log.xlsx XLSX spreadsheet
B08__A03_Statement_of_Work_Lateral_73.pdf PDF
B08__A14_Historic_Drawings_MC420.pdf PDF
B08__A22_PreBid_Site_Visit_Overview_and_Field_Review.pdf PDF
B08__A26_SF-25A_Payment_Bond_Form.pdf PDF
B08__A19_Asbestos_Assessment_Survey_Lateral_73.pdf PDF
B08__A11_Drawings_MC420_Electrical_Transmission.pdf PDF
Sol_140A1626R0014.pdf PDF
B08__A02_Statement_of_Work_Main_Canal_Checks.pdf PDF
B08__A17_Geotechnical_Data_Report_Lateral_73.pdf PDF
B08__A15_Historic_Drawings_Owner_Furnished_Gates.pdf PDF
B08__A08_Drawings_MC185_IFC.pdf PDF
B08__A10_Drawings_MC420_IFC.pdf PDF
B08__A13_Historic_Drawings_MC270.pdf PDF
B08__A04_Specifications_MC185_270_IFC.pdf PDF
B08__A21_DOL_Wage_Rates_AZ20260007_and_AZ20260052.pdf PDF
B08__A09_Drawings_MC270_IFC.pdf PDF
B08__A24_SF-24_Bid_Bond_Form.pdf PDF
B08__A25_SF-25_Performance_Bond_Form.pdf PDF
B08__A01_Pricing_Schedule.pdf PDF
B08__A20_Groundwater_Monitoring_Report_MC185_MC270_MC420.pdf PDF
B08__A06_Specifications_M420_Electrical_Transmission.pdf PDF
B08__A07_Specifications_Lateral_73_IFC.pdf PDF
B08__A12_Drawings_Lateral_73_IFC.pdf PDF
B08__A18_Asbestos_Assessment_Survey_MC185_MC270_MC420.pdf PDF
B08__A16_Geotechnical_Data_Report_MC185_MC270_MC420.pdf PDF
Show all 31

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Manual for

CRIP MC420 Check Replacement La Paz County, Arizona

Bureau of Indian Affairs

Office of Trust Services – Division of Water and Power

Prepared By:

Project No. 4626.12494.01 J:\26\12494-01\81Specs\MC420\00_CoverPageSpecs.docx

Revised October 2025

Issued for Construction

THIS PAGE INTENTIONALLY LEFT BLANK

CRIP MC420 Check Replacement SECTION 00 01 10 La Paz County, Arizona TABLE OF CONTENTS

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\00 01 10 - TOC.docx 00 01 10 -1

TABLE OF CONTENTS

DIVISION 00 – PROCUREMENT AND CONTRACT REQUIREMENTS

00 01 10 Table of Contents

DIVISION 01 – GENERAL CONDITIONS

01 11 00 Summary of Work 01 12 16 Work Sequence 01 14 00 Work Restrictions 01 18 13 Utility Service Connections 01 29 00 Payment Procedures 01 29 73 Schedule of Values 01 32 16 Construction Schedule 01 33 00 Submittal Procedures 01 46 00 Quality Procedures 01 50 00 Temporary Facilities 01 57 20 Environmental Protection 01 57 90 Preservation of Archaeological Data 01 71 23.16 Construction Surveying 01 74 00 Cleaning and Waste Management 01 78 39 Project Record Documents

DIVISION 02 – EXISTING CONDITIONS

02 26 23 Asbestos Assessment 02 41 00 Demolition

DIVISION 03 – CONCRETE

03 10 00 Concrete Forming and Accessories 03 20 00 Concrete Reinforcing 03 30 00 Cast-In-Place Concrete 03 37 13 Shotcrete 03 41 00 Precast Structural Concrete 03 60 00 Grouting

DIVISION 05 – METALS

05 05 13 Shop-Applied Coatings for Metal 05 50 01 Miscellaneous Metal Fabrications 05 52 13 Pipe Railings

DIVISION 13 – SPECIAL CONSTRUCTION

13 34 23 Fabricated Control Building

DIVISION 26 – ELECTRICAL

26 05 01 Basic Electrical Requirements

CRIP MC420 Check Replacement SECTION 00 01 10 La Paz County, Arizona TABLE OF CONTENTS

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\00 01 10 - TOC.docx 00 01 10 -2

26 05 05 Selective Electrical Demolition 26 05 19 Conductors and Cables 26 05 26 Grounding 26 05 29 Hangers and Supports 26 05 33 Raceways and Boxes 26 05 53 Identification 26 05 73 Power Systems Studies 26 24 16 Panelboards 26 27 26 Wiring Devices 26 28 16 Enclosed Switches and Breakers 26 36 13 Manual Transfer Switch 26 51 19 LED Lighting

DIVISION 31 – EARTHWORK

31 00 00 Earthwork 31 05 19 Geosynthetics 31 11 00 Clearing and Grubbing 31 14 10 Topsoil Stripping 31 23 19 Dewatering and Water Control 31 23 23 Controlled Low Strength Material

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 13 73 Concrete Joint Sealants 32 31 10 Fencing 32 92 19 Revegetation

DIVISION 33 - UTILITIES

33 05 97 Staff Gages

DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION

35 22 46 Radial Gates

DIVISION 40 – EQUIPMENT

40 05 59.16 Stainless Steel Stop Logs 40 61 13 Process Control System 40 63 13 Hoist Control Panel 40 63 83 Remote Terminal Units 40 66 43 Wireless Network Systems 40 70 00 Instrumentation for Process Systems

DIVISION 51 – ADDITIONAL INFORMATION

51 00 20 Canal Flow Data 51 00 30 Historic Drawings

END OF SECTION

CRIP MC420 Check Replacement SECTION 01 11 00 La Paz County, Arizona SUMMARY OF WORK

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 11 00 - Summary.docx 01 11 00-1

GENERAL

SECTION INCLUDES

This section presents a summary of the principal components of work to be performed and specifications requirements for the project.

LOCATION

Project is located on the Colorado River Indian Reservation.

Work is located on and adjacent to the Colorado River Irrigation Project (CRIP) Main Canal Check 420 (MC420), south of Indian School Road and east of 4th Ave, approximately 0.75 miles east of the intersection of 4th Avenue and Indian School Road.

PRINCIPAL COMPONENTS OF WORK

Demolition:

1. Demolish existing Main Canal check structure (MC420) and all appurtenances.

2. Demolish existing electrical and control equipment and enclosure.

3. Demolish existing canal and slope paving from approximate station range 418+13 to 431+25; and

4. Properly remove and dispose of radial gates, gate appurtenances, electrical equipment, and materials identified on the drawings.

Site Construction:

1. Managing stormwater runoff.

2. Removing water from work areas and controlling water to prevent flow into work areas;

and

3. Clearing, vegetation removal, topsoil management, excavation, subgrade improvements, and finished grading.

Radial gate:

1. Fabricate, furnish and install new radial gate and all appurtenances, including but not limited to;

a. Gate cathodic protection,

b. Gate coatings and finishes,

c. Gate Hoist Assembly, including but not limited to: hoist base, motor, control panel, cross shaft, and wire rope drums.

d. Fasteners and anchorage,

e. Side seal rubbing plates and bottom sill plate.

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 11 00 - Summary.docx 01 11 00-2

Check Structure:

1. Construct a new concrete check structure and appurtenant features including (but not limited to);

2. Reinforcement,

3. Cast-in-place concrete,

4. Radial gate hoist platforms,

5. Walkways,

6. Steel railings, and

7. Stop log channels.

Construct a canal realignment tying into the new MC420 check structure to include:

1. Concrete canal lining and

2. Reinforcement installation.

Stainless Steel Stop Log Guides

1. Fabricate and install new stainless steel stop log channels/guides in the new MC420 Check Structure.

Electrical System:

1. Supplying and installing a new control building and grounding system,

2. Installing a new 3-phase electrical service drop from the weatherhead of the service pole to the new control building,

3. New 3-phase control equipment for radial gate actuator, winches, controls, control displays and SCADA system, and

4. Commissioning.

Placing and compacting backfill materials, structural fill, finish grading, surface coarse aggregate, site reclamation, and revegetation.

Site Reclamation:

1. Constructing a new drain ditch adjacent to the Main Canal,

2. Constructing realigned access roads adjacent to main canal,

3. Embankment modifications sufficient to satisfy Work Sequencing, see 01 12 16, and

4. Filling, compacting, and finish grading abandoned canal segment.

5. Completing all vegetation removal and replacement, including seeding all disturbed areas.

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 11 00 - Summary.docx 01 11 00-3

SPECIFICATIONS REQUIREMENTS

Imperative statements in these specifications are CONTRACTOR requirements unless otherwise stated.

Where specifications are written in streamlined form, the words ‘shall be’ are included by inference where a colon (:) is used within the sentence or phrase.

DEFINITIONS

None.

ACRONYMS

SCADA – Supervisory Control and Data Acquisition

PRODUCTS

Not used.

EXECUTION

Not used.

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 11 00 - Summary.docx 01 11 00-4

THIS PAGE IS INTENTIONALLY LEFT BLANK

CRIP MC420 Check Replacement SECTION 01 12 16

La Paz County, Arizona WORK SEQUENCE

J:\26\12494-01\81Specs\MC420\01 12 16 - Work Sequence.docx 01 12 16 -1

GENERAL

GENERAL

This specification describes the general work sequence anticipated as part of the work included in the Contract Documents. This work sequence outlines the general procedure of work within operational, environmental and property constraints and is intended to minimize the duration of irrigation operation impacts to the extent practicable. The intent is not to be prescriptive but rather to lay out the general sequencing requirements within which the

CONTRACTOR can determine and employ their own best practices and means and methods.

RELATED SECTIONS

The following list of related specification sections is not intended to be all inclusive.

Section 01 14 00 – Work Restrictions

Section 01 57 20 – Environmental Protection

Section 01 57 90 – Preservation of Archaeology Data

GENERAL WORK SEQUENCE AND PROJECT PHASING

Phase 1 – Construct new Main Canal 420 (MC420) check structure and off-line canal realignment and install Contractor-furnished radial gate and appurtenances (prior to Main

Canal drawdown).

1. Isolation to be maintained by constructing off-line canal and off-line MC420 check structure by avoiding penetration of existing canal embankment and slope paving.

Construction can proceed without interruption to irrigation operations;

2. Reconstruct impacted adjacent drain ditch;

3. Dewatering, moisture conditioning subgrade, maintaining pumps and excavation sumps as required;

4. Construct MC420 check structure and install Contractor-furnished radial gates and all appurtenant equipment;

5. Construct new off-line canal lining;

6. Construct new building slab, control building, electrical controls, and SCADA system;

7. Provide new 3-Phase electrical service to control building;

8. Reconstruct impacted access roads;

9. Satisfy building code requirements to allow final completion of electrical service connection, and

10. Phase 1 testing and initial electrical and SCADA system commissioning.

a. BIA Representative will be responsible for SCADA programming including application files (programming) or commissioning of the local automatic

J:\26\12494-01\81Specs\MC420\01 12 16 - Work Sequence.docx 01 12 16 -2 control logic or user interface screens as outlined in 40 61 13 Process Control

System.

Phase 2 – Complete upstream and downstream Main Canal tie in (during Main Canal drawdown)

1. Coordinate with BIA Representative for final main canal drawdown dates and timeline, as outlined in 01 14 00 Work Restrictions.

2. Demolition

a. Demolish existing Main Canal, canal liner, slope paving and canal embankments to extents shown on the Construction Drawings to allow for tie in to the (Phase 1) MC420 check structure and realigned canal work.

b. The existing MC420 check structure cannot be demolished until the realigned

Main Canal is complete and fully cured, and the new MC420 check structure and radial gate is fully completed, cured, tested, and commissioned.

3. Dewatering, moisture conditioning subgrade, maintaining pumps and excavation sumps as required.

4. Main Canal Tie-ins

a. Construct the upstream and downstream Main Canal embankments.

b. Canal lining and slope paving completed during Phase 2 drawdown shall be sufficiently cured and tied into existing main canal lining and Phase 1 work prior to irrigation operations being returned to the Main canal.

5. Final testing, commissioning, and systems integration.

Phase 3 – Final demolition, reclamation, and grading during a period of active flow of water in the realigned canal and through the new MC420 structure.

1. Main Canal irrigation flow will be returned to the newly construction Main Canal after the drawdown window specified in section 01 14 00 Work Restrictions.

2. Demolition:

a. Finish demolition and disposal of existing canal lining to the extents noted on the drawings and abandon remaining canal lining in place; and

b. Demolish existing MC420 check structure to the extents noted on the drawings and abandon remaining MC420 check structure in place.

c. Comply with the infrastructure removal requirements specified in section

01 57 20 Environmental Protection, specifically related to Wildlife and

Threatened or Endangered Species Habitat Protection.

3. Final Site Reclamation and Grading

a. Complete the final site grading to the lines and grades shown on the Drawings,

b. Install surface course aggregate on all new roadways and access roads, and

c. Complete site seeding and revegetation.

J:\26\12494-01\81Specs\MC420\01 12 16 - Work Sequence.docx 01 12 16 -3

PRODUCTS

None

None

J:\26\12494-01\81Specs\MC420\01 12 16 - Work Sequence.docx 01 12 16 -4

CRIP MC420 Check Replacement SECTION 01 14 00

La Paz County, Arizona WORK RESTRICTIONS

J:\26\12494-01\81Specs\MC420\01 14 00 - Work Restrictions.docx 01 14 00 -1

GENERAL

SECTION INCLUDES

This section covers the restrictions for sequencing the work and maintenance of water for irrigation.

RELATED SECTIONS

The following list of related specification sections is not intended to be all inclusive.

Section 01 12 16 – Work Sequence

Section 01 57 20 – Environmental Protection

Section 01 57 90 – Preservation of Archaeology Data

Section 51 00 20 – Canal Flow Data

OWNERS REPRESENTATIONS

The BIA Representative will schedule a drawdown period in January to allow the Contractor to construct the tie-in components (Phase 2) of this project as outlined in 01 12 16 Work

Sequence.

1. The typical drawdown period is a two-week period generally occurring the second and third week of January of each year. The exact dates vary and will be defined by the BIA

Representative.

2. BIA is attempting to schedule a three-week drawdown period to facilitate a longer construction work window. Contractor shall assume the drawdown period is two weeks long unless explicitly indicated otherwise by BIA Representative.

BIA Representative reports the current Main Canal maximum discharge capacity downstream of the MC420 check structure to be 900 cubic feet per second (cfs).

SITE ACCESS

Provisions for site access are as defined in the Construction Drawings.

AVAILABLE INFORMATION

Current and historic data including stream flow for the Colorado River Indian Reservation

Main Canal near Parker, AZ are provided in Section 51 00 20 – Canal Flow Data.

IRRIGATION REQUIREMENTS

The Colorado River Irrigation Project provides its water users with irrigation water year-round.

A stipulation of this Contract is that the irrigation canal shall remain operational outside of the drawdown period to be scheduled by the BIA Representative.

As described in specification section 01 12 16 (Work Sequence), a canal bypass is not a requirement of this project, provided that the Contractor is capable of constructing Phase 2 of

CRIP MC420 Check Replacement SECTION 01 14 00

La Paz County, Arizona WORK RESTRICTIONS

J:\26\12494-01\81Specs\MC420\01 14 00 - Work Restrictions.docx 01 14 00 -2 the work within the two-week canal drawdown period. If Contractor’s means and methods of construction, or novel approach to this project dictate a required bypass, the aforementioned

BIA Representation regarding canal discharge (see 1.03 B of this section) may be used as a basis of design.

ENVIRONMENTAL REQUIREMENTS

Environmental requirements (e.g., allowed timing of vegetation clearing) influence the allowed work sequence. Refer to section 01 57 20 – Environmental Protection for specific requirements.

PRODUCTS

Not Used

CRIP MC420 Check Replacement SECTION 01 18 13 La Paz County, Arizona UTILITY SERVICE CONNECTION

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 18 13 - Utility Service Connection.docx 01 18 13 -1

GENERAL

GENERAL

This specification describes the general utility service connection sequence anticipated as part of the work included in the Contract Documents. This utility service connection sequence outlines the general procedure of work within operational, ownership, and property constraints and is intended to facilitate the electrical utility service connection and temporary electrical service sequence to the extent practicable and to minimize the duration of electrical service operation impacts to the extent practicable. The intent is not to be prescriptive but rather to provide general sequencing requirements and contact information within which the CONTRACTOR can determine and employ their own best practices and means and methods while ensuring conformance with applicable rules and regulations.

RELATED SECTIONS

The following list of related specification sections is not intended to be all-inclusive.

Section 01 12 16 – Work Sequence

Section 01 14 00 – Work Restrictions

Section 01 50 00 – Temporary Facilities

Section 26 05 01 – Basic Electrical Requirements

DEFINITIONS

1. CRA-ES is the Bureau of Indian Affairs Colorado River Agency Electrical Service

GENERAL UTILITY SERVICE CONNECTION SEQUENCE

Work by Others

1. CRA-ES is capable of supplying temporary power for Contractor’s use off of new distribution pole D2 at 3 Phase 208V. This temporary service would be metered and the Contractor will be required to compensate CRA-ES for temporary Electrical Service provided. Contact Joseph Stewart (BIA CRA-ES) at 928.669.7119, or Colorado River Agency general number at 928.669.7111.

2. After the facility has passed Tribal building inspection and the Contractor has requested activation of the new electrical service, BIA CRA-ES will furnish and install new electrical meter on the Electrical Distribution pole D2 and make the connection to the BIA CRA-ES utility at the weatherhead.

3. The existing 3 Phase 240 V (delta configuration) power will be maintained during Phase 1 and Phase 2 of the MC420 Construction Project to ensure irrigation operations are maintained during the regular irrigation season.

CRIP MC420 Check Replacement SECTION 01 18 13 La Paz County, Arizona UTILITY SERVICE CONNECTION

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 18 13 - Utility Service Connection.docx 01 18 13 -2

Work by Contractor (this Project)

1. The Contractor is responsible for contacting and coordinating with CRA-ES for any temporary electrical service drop provisions, metering, and payment, as required by Contractors means and methods and described above.

2. Construct new building slab, control building, electrical controls, and SCADA system

3. Furnish and install all conduits, wiring, panels, and electrical and SCADA appurtenances as outlined in the Construction Drawings,

4. Contractor shall schedule a Building and Safety Inspection with the CRIT Building and Safety Officer once installation is adequately complete for work to be “Green Tagged”.

5. Contractor is responsible for furnishing and installing all new conduits, and conductors, required for providing 3-Phase 208V electrical service to new control building from Point of Transfer as outlined in the Construction Drawings.

6. Satisfy all applicable electrical and building code requirements to allow final completion of electrical service connection and final testing, commissioning, and systems integration.

7. Provide any necessary communication with BIA CRA-ES to request and coordinate the timing for activating the new electrical service.

PRODUCTS

None

None

CRIP MC420 Check Replacement SECTION 01 29 00 La Paz County, Arizona PAYMENT PROCEDURES

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 29 00 - Payment Procedures.docx 01 29 00 - 1

GENERAL

SECTION INCLUDES

For each bid item, the work will be measured and paid for on either a unit price basis or on a lump sum basis. The quantities provided in the descriptions of the bid items are estimates of the actual quantities of work only and are included solely for guidance in determining the probable cost of work. The actual quantities of work may differ from the quantity estimates provided. The quantities for measurement and payment for unit price bid items shall be as calculated to the neatlines shown on the drawings. All labor, equipment, materials, and incidentals required to complete the work shall be considered subsidiary to that bid item and will not be paid for separately. The contractor agrees to make no claim for damages, loss of anticipated profits, or otherwise, due to differences between the actual work quantities and the quantity estimates provided.

Payment will be made only for each item included in the bid. No work will be paid for that is not completed in accordance with the drawings and specifications and accepted by the BIA Representative. No labor, equipment, materials, or incidentals required to complete the work will be furnished by the BIA Representative.

The basis of measurement and payment for each bid item is described below. A general listing of bid items, accompanied by a brief summary of the work, is also provided. The summaries are not intended to completely describe all work. Refer to the drawings and specifications for detailed information on each bid item.

ACRONYMS

CLIN is Contract line item number

MEASUREMENT AND PAYMENT PROCEDURES

CLIN 02 – Contractor-furnished MC420 Radial Gate

Item 201: Contractor-furnished MC420 Radial Gate and Appurtenances

a. This item consists of design and shop drawing development for the Contractor-furnished MC420 radial gate, gate appurtenances, lifting assemblies, and actuation equipment specified under section 35 22 46 – Radial Gates.

b. This bid item includes, but is not limited to:

i. Complying with the Radial Gate Designer and Manufacturer Qualifications and documenting this compliance through the requisite submittal.

ii. Designing the Contractor-furnished radial gate, gate hoists, gearboxes, cables, drums, motors, rubbing plates and seals, railings and walkway grating integral to the hoist assembly, and cathodic protection.

iii. Developing, compiling, and submitting all information described under the Radial Gate Approval Drawings and Data submittal.

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 29 00 - Payment Procedures.docx 01 29 00 - 2

iv. Related submittal reviews, resubmittals, and coordination required to achieve final, approved/accepted submittals.

c. This bid item does not include furnishing or installing this equipment.

d. Measurement and payment will be at the Contract lump sum price.

CLIN 03 – CRIP MC420 Check Replacement

Item 301: Mobilization and Preparatory Work

a. This bid item includes, but is not limited to:

i. Furnishing, installing, and removing temporary fencing and construction markers around project work areas and other fencing/security.

ii. Establishing and removing the contractor's offices, buildings, and other facilities.

iii. Obtaining, complying with, and transferring permits.

iv. Installing and maintaining environmental controls for the duration of the construction Contract.

v. Providing required bonds and insurance.

vi. Preparing and maintaining the project schedule.

vii. Delivering and removing the contractor's equipment, supplies, and materials; maintaining the site for the duration of the construction Contract; and final site clean-up and demobilization.

viii. Preparing and securing approvals of submittals.

ix. Preparing record drawings.

x. General site maintenance and clean-up.

xi. Providing all other related and necessary labor, equipment, and materials to complete the work that are not accounted for in the other bid items.

b. Measurement and payment will be at the Contract lump sum price.

c. Ten (10) percent of the lump sum price will be paid at the time of the first monthly progress payment; an additional forty (40) percent will be paid when one-half of the original contract amount (excluding Mobilization and Preparatory Work) is earned. An additional thirty (30) percent will be paid when two-thirds of the original contract amount (excluding Mobilization and Preparatory Work) is earned. The remaining twenty (20) percent will be paid upon final acceptance of the project.

d. The Contractor may elect to present the BIA Representative with an alternate payment schedule based on a detailed schedule of values. Acceptance by the BIA Representative of the Contractor’s proposed alternate payment schedule is at the sole discretion of the BIA Representative.

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 29 00 - Payment Procedures.docx 01 29 00 - 3

Item 302: Water Control and Construction Dewatering

a. This bid item includes, but is not limited to:

i. Preparing, submitting, and updating Water Control and Dewatering Plans.

ii. Evaluating, designing, constructing, maintaining, replacing, and monitoring water control and dewatering measures.

iii. Furnishing and installing all materials, sediment basins, diversion measures, slope drains, check dams, cofferdams, pumps, dewater bags, earth embankments, sheet pile, wells, pipes, culverts, stream crossings, or other material necessary for water control.

iv. Disassembly and demobilizing of cofferdams and other dewatering materials and equipment.

v. Obtaining and complying with all required permits.

b. Measurement and payment will be at the Contract lump sum price.

c. One-third of the lump sum price for this item will be paid after twenty-five (25) percent of the original contract amount (excluding Water Control/Dewatering) has been earned, the second third after fifty (50) percent of the original contract amount (excluding Water Control/Dewatering) has been earned, and the final third will be paid upon final acceptance of the project.

d. The Contractor may elect to present the BIA Representative with an alternate payment schedule based on a detailed schedule of values. Acceptance by the BIA Representative of the Contractor’s proposed alternate payment schedule is at the sole discretion of the BIA Representative.

Item 303: Site Grading

a. This bid item includes, but is not limited to:

i. Clearing and grubbing within the construction limits shown on the Drawings.

ii. Grading of the project site surface to the neatlines shown on the Drawings.

iii. Excavations to provide the drain ditch realignment defined in the Drawings.

iv. Excavation for the main canal realignment to the subgrade neatlines shown on the Drawings.

v. Grading and preparation of access roads to bottom of aggregate surface course.

vi. Salvaging material from excavations for use as embankment fill material.

vii. Filling and reclaiming existing Main Canal

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 29 00 - Payment Procedures.docx 01 29 00 - 4

viii. Embankment fill for the drain ditch.

ix. Excavating, stockpiling, and hauling materials from excavation areas to fill areas.

x. All earthwork not included in other bid items.

b. Measurement and payment will be at the Contract lump sum price.

Item 304: Drain Ditch Pipe Culverts

a. This item consists of furnishing and installing the conveyance pipe culvert(s) for the drain ditch realignment adjacent to the CRIP Main Canal.

b. This bid item includes, but is not limited to:

i. Trench excavation and backfill.

ii. Providing and installing pipe bedding materials.

iii. Pipe, fittings, end treatments and all other pipe appurtenances not specifically priced separately.

iv. Furnishing all labor, equipment, and materials associated with or incidental to installing the drain ditch pipe culvert.

c. Measurement and payment will be at the Contract lump sum price.

Item 305: Structure Excavation, Foundation Improvements, and Backfill

a. This item consists of excavation and foundation improvements for cast-in-place concrete structures and slabs including the check structure and control building base slab.

b. This item includes, but is not limited to:

i. Excavation to the subgrade neatlines shown on the Drawings.

ii. Preparing, scarifying, moisture conditioning and compacting subgrade.

iii. Hauling, stockpiling, and wasting excess excavated material.

iv. Stabilization geotextile.

v. Importing and placement of structural foundation fill.

vi. Structure backfill.

vii. Quality control testing of the placed materials.

viii. All labor, equipment, and materials necessary to meet compaction requirements shall be considered incidental.

c. Measurement and payment will be at the Contract lump sum price.

Item 306: Canal Subgrade Preparation and Foundation Improvements

a. This item consists of subgrade preparation and foundation improvements for cast-in-place concrete base slab and slope paving for the CRIP Main Canal.

b. This item includes, but is not limited to:

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 29 00 - Payment Procedures.docx 01 29 00 - 5

i. Preparing, scarifying and moisture conditioning subgrade.

ii. Hauling, stockpiling, and wasting excess material.

iii. Importing and placement of bedding.

iv. Embankment fill.

v. Quality control testing of placed materials.

vi. All labor, equipment, and materials necessary to meet compaction requirements shall be considered incidental.

c. Measurement and payment will be at the Contract lump sum price.

Item 307: Stilling Wells

a. This item consists of furnishing and installing new stilling wells and appurtenant features for water level monitoring as shown in the Construction Documents.

b. This bid item includes, but is not limited to:

i. Furnishing all labor, equipment, and materials associated with installing the new CRIP MC420 stilling wells at the locations specified in the Construction Drawings.

ii. Excavation, foundation improvements, and backfill.

iii. Providing and installing access tube pipe, fittings, and pipe bedding materials.

iv. Providing and installing staff gages as shown on the Drawings.

v. Coordinating expansion and contraction joint locations with canal lining activities and extending the canal liner around stilling well.

vi. Manhole, manhole cover, mounting brackets, anchors, and all other appurtenances.

vii. Providing and installation of bollards will be paid under Bid Item Safety Features.

c. Measurement and payment will be at the Contract lump sum price.

Item 308: Concrete Structures

a. This item consists of furnishing and installing reinforced concrete to construct the MC420 check structure, operator walkways and control building base slab.

b. This bid item includes, but is not limited to:

i. Furnishing all labor, equipment, and materials required for or incidental to the construction of cast-in-place and pre-cast concrete structures.

ii. Forming, reinforcement, embedments, concrete mix materials, installing, finishing, curing and protection, knockouts, saw cutting, chipping, doweling, bonding agents, water stops, joints, and all other incidentals.

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 29 00 - Payment Procedures.docx 01 29 00 - 6

iii. Quality control testing of concrete.

c. Measurement and payment will be at the Contract lump sum price.

Item 309: Concrete Canal Lining

a. This item consists of furnishing and installing reinforced concrete to construct the CRIP Main Canal concrete canal lining base slab and slope paving.

b. This bid item includes, but is not limited to:

i. Furnishing all labor, equipment, and materials required for or incidental to the construction of concrete Main Canal section.

ii. Forming, reinforcement, concrete materials, installing, finishing, curing, knockouts, saw cutting, doweling, expansion and contraction joints, and all other incidentals.

iii. Coordinate and construct connection to existing canal liner

iv. Quality control testing of concrete.

c. Measurement and payment will be at the Contract lump sum price.

Item 310: Provide and Install Contractor-furnished Radial Gate and Appurtenances

a. This item consists of fabricating, installing, and readying for service the Contractor-furnished radial gate equipment designed under CLIN 02.

b. This bid item includes, but is not limited to:

i. Fabricating the Contractor-furnished radial gate and appurtenances, including furnishing all materials and equipment, coordinating and completing Owner-witnessed factory acceptance tests.

ii. Delivering the equipment to the project site.

iii. Furnishing all labor, equipment, and materials necessary for installing Contractor-furnished radial gate, gate hoists, gearboxes, cables, drums, motors, rubbing plates and seals, and cathodic protection.

iv. This item also includes providing and installing all hardware and anchorage necessary for installation of Contractor-furnished Materials.

v. This item also includes providing all labor, equipment, and materials necessary for field directed testing requested by the BIA Representative.

vi. Completing intermittent radial gate testing to ensure proper seating on sill and rubbing plates.

c. Measurement and payment will be at the Contract lump sum price.

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 29 00 - Payment Procedures.docx 01 29 00 - 7

Item 311: Pipe Railings and Miscellaneous Metals

a. This item consists of providing and installing the pipe railings and any other miscellaneous metals associated with the MC420 Check structure.

b. This bid item includes, but is not limited to:

i. Furnishing all materials, tools, equipment, and labor necessary to provide and install pipe railings, hoist platforms, bulkhead channels and any other miscellaneous metals in accordance with the Contract Documents.

ii. Structural steel, bar grating, anchors, and fasteners.

iii. Hot-dip galvanizing and field repairs to galvanizing coating.

iv. Supplying and installing any miscellaneous metal work not specifically included in another item is considered incidental to the pipe railings and miscellaneous metals.

c. Measurement and payment will be at the Contract lump sum price.

Item 312: Control Building

a. This item consists of providing and installing the control building.

b. This bid item includes, but is not limited to:

i. Furnishing all labor, equipment, and materials to install the new control building structure.

ii. Coordinate and construct wall and slab penetrations.

c. Measurement and payment will be at the Contract lump sum price.

Item 313: Electrical Equipment and Control System

a. This item consists of furnishing and installing all on-site electrical panels, control equipment, conduit, and conductors from the Colorado River Agency Electrical Services (CRA-ES) point-of-transfer (PoT) at the weatherhead on the new three-phase overhead electrical service through the control building and electrically actuated equipment and all equipment necessary for operating and monitoring the system.

b. This bid item includes, but is not limited to:

i. Furnishing all labor, equipment, and materials to complete all electrical system work identified in the Contract Documents.

ii. New wiring, lighting, switches, outlets, disconnect, control panels, interface screens, and electrical panels for the new electrical and control building.

iii. Coordinating approval of the control building and electrical installation with the BIA Representative, the Colorado River Indian Tribes Building and Safety Officer and coordination the final electrical connection and meter installation with the CRA-ES.

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 29 00 - Payment Procedures.docx 01 29 00 - 8

c. Measurement and payment will be at the Contract lump sum price.

Item 314: Demolition

a. This bid item includes, but is not limited to:

i. Demolition, selective demolition, and disposal of all existing structures, elements, and features designated for removal in the Contract Documents including existing concrete, rebar, steel, anchorage, reinforcement, shotcrete, slope paving, radial gate, gate appurtenances, hoists, platforms, railings, walkways, fences, electrical and control equipment, existing check structure, and stilling wells.

ii. Abandonment of existing check structure concrete and canal slope paving to the extents identified in the Contract Documents.

iii. Legal disposal at an off-site facility.

iv. Salvaging any materials specifically identified in the Contract Documents as to be salvaged.

v. Removal of loose material and any cleaning necessary or incidental to demolition.

vi. Protection of existing structures and materials not designated for removal.

b. Measurement and payment will be at the Contract lump sum price.

Item 315: Roadway Surface Course

a. This item consists of furnishing, placing, and compacting surface course aggregates to complete all access road improvements included in the work.

b. This bid item includes, but is not limited to:

i. Furnishing all labor, equipment, and materials required for, or incidental to, this item.

ii. Providing and installing roadway surface course aggregate as indicated in the Construction Documents.

c. Measurement and payment will be at the Contract lump sum price.

Item 316: Reclamation and Seeding

a. This item consists of spreading salvaged topsoil, finished grading, site restoration, and revegetation of disturbed areas.

b. This bid item includes, but is not limited to:

i. Furnishing all labor, equipment, and materials to clean all affected areas, lay down, staging, and waste areas, and restore the site drainage patterns.

ii. Cleanup and disposal of remaining aggregate, disposal of excess concrete rubble not abandoned on-site, grading of waste materials from

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 29 00 - Payment Procedures.docx 01 29 00 - 9 excavations, cleanup and disposal of waste concrete materials, and other incidentals to restore the site to pre-disturbance conditions.

iii. Topsoil replacement and grading.

iv. Seeding, fertilizing, mulching.

c. Measurement and payment will be at the Contract lump sum price.

Item 317: Fencing, Signage, and Gates

a. This item consists of furnishing and installing all fencing, gates and signage indicated in the plans.

b. This bid item includes, but is not limited to:

i. Furnishing all labor, equipment, and materials to provide fencing, posts, and gates shown on the Construction Drawings.

c. Measurement and payment will be at the Contract lump sum price.

Item 318: Safety Features

a. This item consists of furnishing and installing all canal egress ladders, safety cables, and bollards indicated in the plans.

b. This bid item includes, but is not limited to:

i. Furnishing all labor, equipment, and materials to install canal egress ladders, safety cables, and pipe bollards shown on the Construction Drawings.

ii. All pipe bollards whether associated with or adjacent to safety cables, stilling wells, or fences and gates.

c. Measurement and payment will be at the Contract lump sum price.

Item 319: Stainless Steel Stop Log Guides

a. This item consists of providing and installing stop log channels/guides for the new MC420 check structure.

b. This bid item includes, but is not limited to:

i. Furnishing all labor, equipment, and materials to fabricate and install bulkhead channels conforming to the dimensions shown on the Drawings and accommodating stainless steel stop logs procured under CLIN 01 for the MC185/MC270 structures.

c. Measurement and payment will be at the Contract lump sum price.

Item 320: Field Directed Earthwork

a. This item consists of providing all labor, equipment, and materials necessary for field directed earthwork requested by the BIA Representative.

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 29 00 - Payment Procedures.docx 01 29 00 - 10

b. This bid item includes, but is not limited to:

i. Furnishing all labor, equipment, and materials required to sub-excavate unsuitable material found during structure excavation or site grading.

ii. Hauling, stockpiling, and wasting unsuitable excavated material.

iii. Importing and placement of structural foundation fill that is not incidental to any other bid item.

iv. All labor, equipment, and materials necessary to meet compaction requirements shall be considered incidental.

c. Measurement and payment will be at the Contract cubic yard price.

PRODUCTS

Not Used

EXECUTION

CRIP MC420 Check Replacement SECTION 01 29 73 La Paz County, Arizona SCHEDULE OF VALUES

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 29 73 - Schedule of Values.docx 01 29 73 - 1

GENERAL

SUMMARY

This Section defines the process whereby the Contractor will develop the Schedule of Values (lump sum price breakdown) for review and approval by the BIA Representative.

Monthly progress payment amounts for some bid items will be determined from the in-progress status (i.e., estimated percent complete) of the work features identified in Section 01 29 00 – Payment Procedures.

SUBMITTALS

Submit the following in accordance with Section 01 33 00 – Submittals.

01 29 73-1, Schedule of Values

1. Prepare and submit a detailed Schedule of Values for every work feature within 30 days from the date of Award or 14 days prior to the Pre-Construction Meeting, whichever occurs first.

2. The schedule of values must be sufficiently detailed to determine appropriate monthly progress payments.

3. The BIA Representative will be the sole judge of acceptable numbers, details, and descriptions of values established.

4. If, in the opinion of the BIA Representative, a greater number of Schedule of Values items than proposed is necessary, the Schedule of Values will be returned for revision.

5. Adjustments and Acceptance

a. During the Pre-Construction Meeting, the level of detail and value allocations will be discussed to determine if the Schedule of Values provides an acceptable level of detail to support interim progress payments for the work features. The CO’s review of the Schedule of Values submittal shall be returned to Contractor within 7 days following the Pre-Construction Conference.

b. Make necessary adjustments to the level of detail and/or value allocation and submit a revised Schedule of Values within 7 Days from the date of receiving the CO’s review comments.

PRODUCTS

Not Used

EXECUTION

CRIP MC420 Check Replacement SECTION 01 29 73 La Paz County, Arizona SCHEDULE OF VALUES

\\dowl.com\j\Projects\26\12494-01\81Specs\MC420\01 29 73 - Schedule of Values.docx 01 29 73 - 2

CRIP MC420 Check Replacement SECTION 01 32 16

La Paz County, Arizona CONSTRUCTION PROGRESS SCHEDULE

J:\26\12494-01\81Specs\MC420\01 32 16 - Construction Schedule.docx 01 32 16 -1

GENERAL

SECTION INCLUDES

This section covers the requirements for developing the baseline construction schedule and updating and maintaining the construction program.

REFERENCE STANDARDS

Associated General Contractors of America (AGC)

1. AGC Manual – Construction Planning and Scheduling Manual

DEFINITIONS

Schedule: Construction schedule using the Critical Path Method (CPM) of planning and scheduling a construction project. Activities are arranged based on activity relationships and network calculations identifying the “critical activities” that determine the earliest completion date.

Project Calendars: Cross reference between the number of workdays and calendar days. The project calendar serves as the basis for the day/date conversion and assigns workdays and non-workdays.

Resources: Equipment, labor or crews, materials, subcontractors, fabricators, manufacturers, and consultants.

SUBMITTALS

Submit the following in accordance with Section 01 33 00 – Submittals.

01 32 16-1, Representative Information

1. Designation of authorized representative to develop and maintain the Construction

Program. Representative shall be experienced in developing and maintaining construction schedules and knowledgeable of activities and progress on-site to develop and maintain accurate and reliable schedules.

01 32 16-2, Baseline Schedule

1. Include:

a. Definition of project Calendars.

b. Gantt Chart (bar chart) for project.

c. Narrative of the construction sequence.

d. Activity report including all logic constraints consisting of predecessors, successors, and constraint dates.

e. Table listing equipment, manpower, and material limitations used to produce baseline schedule.

01 32 16-3, Updated Schedule

1. Include:

J:\26\12494-01\81Specs\MC420\01 32 16 - Construction Schedule.docx 01 32 16 -2

a. Updated activity and milestone schedule summary.

b. Definition of project calendars if revised from baseline calendars.

c. Gantt chart for project.

d. Narrative report specifically stating status of project.

1. If negative float exists, cite specific actions and conditions which caused the “behind schedule” condition and provide proposed course of action to complete the project within the specified delivery time.

2. List of Contractor-initiated changes to the current schedule, including the reason for the change and any unresolved issues relating to the

Construction Program. COR and Owner Representative reserve the right to reject Contractor-initiated changes to the approved schedule.

e. Submittals register. Updated monthly register including: submittals as listed in submittal table, revised submittals, dates, and status. This register document is separate from the scheduling database.

01 32 16-4, Time Impact Analysis

1. Include:

a. Construction Program database with proposed revised activity and milestone data.

b. Proposed schedule revisions, specifically identifying changed or deleted activities and the impact on the completion date.

c. Narrative report explaining results and conclusions.

CONSTRUCTION SEQUENCE

Prepare construction schedules using CPM, under concepts and methods outlined in the AGC

Manual.

1. Establish workday calendar(s) and use these in the schedule to translate the activity’s workday duration into calendar dates. Use calendar names unique for this project, do not use software default calendar names. Save calendars as project calendars, not global calendars.

2. Prepare schedule based on required sequence and interdependence of activities.

3. Prepare detailed activity network for accomplishing required work organized by Work

Breakdown Structure (WBS).

4. Activities except “Award” shall have predecessor activities and activities except

“Contract Complete” shall have successor activities.

5. Include dates for interim milestones, critical interface events for BIA Representative, time or seasonal constraints specified in the contract documents, and contract completion.

6. Include work to be performed by subcontractors.

7. Develop the Construction Program to account for seasonal weather conditions.

J:\26\12494-01\81Specs\MC420\01 32 16 - Construction Schedule.docx 01 32 16 -3

8. If activity codes are utilized, use unique activity code names assigned as project codes rather than global codes. Utilize the WBS, in lieu of activity codes, for general organization of the schedule.

9. Define activities to a level of detail to result in no single activity having a duration greater than 20 workdays, unless otherwise accepted by BIA Representative.

a. Durations for administrative activities (e.g., submittals and reviews, fabrication, manufacturing) or other specific activities identified in the contract will not be subject to the workday limitation.

10. Include activities for BIA Representatives review and approval. Assign submittal review activities to a 7-day calendar with durations as specified in Section 01 33 00 –

Submittals. Include activities for issuance of submittals, submittal reviews, and fabrication or manufacturing activities when work involves significant quantities, long lead times, is on the critical path, or as requested by the BIA Representative.

11. Include contract title, contract number, and Contractor’s name on each sheet of the

Gantt chart.

12. For each activity on the Gantt chart, display identification number, activity description, planned duration, start date, finish date, total float, and calendar identification.

13. Include table of abbreviations used in the schedule, listed, and defined alphabetically.

14. Use durations in units of whole workdays.

15. Equate durations for BIA Representative reviews and other identified actions to the maximum number of calendar days specified in their respective paragraphs.

Baseline Schedule:

1. Represents Contractor’s as-planned approach to accomplishing the work. Does not include actual start dates, percent completes, or actual finish dates.

Updated Schedule:

1. Meet weekly with the BIA Representative at a location approved by the BIA

Representative, to review progress. Establish dates that activities were started and completed, discuss remaining durations for each activity started but not yet completed.

a. Discuss schedule status and identify potential negative schedule impacts.

b. Submit revised schedule that accurately identifies actual start/finish dates, identifies corrective actions to recover schedule, or request approval to extend the construction schedule.

2. Provide a 3-week look-ahead schedule at weekly progress meetings.

3. Following receipt of an executed contract Modification, incorporate the activity data and logic relationships stipulated in the modification into the schedule for discussion at the next progress meeting.

4. The project schedule shall be updated and submitted to the BIA Representative for approval with the Contractor’s monthly progress payment.

J:\26\12494-01\81Specs\MC420\01 32 16 - Construction Schedule.docx 01 32 16 -4

5. Assign a unique project file name to each schedule update issued. Schedule updates shall be issued as a pdf and comply with the following file naming convention:

YYMMDD_CRIP MC420 Check Replacement Schedule Update.pdf

TIME IMPACT ANALYSIS

Provide a time impact analysis for contract changes, e.g., a change order, proposed modification, or value engineering change proposal, to support a claim or request for an equitable adjustment to the contract that involves a delay or accelerated schedule.

The BIA Representative may use the time impact analysis to determine if a time extension or reduction to the contract milestone dates is justified.

A time impact analysis is applicable whether the Contractor’s current schedule milestone dates are the same as, earlier, or later than those required under the contract.

Changes, additions, or deletions to activities, activity durations, or activity time frames will not automatically mean that an extension or reduction of contract time is warranted.

Time extensions for performance will be considered only to the extent that the Contractor’s current scheduled milestone dates exceed the contract milestone dates.

For each activity directly affected by a change or delay, include the current and proposed items:

1. Activity description

2. Types and quantities of major pieces of equipment, principal manpower, and pacing materials (materials that affect activity start, duration, or finish).

3. Activity duration.

4. A narrative containing the rationale used in developing the proposed logic relationships and activity data.

Float is not for the exclusive use by, or benefit of, either the BIA Representative or the

Contractor.

Prepare a single time impact analysis for modifications issued after Notice to Proceed (NTP) and prior to approval of the baseline schedule. Submit the time impact analysis with the baseline schedule submittal.

Perform time impact analyses using data in the current, approved schedule at the time of the change or delay event.

1. Prepare proposed revised schedule and narrative description describing and highlighting where changes or delays are included.

2. Prepare summary comparing the results of two schedule analyses: One using current schedule data, and one using proposed schedule data incorporating the changes or delays.

a. Show contract milestone and activities whose periods of performance have shifted.

J:\26\12494-01\81Specs\MC420\01 32 16 - Construction Schedule.docx 01 32 16 -5

b. Base mathematical analyses on status of work and available float from the time the CO directs or proposes changes to the work, the Contractor submits a value engineering change proposal, or when a delay occurs.

REVIEW AND EVALUATION

Baseline Schedule:

1. Within 14 calendar days after receipt of baseline schedule:

a. BIA Representative will accept or reject the proposed baseline schedule.

b. If schedule is rejected,…