Attachment T - L10 Major Payment Events Payment Schedule and Completion Criteria.pdf

PDF 1 MB Posted

Attached to
Landsat 10 Spacecraft _ DRAFT RFP
Solicitation number
80GSFC26D0015
Issued by

About this file

This document is Attachment T to RFP 80GSFC26R0015, establishing the Landsat 10 Spacecraft Major Payment Events, Payment Schedule, and Completion Criteria for NASA's Goddard Space Flight Center.

The attachment defines 26 commercial milestone payment events spanning the entire Landsat 10 spacecraft development and deployment lifecycle, from major subcontract awards through final on-orbit acceptance. Key milestones include design reviews (System Requirements Review, Preliminary Design Review, Critical Design Review), deliverables of ground support equipment (CTSS, OOpS, SoftSim, LVIS, RF Suitcase Simulator), spacecraft assembly and testing (Comprehensive Performance Test), instrument integration, environmental testing (vibration, EMI/EMC, thermal vacuum, acoustics), mission readiness tests, pre-ship review, launch site testing, launch execution, and on-orbit acceptance review. Payment percentages, amounts, and schedules are designated as "TBP" (To Be Planned) throughout the document, indicating these values will be determined during contract negotiation. Each milestone contains detailed completion criteria that the Contracting Officer must verify before authorizing payment. Criteria typically require demonstration of successful test completion with acceptable results, delivery of data deliverables, closure of critical action items, and government approval of technical reviews and design documentation. The final 10% payment is withheld until the On-Orbit Acceptance Review (per Clause H.16), confirming the spacecraft meets all requirements including successful activation, calibration, appendage deployment, and specification compliance on-orbit.

View the file

Other files

File Type Posted
Exhibit 6 - L10 Past Performance Questionnaire R.pdf PDF
Attachment S - L10 Time and Materials Rate Matrices Rev.pdf PDF
Attachment X DRD 5 - CAIRIA DRD.pdf PDF
Attachment E - L10 Spacecraft to Ground Interface Req Document (SC to GND IRD) Rev.pdf PDF
Enclosure 5 - Geometric Budget (GEB) Support Presentation.pdf PDF
Attachment F - L10 Observatory Environment Req Document (ObsERD)R.pdf PDF
Exhibit 4 - L10 Gate Criteria Fill In R.pdf PDF
Enclosure 3 - L10 Design Reference Case - DRC-18 Definition.pdf PDF
Attachment P - L10 Acronym List.pdf PDF
Exhibit 2 - L10 Spacecraft and Observatory Environmental Testing Matrix Fill-in.pdf PDF
Attachment V - L10 C-SCRM Plan.pdf PDF
Attachment X DRD 3 - CPIC DRD.pdf PDF
Attachment X DRD 4 - CITAR DRD updated.pdf PDF
Exhibit 5 - L10 Spacecraft Specifications Fill-in.pdf PDF
Attachment A - L10 Statement of Work (SOW).pdf PDF
Attachment O - L10 Lexicon.pdf PDF
Attachment K - L10 Space Environmental Req Document (LSERD).pdf PDF
Attachment X DRD 2 - NASA C-SCRM Plan Questionnaire.xlsx XLSX spreadsheet
DRFP Landsat 10 80GSFC26R0015 Terms and Conditions.pdf PDF
Attachment X DRD 6 - SCV Reporting.pdf PDF
Attachment B - L10 SC CDRL and DID Rev.pdf PDF
Attachment X DRD 3 - CPIC DRD Template for IT Portfolio PPM Data Collection.xlsx XLSX spreadsheet
Attachment L - L10 Analytical Math Model Definitions (LAMMD) Rev.pdf PDF
DRFP L10 80GSFC26R0015 Cover Letter Sgn.pdf PDF
Enclosure 4 - L10 Geometric Error Budget (GEB).pdf PDF
Attachment N - L10 World Reference System - 3 Definition Rev.pdf PDF
Exhibit 1 - L10 Pricing Template.xlsx XLSX spreadsheet
Enclosure 1 - L10 Mission Synopsis Rev.pdf PDF
Attachment C - L10 Spacecraft Requirements Document (SC SRD).pdf PDF
Attachment I - L10 Payload to Launch Services Interface Description Doc (LS IDD) Rev.pdf PDF
Exhibit 3 - L10 Spacecraft Master Equipment List (MEL) Fill In.pdf PDF
Attachment D - L10 Spacecraft Interface Requirements Document (SCIRD).pdf PDF
Attachment M - L10 Spacecraft Government Furnished Equipment Information List (SC GFEGFI).pdf PDF
Attachment Q - LandIS Simplified Mechanical Interface Control Drawing (MICD).pdf PDF
Attachment X DRD 4 - CITAR Report Template.xlsx XLSX spreadsheet
Attachment X DRD 1 - OCI Plan.pdf PDF
Attachment J - L10 Radiation Environments Description (LRED) Rev.pdf PDF
Attachment H - L10 Spacecraft Deliverable Items List (DIL).pdf PDF
Attachment X - Non-Technical Contract Data Requirements List.pdf PDF
Attachment R - L10 Spacecraft Contractor Standards.pdf PDF
Attachment U - L10 OCI Plan Rev.pdf PDF
Attachment W - Small Business Subcontracting Plan.pdf PDF
Enclosure 2 - L10 Observatory Quality Assurance Surveillance Plan.pdf PDF
Attachment G - L10 Spacecraft Simulator Req Document (SC Sim RD).pdf PDF
Attachment X DRD 2 - Security Requirements for Unclassified IT Resources DRD C-SCRM requirements.pdf PDF
Enclosure 3 - L10 Design Reference Case - DRC-18.pdf PDF
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment No. T

Landsat 10 Major Payment Events, Payment Schedule, and

Completion Criteria

RFP 80GSFC26R0015

National Aeronautics and Space Administration

Goddard Space Flight Center

L10 Major Payments Events and Acceptance Criteria L10-SC-DESC-0058 Rev -

(This page intentionally left blank)

L10 Major Payments Events and Acceptance Criteria L10-SC-DESC-0058 Rev -

1. Commercial Milestone Payment Schedule The contractor shall complete all activities required for each Milestone Payment Event prior to submitting the respective invoice. The payment schedules are defined in Table 1.1 and the completion criteria are defined in Table 1.2.

Table 1.1 – Landsat 10 Commercial Milestone Payment Events

Payment Event

No.

Commercial Milestone Payment Event Payment

Percent Payment Amount

Months

ARO

1 Major Subcontracts Awarded TBP $TBP TBP

2 Spacecraft System Requirements Review (SRR) Completion

TBP $TBP TBP

3 Spacecraft Preliminary Design Review (PDR) Completion

TBP $TBP TBP

4 All Subcontracts Awarded TBP $TBP TBP

5 Spacecraft Critical Design Review (CDR) Completion

TBP $TBP TBP

6 CTSS Delivery to MOC (Qty2) and to EROS (Qty3) TBP $TBP TBP 7 OOpS Delivery to MOC (Qty 2) TBP $TBP TBP 8 SC SoftSim Delivery to MOC (Qty 3) TBP $TBP TBP 9 Launch Vehicle Interface Simulator (Qty 1) Delivery TBP $TBP TBP

10 SC Baseline Comprehensive Performance Test (CPT) Completion

TBP $TBP TBP

11 RF Suitcase Simulator Delivery to EROS (Qty1) TBP $TBP TBP 12 SC EIDP Delivery and Acceptance TBP $TBP TBP 13 Operational Development Tools Delivery TBP $TBP TBP 14 Instrument Integration Completion TBP $TBP TBP 15 RF Compat Testing Completion TBP $TBP TBP 16 Mission Readiness Test (MRT) 1-4 completion TBP $TBP TBP

17 Observatory Pre-Environmental Review (PER) Completion

TBP $TBP TBP

18 Observatory Vibration Test Completion TBP $TBP TBP 19 Observatory EMI/EMC Test Completion TBP $TBP TBP 20 Observatory TVac Test Completion TBP $TBP TBP 21 Acoustics Test Completion TBP $TBP TBP 22 MRT 5-7 Completion TBP $TBP TBP 23 Observatory Pre-Ship Review (PSR) Completion TBP $TBP TBP 24 Launch Site CPT Completion TBP $TBP TBP 25 Launch and Succesful Power Application to SC TBP $TBP TBP

26 Final Acceptance – On-Orbit Acceptance Review (AOR) (Clasue H.16) (10%)

TBP $TBP TBP