Attachment T - L10 Major Payment Events Payment Schedule and Completion Criteria.pdf
PDF 1 MB Posted
- Attached to
- Landsat 10 Spacecraft _ DRAFT RFP
- Solicitation number
- 80GSFC26D0015
About this file
This document is Attachment T to RFP 80GSFC26R0015, establishing the Landsat 10 Spacecraft Major Payment Events, Payment Schedule, and Completion Criteria for NASA's Goddard Space Flight Center.
The attachment defines 26 commercial milestone payment events spanning the entire Landsat 10 spacecraft development and deployment lifecycle, from major subcontract awards through final on-orbit acceptance. Key milestones include design reviews (System Requirements Review, Preliminary Design Review, Critical Design Review), deliverables of ground support equipment (CTSS, OOpS, SoftSim, LVIS, RF Suitcase Simulator), spacecraft assembly and testing (Comprehensive Performance Test), instrument integration, environmental testing (vibration, EMI/EMC, thermal vacuum, acoustics), mission readiness tests, pre-ship review, launch site testing, launch execution, and on-orbit acceptance review. Payment percentages, amounts, and schedules are designated as "TBP" (To Be Planned) throughout the document, indicating these values will be determined during contract negotiation. Each milestone contains detailed completion criteria that the Contracting Officer must verify before authorizing payment. Criteria typically require demonstration of successful test completion with acceptable results, delivery of data deliverables, closure of critical action items, and government approval of technical reviews and design documentation. The final 10% payment is withheld until the On-Orbit Acceptance Review (per Clause H.16), confirming the spacecraft meets all requirements including successful activation, calibration, appendage deployment, and specification compliance on-orbit.
View the file
Other files
Show all 46
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment No. T
Landsat 10 Major Payment Events, Payment Schedule, and
Completion Criteria
RFP 80GSFC26R0015
National Aeronautics and Space Administration
Goddard Space Flight Center
L10 Major Payments Events and Acceptance Criteria L10-SC-DESC-0058 Rev -
(This page intentionally left blank)
L10 Major Payments Events and Acceptance Criteria L10-SC-DESC-0058 Rev -
1. Commercial Milestone Payment Schedule The contractor shall complete all activities required for each Milestone Payment Event prior to submitting the respective invoice. The payment schedules are defined in Table 1.1 and the completion criteria are defined in Table 1.2.
Table 1.1 – Landsat 10 Commercial Milestone Payment Events
Payment Event
No.
Commercial Milestone Payment Event Payment
Percent Payment Amount
Months
ARO
1 Major Subcontracts Awarded TBP $TBP TBP
2 Spacecraft System Requirements Review (SRR) Completion
TBP $TBP TBP
3 Spacecraft Preliminary Design Review (PDR) Completion
TBP $TBP TBP
4 All Subcontracts Awarded TBP $TBP TBP
5 Spacecraft Critical Design Review (CDR) Completion
TBP $TBP TBP
6 CTSS Delivery to MOC (Qty2) and to EROS (Qty3) TBP $TBP TBP 7 OOpS Delivery to MOC (Qty 2) TBP $TBP TBP 8 SC SoftSim Delivery to MOC (Qty 3) TBP $TBP TBP 9 Launch Vehicle Interface Simulator (Qty 1) Delivery TBP $TBP TBP
10 SC Baseline Comprehensive Performance Test (CPT) Completion
TBP $TBP TBP
11 RF Suitcase Simulator Delivery to EROS (Qty1) TBP $TBP TBP 12 SC EIDP Delivery and Acceptance TBP $TBP TBP 13 Operational Development Tools Delivery TBP $TBP TBP 14 Instrument Integration Completion TBP $TBP TBP 15 RF Compat Testing Completion TBP $TBP TBP 16 Mission Readiness Test (MRT) 1-4 completion TBP $TBP TBP
17 Observatory Pre-Environmental Review (PER) Completion
TBP $TBP TBP
18 Observatory Vibration Test Completion TBP $TBP TBP 19 Observatory EMI/EMC Test Completion TBP $TBP TBP 20 Observatory TVac Test Completion TBP $TBP TBP 21 Acoustics Test Completion TBP $TBP TBP 22 MRT 5-7 Completion TBP $TBP TBP 23 Observatory Pre-Ship Review (PSR) Completion TBP $TBP TBP 24 Launch Site CPT Completion TBP $TBP TBP 25 Launch and Succesful Power Application to SC TBP $TBP TBP
26 Final Acceptance – On-Orbit Acceptance Review (AOR) (Clasue H.16) (10%)
TBP $TBP TBP
File details come from the government source that posted it. Updated .