This document is a Government Furnished Equipment/Information List (GFE/GFI) for the Landsat 10 spacecraft, issued by NASA's Goddard Space Flight Center under RFP 80GSFC26R0015.

The GFE section lists 19 items that NASA will provide to the spacecraft contractor, including the Landsat Instrument Suite (LandIS) with associated simulators, flight hardware, and ground support equipment. Key physical items include the LandIS instrument (delivery NET 9/20/29), flight mounting hardware, electrical connectors (quantity TBD at Instrument CDR + 6 months), and ground support equipment. The document also identifies government-furnished services including launch services (L-33 months through launch), Launch Services Provider support for environmental testing and payload adapter fit-checks (NET Launch - 12 months), payload processing facility services at the launch site (Selection Notice L-15 months, occupancy L-2 months through launch plus 7 days), and spacecraft propellant and pressurant (L-1 month). Additionally, NASA will provide command and telemetry processors (4 units at Simulator I&T start), Ground System to Spacecraft Integration Rack hardware, wideband data capture devices (2 units, Simulator deliveries - 6 months), and network compatibility equipment. The GFI section identifies three information items: LandIS instrument scripts, I&T procedures and command/telemetry database (delivery as agreed in Giver/Receiver List), LandIS CAD/FEM model (1 month ACA with updates as required), and LandIS thermal model (1 month ACA with updates as required). One TBD exists for the quantity of LandIS electrical connectors, with resolution due at Spacecraft CDR.

View the file

Other files

File Type Posted
Exhibit 6 - L10 Past Performance Questionnaire R.pdf PDF
Attachment S - L10 Time and Materials Rate Matrices Rev.pdf PDF
Attachment X DRD 5 - CAIRIA DRD.pdf PDF
Attachment E - L10 Spacecraft to Ground Interface Req Document (SC to GND IRD) Rev.pdf PDF
Enclosure 5 - Geometric Budget (GEB) Support Presentation.pdf PDF
Attachment F - L10 Observatory Environment Req Document (ObsERD)R.pdf PDF
Attachment T - L10 Major Payment Events Payment Schedule and Completion Criteria.pdf PDF
Exhibit 4 - L10 Gate Criteria Fill In R.pdf PDF
Enclosure 3 - L10 Design Reference Case - DRC-18 Definition.pdf PDF
Attachment P - L10 Acronym List.pdf PDF
Exhibit 2 - L10 Spacecraft and Observatory Environmental Testing Matrix Fill-in.pdf PDF
Attachment V - L10 C-SCRM Plan.pdf PDF
Attachment X DRD 3 - CPIC DRD.pdf PDF
Attachment X DRD 4 - CITAR DRD updated.pdf PDF
Exhibit 5 - L10 Spacecraft Specifications Fill-in.pdf PDF
Attachment A - L10 Statement of Work (SOW).pdf PDF
Attachment O - L10 Lexicon.pdf PDF
Attachment K - L10 Space Environmental Req Document (LSERD).pdf PDF
Attachment X DRD 2 - NASA C-SCRM Plan Questionnaire.xlsx XLSX spreadsheet
DRFP Landsat 10 80GSFC26R0015 Terms and Conditions.pdf PDF
Attachment X DRD 6 - SCV Reporting.pdf PDF
Attachment B - L10 SC CDRL and DID Rev.pdf PDF
Attachment X DRD 3 - CPIC DRD Template for IT Portfolio PPM Data Collection.xlsx XLSX spreadsheet
Attachment L - L10 Analytical Math Model Definitions (LAMMD) Rev.pdf PDF
DRFP L10 80GSFC26R0015 Cover Letter Sgn.pdf PDF
Enclosure 4 - L10 Geometric Error Budget (GEB).pdf PDF
Attachment N - L10 World Reference System - 3 Definition Rev.pdf PDF
Exhibit 1 - L10 Pricing Template.xlsx XLSX spreadsheet
Enclosure 1 - L10 Mission Synopsis Rev.pdf PDF
Attachment C - L10 Spacecraft Requirements Document (SC SRD).pdf PDF
Attachment I - L10 Payload to Launch Services Interface Description Doc (LS IDD) Rev.pdf PDF
Exhibit 3 - L10 Spacecraft Master Equipment List (MEL) Fill In.pdf PDF
Attachment D - L10 Spacecraft Interface Requirements Document (SCIRD).pdf PDF
Attachment Q - LandIS Simplified Mechanical Interface Control Drawing (MICD).pdf PDF
Attachment X DRD 4 - CITAR Report Template.xlsx XLSX spreadsheet
Attachment X DRD 1 - OCI Plan.pdf PDF
Attachment J - L10 Radiation Environments Description (LRED) Rev.pdf PDF
Attachment H - L10 Spacecraft Deliverable Items List (DIL).pdf PDF
Attachment X - Non-Technical Contract Data Requirements List.pdf PDF
Attachment R - L10 Spacecraft Contractor Standards.pdf PDF
Attachment U - L10 OCI Plan Rev.pdf PDF
Attachment W - Small Business Subcontracting Plan.pdf PDF
Enclosure 2 - L10 Observatory Quality Assurance Surveillance Plan.pdf PDF
Attachment G - L10 Spacecraft Simulator Req Document (SC Sim RD).pdf PDF
Attachment X DRD 2 - Security Requirements for Unclassified IT Resources DRD C-SCRM requirements.pdf PDF
Enclosure 3 - L10 Design Reference Case - DRC-18.pdf PDF
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment No. M

Landsat 10 Spacecraft Government Furnished Equipment/Information

List (SC GFE/GFI)

RFP 80GSFC26R0015

National Aeronautics and Space Administration Goddard Space Flight Center

Landsat 10 SC GFE/GFI L10-SC-LIST-0007 Revision D ii Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.

Landsat 10 Spacecraft Government Furnished Equipment/Information List (SC GFE/GFI)

Signature/Approval Page

Prepared by:

Electronic Signature in TDMS Approval Date in TDMS Cagatay Aymergen Date Landsat 10 Deputy Project Manager / Acting Observatory Manager

NASA/GSFC, Code 426

Approved by:

Cagatay Aymergen Date Landsat 10 Deputy Project Manager / Acting CCB Chair / Acting Observatory Manager

Ross Henry Date Landsat 10 Project Manager

Evan Webb Date Landsat 10 Mission Systems Manager NASA/GSFC, Code 533 iii Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.

CM Foreword This document is a Landsat 10 Project Configuration Management (CM)-controlled document.

Note: Prior to February 2026, the project name was Landsat Next (LNext).

For the purposes of configuration management, the prefixes “LNEXT” and “L10” are completely interchangeable. For example, LNEXT-MGMT-PLAN-0004 is the same as L10-MGMT-PLAN- 0004.

Changes to this document require prior approval of the applicable Configuration Control Board (CCB) Chairperson or designee. Proposed changes shall be submitted to the Landsat 10 CM Office (CMO), along with supportive material justifying the proposed change. Changes to this document will be made by complete revision.

Questions or comments concerning this document should be addressed to:

NASA/Goddard Space Flight Center Landsat 10 Project Office, Code 426 Attention: Configuration Management Office Greenbelt, Maryland 20771 iv Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.

Change History Log v Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.

List of TBDs/TBRs Hyperlink to TBx Location Summary Ind.

Name/Org.

Due Date

TBx-1 Section 1 TBD for quantity of LandIS electrical connectors Obs.

Manager

SC

CDR

vi Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.

Table of Contents SIGNATURE/APPROVAL PAGE ................................................................................................ II CM FOREWORD ..........................................................................................................................III CHANGE HISTORY LOG .......................................................................................................... IV

LIST OF TBDS/TBRS .................................................................................................................... V

TABLE OF CONTENTS .............................................................................................................. VI LIST OF FIGURES ...................................................................................................................... VI LIST OF TABLES ........................................................................................................................ VI

1.0 SPACECRAFT GFE ITEMS:

2.0 GFI ITEMS:

List of Figures No table of contents entries found.

List of Tables No table of contents entries found.

Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.

1.0 SPACECRAFT GFE ITEMS:

Number Item Qty Delivery Date GFE-1 Landsat Instrument Suite

(LandIS) Interface Simulator (LIS), including harnesses.

1 Spacecraft Critical Design Review (CDR) - 3 Months

GFE-2 LandIS Operations Simulator (LOpS)

3 Instrument Pre-Ship Review (PSR) – 6 months

GFE-3 LandIS Instrument 1 NET 9/20/29 GFE-4 LandIS Flight Mounting

Hardware A/R With Item 3

GFE-5 LandIS Electrical Connectors TBD Instrument CDR + 6 months GFE-6 LandIS Ground Support

Equipment including purge cart A/R With Item 3

GFE-7 Launch Service (to include Launch Service analysis results)

1 L – 33 months thru launch

GFE-8 LV Flight Umbilical Connectors, mated pairs for Observatory to Launch Vehicle umbilical connection

3 sets L-18 months

GFE-9 LV Electrical GSE Interface Connectors, mated pairs for each Satellite EGSE-to-LV EGSE test interface connections

3 sets L-18 months

GFE-10 Launch Services Provider Support (hardware and engineering) for Observatory Environmental Testing to include Separation Shock Test

1 NET Launch – 12 months (driven by Observatory mechanical environmental testing schedule)

GFE-11 Launch Services Provider Support (hardware and engineering) for Observatory-to- Flight Payload Adapter Fit-check (to include mechanical and electrical interfaces)

1 NET Launch – 12 months (driven by Observatory mechanical environmental testing schedule)

GFE-12 Payload Processing Facility Services at Launch Site (facility occupancy and related support services)

1 Selection Notice: L – 15 months Occupancy: L – 2 months thru launch + 7 days

GFE-13 Spacecraft Propellant and Pressurant

1 L – 1 month (est.)

GFE-14 Near Space Network (NSN) and Landsat Ground Network (LGN) Compatibility Equipment

1 RF Compatibility Test – 2 months

GFE-15 Drill Template for LandIS-SC Interface

1 Instrument CDR + 6 months

GFE-16 Command and Telemetry Processors

4 Start of Simulator Integration and Test (I&T) And Prior to first power up of the Spacecraft

GFE-17 Ground System to Spacecraft Integration Rack (GSSIR)

1 Spacecraft I&T start – 3 months

GFE-18 Wideband Data Capture (WDC) Device

2 Simulator deliveries – 6 months

Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.

GFE-19 External Network Wide Area Network (WAN) and equipment

1 Spacecraft I&T start – 3 months

Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.

2.0 GFI ITEMS:

Number Item Delivery Date GFI-1 LandIS Instrument Scripts, I&T

Procedures and Command and Telemetry Database

As agreed to in the Giver/Receiver List

GFI-2 LandIS CAD/FEM Model 1 month ACA. Updates as required and agreed to in the Giver/Receiver List.

GFI-3 LandIS Thermal Model 1 month ACA. Updates as required and agreed to in the Giver/Receiver List.