July 10, 2014, Rev 3 Schedule of Pricing Maintenance and Repair of Research Vessel Kiyi
Spec. Ref.
| 4.1 |
| Hauling, Blocking and Launching |
| 6.1 |
| Hull High Pressure Wash and Visual Inspection |
| 6.2 |
| Underwater Hull Coating |
| 6.3 |
| ABS Survey – Load Line |
| 6.4 |
| Transducer Well Inspection |
| 6.5 |
| Clean and Inspect All Tanks and Voids |
| 6.6 |
| Inspect Crane Pedestal |
| 7.1 |
| Inspect, Clean and Refurbish Propellers |
| 7.2 |
| Inspect Propulsion Shafts |
| 7.3 |
| Bow Thruster Inspection and Maintenance |
| 8.1 |
| Inspect and Coat Anchor Chain |
| 8.2 |
| Chain Locker Preservation |
| 8.3 |
| Inspect Topside Coating |
| 8.7 |
| Install Dripless Shaft Seals, Shaft Tachometers, & Temperature Sensors |
| 8.8 |
| Install Emergency Steering |
| 8.9 |
| Replace Bilge Pump & Install Fire Pump Switch |
| Option |
| 8.10 |
| Install Instrument Crane |
| Option |
| 8.11 |
| Modify Starboard Side Davit |
| Option |
| 8.12 |
| Replace Smoke & Fire Detection Sysmte |
| Option |
| 8.13 |
| Modify Steering Pump Selector Panel |
| Option |
| 8.14 |
| Install Additional Ventilation in Lazarette |
| Option |
| 8.15 |
| Inspect Toilet Flush Valves |
| Option |
| 8.16 |
| Relocate Starlink Antenna |
| Option |
| 8.17 |
| Change Coolant |
| Option |
| 8.18 |
| Modify Shower Sumps |
| Option |
| 8.19 |
| Window Inspection and Repair |
| Option |
| 8.20 |
| Dry Lab Power Repair |
| Option |
| 8.21 |
| Modify Tank Access Ladders |
TOTAL
LABOR RATES
Shipyard Labor: The Contractor’s fully loaded man-hour rate will be used for negotiating change orders, if necessary. The contractor agrees that the number of man hours included in its price proposal for such modifications shall include only direct production man-hours. For these purposes, direct production man-hours are for skilled labor at the journeyman level expended in direct production, inspection, repair, or installation as exemplified by the following functions:
Foremen and Shop Supervisors General Labor Rigging Staging/scaffolding Welding Machinists (inside and outside) Fire Watch Burning Brazing Abrasive cleaning/blasting Tank cleaning Carpentry Electrical Work Lagging Ship-fitting Painting Sheet-metal Work Pipefitting Diesel Mechanics Marine Chemist Nondestructive Testing Navigation/Communications Electronics Hydraulic Crane and winch inspection and maintenance Material handling & Warehousing
Project Management & Engineering: Project Management & Engineering support functions shall be considered to be included in the Offeror’s fully loaded rate for direct production man-hours. Examples of support functions include:
Planning Quality Assurance Testing Engineering Design Lofting
| G14PS00428 |
| Attachment D Schedule of Pricing |
Amendment 0002