This document contains an attachment for a construction and design experience project data sheet as well as information on a related federal contract opportunity for the restoration of outfitting capacity at Berth 6C in Portsmouth Naval Shipyard in Kittery, Maine.
The project data sheet attachment requests information on up to five relevant past construction or design projects to be submitted by offerors, including contract details, award and completion dates, project descriptions, types of work performed, and construction or design fees. The related federal contract opportunity is a design-bid-build solicitation for the restoration of outfitting capacity at Berth 6C issued by the Department of the Navy Naval Facilities Engineering Command. It provides the solicitation number, name, opportunity type, agency details, and notes that a full RFP is attached. The response is due by the date specified in the RFP.
View the file
Other files for this federal contract opportunity
Show all 34
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT C
CONSTRUCTION & DESIGN EXPERIENCE PROJECT DATA SHEET
Project No. (check one) : CON #1 CON #2 CON #3 CON #4 CON #5
1. Experience for: Offeror Joint-Venture Other (Explain)
Firm Name:
Address:
Phone Number:
DUNS Number:
Point of Contact: Contact Phone Number:
2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain)
Percent of project work performed:
If subcontractor, who was prime (Name/Phone #):
3. Contract Number: Delivery/Task Order Number:
Title:
Location:
4. Award Date (mm/dd/yy): Completion Date (mm/dd/yy):
5. Type of work:
New Construction Renovation Repair Alteration Other (explain):
6. Type of Contract/Task Order: (Check ALL that apply)
Firm-Fixed Price Cost/Time and Material Other (explain):
Complete Block 7 for Construction Projects. Complete Block 8 for Design Projects.
7. Construction Project:
Award Amount: Final Price:
Type of Contract/Task Order: (Check ALL that apply)
Design-Build Design-Bid-Build Delivery/Task Order (IDIQ) Other (explain):
If Design-Build, identify the Lead Design Firm:______________________________________________
8. Design Project:
A/E Design Fee: Total Construction Value:
Type of Contract/Task Order: (Check ALL that apply)
Design-Build RFP Development Designer of Record Engineering Services Full Plans & Specs
Other (explain):
9. Provide a detailed description of the project and the relevancy to the project requirements of this RFP (i.e.:
unique features, square footage, construction methods), including any sustainable features or USGBC LEED certifications. If design-build, include a description of the design-effort.
10. Provide a detailed description of what work your firm self-performed on this project:
11. Other Information: