1659622spc01of01.pdf

PDF 17 MB Posted

Attached to
Restore Outfitting Capacity, Berth 6C Federal contract opportunity
Solicitation number
N4008522R2578
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

This document provides details on a federal solicitation opportunity for the Department of the Navy Naval Facilities Engineering Command. Solicitation number N4008522R2578 seeks bids to restore outfitting capacity at berth 6C at the Portsmouth Naval Shipyard in Kittery, Maine. As outlined in the attached request for proposal, the scope of work involves restoring outfitting capacity at the specified berth. No response deadline, award date, pricing terms, or set-asides are included. The sole agency involved is the Department of the Navy Naval Facilities Engineering Command.

View the file

Other files for this federal contract opportunity

Other files attached to Restore Outfitting Capacity, Berth 6C, newest first.
File Type Posted
N4008522R2578 AMENDMENT 0006.pdf PDF
AMENDMENT 0005_Revised Sheet G-106 - Phase 3.pdf PDF
N4008522R2578 AMENDMENT 0005.pdf PDF
REV2_Berth 6 Bid Schedule.pdf PDF
N4008522R2578 AMENDMENT 0004.pdf PDF
N4008522R2578 AMENDMENT 0003.pdf PDF
Amendment 0003_Sheet ES507.pdf PDF
Revised Berth 6_Final Bid Schedule.pdf PDF
N4008522R2578 AMENDMENT 0002.pdf PDF
N4008522R2578 AMENDMENT 0001.pdf PDF
1975 - Eval. of Exisiting Crane Foundations Berth 6.pdf PDF
Appendix B Berth 6 Geotechnical Report.pdf PDF
Appendix A Berth 6 HAZMAT Survey.pdf PDF
ATTACHMENT E SPCD.docx DOCX document
1977-Additional Crane Rail System Construction Drydock No. 1 Berths 6 7.pdf PDF
2002 - 1728A Berth 6 Bollards - Drawings.pdf PDF
2000 - 1337C Berth 5 and 6 Repairs Drawings.pdf PDF
2014-Structural Repairs to Berths 6A 6B and 6C.pdf PDF
1974 - Berth 6 Repairs.pdf PDF
1943 - Berth 6 Crane Track Foundations.pdf PDF
B6_Updated Final Design Drawings_Signed.pdf PDF
Berth 6_Final Bid Schedule.pdf PDF
ATTACHMENT C Construction and Design Exp Project Data Sheet.pdf PDF
ATTACHMENT B Past Performance Questionnaire.pdf PDF
Attachment A - PPI Inquiry Log.xls XLS spreadsheet
ATTACHMENT F SMALL BUSINESS SUBCONTRACTING PLAN.docx DOCX document
ATTACHMENT D HISTORICAL SMALL BUSINESS UTILIZATION.docx DOCX document
1982 - Track Replacement Berth 6.pdf PDF
Appendix D Berth 6 eOMSI Workbook.xlsx XLSX spreadsheet
UFGS4288 Submittal Register.xlsx XLSX spreadsheet
Attachment G - PIEE Vendor Access Instructions.pdf PDF
2019-Sea Level Rise Mitigation Wall B5 AND B6A_Rev10.4.19.pdf PDF
Appendix E Berth 6 NAVFAC ISRL.XLSX XLSX spreadsheet
N4008522R2578.pdf PDF
Show all 34

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WORK ORDER NO.

At the

PREPARED BY:

APPROVED BY:

Specifications:

For Commander, NAVFAC:

Date:

Submitted By: Date:

CONTRACT NO. N40085-21-R-0068

Civil Utilities: Steven Sargent, P.E.

Structural: Eric Levesque, P.E.

Geotechnical: John DiGenova, P.E.

Mechanical: Bruce L'ltalien, P.E.

Electrical: Wayne Whippie, P.E.

Fire Protection: Laura E. Clebak, P.E.

Help Note All fields can be edited. If you have trouble selecting a field, either use the tab key or click "highlight fields" in Acrobat 7. Fields that are not needed can be selected and deleted. Tool tips with "additional field" can be deleted or changed. The contract number can also be deleted or changed.

Berth 6 Repairs and Improvements 1659622

PROJECT TABLE OF CONTENTS Page 1

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 15 02/11 LIST OF DRAWINGS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 08/15 SUMMARY OF WORK

01 14 00.00 22 WORK RESTRICTIONS (PWD ME) PNSY

PROJECTS

01 20 00.00 22 03/17 PRICE AND PAYMENT PROCEDURES (PWD ME)

DESIGN-BID-BUILD PROJECTS

01 30 00 02/2020 ADMINISTRATIVE REQUIREMENTS

01 31 23.13 22 03/20 ELECTRONIC CONSTRUCTION AND FACILITY

SUPPORT CONTRACT MANAGEMENT SYSTEM

01 32 17.00 25 03/15 NETWORK ANALYSIS SCHEDULES (NAS) (PWD

ME)

01 33 00 05/11 SUBMITTAL PROCEDURES

01 35 26.00 22 2/19 GOVERNMENTAL SAFETY REQUIREMENTS (PWD

ME)

01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS

01 44 00.22 08/17 ARCHAEOLOGICAL MONITORING (PWD ME)

01 45 00.00 20 07/15 QUALITY CONTROL (PWD ME)

01 50 00.00 22 02/2020 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS (PWD ME)

01 57 19.00 22 02/19 TEMPORARY ENVIRONMENTAL CONTROLS -

PORTSMOUTH NAVAL SHIPYARD (PWD ME)

01 74 19.00 22 04/15 CONSTRUCTION AND DEMOLITION WASTE

MANAGEMENT (PWD ME)

01 78 00.00 22 07/15 CLOSEOUT SUBMITTALS (PWD ME)

01 78 23 08/15 OPERATION AND MAINTENANCE DATA

01 78 24.00 22 02/15 FACILITY ELECTRONIC OPERATION AND

MAINTENANCE SUPPORT INFORMATION (eOMSI)

01 91 13 03/15 GENERAL COMMISSIONING REQUIREMENTS

(PWD ME)

DIVISION 02 - EXISTING CONDITIONS

02 41 00 05/10 DEMOLITION

02 83 00.00 22 11/18 LEAD, CHROMIUM, AND CADMIUM

REMEDIATION (PNSY PROJECTS)

DIVISION 03 - CONCRETE

03 30 00 02/19 CAST-IN-PLACE CONCRETE

03 45 33 05/16 PRECAST STRUCTURAL CONCRETE

DIVISION 05 - METALS

05 05 23.16 08/18 STRUCTURAL WELDING

05 12 00 08/18 STRUCTURAL STEEL

05 30 00.01 05/15 MOORING HARDWARE

05 51 00 02/17 METAL STAIRS

05 52 00 02/18 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 73 01 05/18 FIBERGLASS REINFORCED PLASTIC (FRP)

PROJECT TABLE OF CONTENTS Page 2

GRATING

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 13 53 02/16 ELASTOMERIC SHEET WATERPROOFING

07 84 00 05/10 FIRESTOPPING

DIVISION 09 - FINISHES

09 97 13.26 02/16 COATING OF EXISTING STEEL WATERFRONT

STRUCTURES

DIVISION 22 - PLUMBING

22 15 13.00 20 04/06 HIGH-PRESSURE COMPRESSED AIR SYSTEM

22 15 14.00 40 11/17 GENERAL SERVICE COMPRESSED-AIR

SYSTEMS, LOW PRESSURE

22 15 43 11/14 NITROGEN PIPING IN PREFABRICATED

CONDUIT SYSTEM

22 15 50 11/14 NITROGEN PIPING IN CONCRETE DUCTS

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 03 00.00 20 08/10 BASIC MECHANICAL MATERIALS AND METHODS

23 22 13.35 40 02/17 STEAM TRAPS

DIVISION 26 - ELECTRICAL

26 05 33 01/07 DOCKSIDE POWER CONNECTION STATIONS

26 08 00 08/08 APPARATUS INSPECTION AND TESTING

26 11 16 02/10 SECONDARY UNIT SUBSTATIONS

26 13 00 11/14 SF6/HIGH-FIREPOINT FLUIDS INSULATED

PAD-MOUNTED SWITCHGEAR AND PAD-MOUNTED

VOLTAGE REGULATORS

26 24 13 05/15 SWITCHBOARDS

26 27 29 04/06 MARINA ELECTRICAL WORK

26 51 00 05/20 INTERIOR LIGHTING

26 56 00 05/20 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING

SYSTEM

DIVISION 31 - EARTHWORK

31 23 00.00 22 10/2018 EXCAVATION AND FILL

31 68 13 11/08 ROCK ANCHORS

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 12 16 08/09 HOT-MIX ASPHALT (HMA) FOR ROADS

32 17 23 08/16 PAVEMENT MARKINGS

32 31 13.53 02/20 HIGH-SECURITY FENCES

DIVISION 33 - UTILITIES

33 11 00 02/18 FRESHWATER UTILITY DISTRIBUTION PIPING

33 20 00 04/08 PURE WATER UTILITY DISTRIBUTION PIPING

PROJECT TABLE OF CONTENTS Page 3

33 30 00 05/18 SANITARY SEWERAGE

33 31 23.00 10 08/18 SANITARY SEWER FORCE MAIN PIPING

33 34 01 04/08 WHEELER MAIN PIPING

33 40 00 02/10 STORM DRAINAGE UTILITIES

33 63 13.19 02/16 CONCRETE TRENCH HYDRONIC AND STEAM

ENERGY DISTRIBUTION

33 71 02 02/15 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

DIVISION 34 - TRANSPORTATION

34 11 00 04/08 RAILROAD TRACK AND ACCESSORIES

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 59 13.16 05/11 MARINE FENDERS

DIVISION 40 - PROCESS INTERCONNECTIONS

40 17 26.00 20 04/06 WELDING PRESSURE PIPING

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 22 13.33 05/10 PORTAL CRANE TRACK INSTALLATION

APPENDIX A – “Berth 6 Hazardous Material Survey”, November 23, 2020, completed by Absolute Resource Associates

APPENDIX B – “Geotechnical Data Report Berth 6 Repairs and Improvements, Portsmouth Naval Shipyard, Kittery, Maine”, dated: December 2020, prepared by Haley and Aldrich

APPENDIX C – Reference Drawings

APPENDIX D – eOMSI Workbook

APPENDIX E – NAVFAC ISRL

-- End of Project Table of Contents --

DOCUMENT 00 01 15

LIST OF DRAWINGS

02/11

PART 1 GENERAL

1.1 SUMMARY

This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."

1.2 CONTRACT DRAWINGS

Contract drawings are as follows:

DRAWING NO. PWD ME

DWG NO.

NAVFAC

DWG NO.

TITLE

G-001 12841763 TITLE SHEET

G-002 12841764 LIST OF DRAWINGS - 1

G-003 12841765 LIST OF DRAWINGS -2

G-004 12841766 GENERAL NOTES - 1

G-005 12841767 GENERAL NOTES - 2

G-101 12841768 WORK PLAN

G-102 12841769 SITE ACCESS PLAN

G-103 12841770 MILESTONE PLAN

G-104 12841771 PHASING PLAN - PHASE 1

G-105 12841772 PHASING PLAN - PHASE 2

G-106 12841773 PHASING PLAN - PHASE 3

G-107 12841774 PHASING PLAN - DRY DOCK 2 AREA

G-108 12841775 PHASING PLAN - CAISSION END WORK AREA

G-109 12841776 ARCHAEOLOGICAL SENSITIVE AREA PLAN

GU101 12841777 UTILITIES CONSTRUCTION REQUIREMENTS AND CONSTRAINTS

V-001 12841778 SURVEY NOTES AND TABLES

V-002 12841779 EXISTING CONDITIONS KEY PLAN

DOCUMENT 00 01 15 Page 1

V-101 12841780 EXISTING CONDITIONS PLAN - PART A

V-102 12841781 EXISTING CONDITIONS PLAN - PART B

V-103 12841782 EXISTING CONDITIONS PLAN - PART C

V-104 12841783 EXISTING CONDITIONS PLAN - PART D

V-105 12841784 EXISTING CONDITIONS PLAN - PART E

H-001 12841785 HAZARDOUS MATERIAL GENERAL NOTES

H-101 12841786 HAZARDOUS MATERIAL PLAN

B-101 12841787 BERTH 6 BORING PLAN

B-601 12841788 BORING LOGS - 1

B-602 12841789 BORING LOGS - 2

B-603 12841790 BORING LOGS - 3

B-604 12841791 BORING LOGS - 4

C-001 12841792 COMPOSITE UTILITIES LEGEND, NOTES AND ABBREVIATIONS

VU101 12841793 COMPOSITE EXISTING UTILITIES CONDITIONS PLAN PART

A

VU102 12841794 COMPOSITE EXISTING UTILITIES CONDITIONS PLAN PART

B

VU103 12841795 COMPOSITE EXISTING UTILITIES CONDITIONS PLAN PART

C

VU104 12841796 COMPOSITE EXISTING UTILITIES CONDITIONS PLAN PART

D

VU105 12841797 COMPOSITE EXISTING UTILITIES CONDITIONS PLAN PART

E

VU301 12841798 COMPOSITE EXISTING UTILTIES TYPICAL SECTIONS

VU501 12841799 COMPOSITE EXISTING UTILITIES DETAILS 1

VU502 12841800 COMPOSITE EXISTING UTILITIES DETAILS 2

VU503 12841801 COMPOSITE EXISTING UTILITIES DETAILS 3

CR101 12841802 COMPOSITE UTILITIES REMOVALS PLAN PART A

CR102 12841803 COMPOSITE UTILITIES REMOVALS PLAN PART B

CR103 12841804 COMPOSITE UTILITIES REMOVALS PLAN PART C

CR104 12841805 COMPOSITE UTILITIES REMOVALS PLAN PART D

CR105 12841806 COMPOSITE UTILITIES REMOVALS PLAN PART E

DOCUMENT 00 01 15 Page 2

CU101 12841807 COMPOSITE UTILITIES PLAN PART A

CU102 12841808 COMPOSITE UTILITIES PLAN PART B

CU103 12841809 COMPOSITE UTILITIES PLAN PART C

CU104 12841810 COMPOSITE UTILITIES PLAN PART D

CU105 12841811 COMPOSITE UTILITIES PLAN PART E

CU301 12841812 COMPOSITE UTILITIES TYPICAL SECTIONS

CU501 12841813 COMPOSITE UTILITIES DETAILS 1

CU502 12841814 COMPOSITE UTILITIES DETAILS 2

CF101 12841815 UTILITY DUCT DETAIL PLAN FRESHWATER

CF501 12841816 FRESHWATER DETAILS 1

CF502 12841817 FRESHWATER DETAILS 2

CP201 12841818 SEWER PROFILES

CP501 12841819 SEWER DETAILS

CW201 12841820 WHEELER PROFILES

CW501 12841821 WHEELER DETAILS

CC101 12841822 EROSION AND SEDIMENT CONTROL PLAN

CC501 12841823 EROSION AND SEDIMENT CONTROL NOTES AND DETAILS

CD101 12841824 CIVIL DEMOLITION PLAN - PART A

CD102 12841825 CIVIL DEMOLITION PLAN - PART B

CD103 12841826 CIVIL DEMOLITION PLAN - PART C

CD104 12841827 CIVIL DEMOLITION PLAN - PART D

CD105 12841828 CIVIL DEMOLITION PLAN - PART E

CD301 12841829 CIVIL DEMOLITION SECTIONS - 1

CD302 12841830 CIVIL DEMOLITION SECTIONS - 2

CS101 12841831 CIVIL SITE PLAN - PART A

CS102 12841832 CIVIL SITE PLAN - PART B

CS103 12841833 CIVIL SITE PLAN - PART C

DOCUMENT 00 01 15 Page 3

CS104 12841834 CIVIL SITE PLAN - PART D

CS105 12841835 CIVIL SITE PLAN - PART E

CS401 12841836 FENCE PART PLAN - 1

CS402 12841837 FENCE PART PLAN - 2

CS403 12841838 SUBSTATION YARD GRADING AND DRAINAGE PART PLAN

CS404 12841839 BERTH 6 GRADING AND DRAINAGE PART PLAN

CS405 12841840 SITE BOLLARD PART PLAN

CS501 12841841 REMOVABLE STAIR DETAILS - 1

CS502 12841842 REMOVABLE STAIR DETAILS - 2

CS503 12841843 MISCELLANEOUS DETAILS

CS504 12841844 GRADING AND DRAINAGE DETAILS - 1

CS505 12841845 GRADING AND DRAINAGE DETAILS - 2

CS506 12841846 FENCE DETAIL

ST101 12841847 STRUCTURAL PLAN - PART A

ST102 12841848 STRUCTURAL PLAN - PART B

ST103 12841849 STRUCTURAL PLAN - PART C

ST104 12841850 STRUCTURAL PLAN - PART D

ST105 12841851 STRUCTURAL PLAN - PART E

ST201 12841852 ABOVE-GRADE UTILITY DUCT PROFILE - 1

ST202 12841853 ABOVE-GRADE UTILITY DUCT PROFILE - 2

ST203 12841854 ABOVE-GRADE UTILITY DUCT PROFILE - 3

ST301 12841855 STRUCTURAL SECTIONS - 1

ST302 12841856 STRUCTURAL SECTIONS - 2

ST303 12841857 STRUCTURAL SECTIONS - 3

ST304 12841858 ABOVE-GRADE UTILITY DUCT SECTIONS -1

ST305 12841859 ABOVE-GRADE UTILITY DUCT SECTIONS -2

ST401 12841860 SERVICE BROW ANCHOR PART PLAN

DOCUMENT 00 01 15 Page 4

ST402 12841861 ROCK ANCHOR PART PLAN - 1

ST403 12841862 ROCK ANCHOR PART PLAN - 2

ST404 12841863 SCHEMATIC - MOORING HARDWARE CONSTRUCTION STAGES

ST405 12841864 ABOVE-GRADE UTILITY DUCT PART PLAN

ST501 12841865 MOORING HARDWARE CLEAT - 1

ST502 12841866 MOORING HARDWARE CLEAT - 2

ST503 12841867 MOORING HARDWARE BOLLARD - 1

ST504 12841868 MOORING HARDWARE BOLLARD - 2

ST505 12841869 MOORING HARDWARE BOLLARD - 3

ST506 12841870 MOORING HARDWARE BOLLARD - 4

ST507 12841871 MOORING HARDWARE FOUNDATION DETAILS - 1

ST508 12841872 MOORING HARDWARE FOUNDATION DETAILS - 2

ST509 12841873 MOORING HARDWARE FOUNDATION DETAILS - 3

ST510 12841874 MOORING HARDWARE GENERAL DETAILS

ST511 12841875 MISCELLANEOUS DETAILS

SJ101 12841876 STRUCTURAL MISCELLANEOUS PLAN - PART A

SJ102 12841877 STRUCTURAL MISCELLANEOUS PLAN - PART B

SJ103 12841878 STRUCTURAL MISCELLANEOUS PLAN - PART C

SJ104 12841879 STRUCTURAL MISCELLANEOUS PLAN - PART D

SJ105 12841880 STRUCTURAL MISCELLANEOUS PLAN - PART E

SJ501 12841881 GUARDRAIL AND MISCELLANEOUSE DETAILS

SJ502 12841882 PRECAST VAULT DETAILS

SJ503 12841883 EQUIPMENT PAD DETAILS

SJ504 12841884 RAIL PENETRATION DETAILS - 1

SJ505 12841885 RAIL PENETRATION DETAILS - 2

SJ506 12841886 RAIL PENETRATION DETAILS - 3

SJ507 12841887 RAIL PENETRATION DETAILS - 4

DOCUMENT 00 01 15 Page 5

SJ508 12841888 RAIL PENETRATION DETAILS - 5

SJ509 12841889 RAIL PENETRATION DETAILS - 6

SY101 12841890 ABOVE-GRADE UTILITY DUCT COVER PLAN

SY102 12841891 ABOVE-GRADE UTILITY DUCT COVER PART PLAN - 1

SY103 12841892 ABOVE-GRADE UTILITY DUCT COVER PART PLAN - 2

SY104 12841893 ABOVE-GRADE UTILITY DUCT COVER PART PLAN - 3

SY105 12841894 ABOVE-GRADE UTILITY DUCT COVER PART PLAN - 4

SY106 12841895 ABOVE-GRADE UTILITY DUCT COVER PART PLAN - 5

SY107 12841896 ABOVE-GRADE UTILITY DUCT COVER PART PLAN - 6

SY108 12841897 ABOVE-GRADE UTILITY DUCT COVER PART PLAN - 7

SY109 12841898 ABOVE-GRADE UTILITY DUCT COVER PART PLAN - 8

SY110 12841899 ABOVE-GRADE UTILITY DUCT COVER PART PLAN - 9

SY111 12841900 ABOVE-GRADE UTILITY DUCT COVER PART PLAN - 10

SY501 12841901 STRUCTURAL COVER DETAILS - 1

SY502 12841902 STRUCTURAL COVER DETAILS - 2

SY503 12841903 STRUCTURAL COVER DETAILS - 3

SY504 12841904 STRUCTURAL COVER DETAILS - 4

SY505 12841905 STRUCTURAL COVER DETAILS - 5

SY506 12841906 STRUCTURAL COVER DETAILS - 6

SS001 12841907 STRUCTURAL SUPPORTS NOTES, DESIGN LOADS AND

ABBREVIATIONS

SS101 12841908 STRUCTURAL SUPPORTS PLAN 1

SS102 12841909 STRUCTURAL SUPPORTS PLAN 2

SS401 12841910 BELOW-GRADE UTILITY DUCT PLAN, SECTION AND DETAILS

SS402 12841911 LOAD CENTER VAULT PLANS

SS403 12841912 LOAD CENTER VAULT SECTIONS

SS404 12841913 VOLTAGE REGULATOR CONCRETE PAD PLANS, DETAILS AND

NOTES

SS405 12841914 BELOW-GRADE UTILITY DUCT PLAN AND DETAIL

DOCUMENT 00 01 15 Page 6

SS501 12841915 STRUCTURAL SUPPORTS DETAILS

SS502 12841916 LOAD CENTER VAULT DETAILS 1

SS503 12841917 LOAD CENTER VAULT DETAILS 2

M-001 12841918 MECHANICAL LEGEND AND ABBREVIATIONS

MT101 12841919 UTILITY DUCT DETAIL PLAN STEAM AND CONDENSATE

MT501 12841920 STEAM PIPING DETAILS 1

MT502 12841921 STEAM PIPING SCHEDULES AND DETAILS

MT503 12841922 STEAM PIPING SECTIONS AND DETAILS

MA101 12841923 UTILITY DUCT DETAIL PLAN HIGH PRESSURE AIR

MA501 12841924 HIGH PRESSURE AIR DETAILS 1

MA502 12841925 HIGH PRESSURE AIR DETAILS 2

MC101 12841926 UTILITY DUCT DETAIL PLAN LOW PRESSURE COMPRESSED

AIR

MC501 12841927 LOW PRESSURE COMPRESSED AIR PIPING DETAILS 1

MC502 12841928 LOW PRESSURE COMPRESSED AIR PIPING DETAILS 2

MN101 12841929 UTILITY DUCT DETAIL PLAN LOW PRESSURE NITROGEN

MN201 12841930 LOW PRESSURE NITROGEN PROFILES

MN501 12841931 NITROGEN PIPING DETAILS 1

MN502 12841932 NITROGEN PIPING DETAILS 2

MP101 12841933 UTILITY DUCT DETAIL PLAN PURE WATER

MP501 12841934 PURE WATER PIPING DETAILS 1

MP502 12841935 PURE WATER/NITROGEN SERVICE BRANCH CABINET ENCLOSURE

MP503 12841936 PURE WATER PIPING DETAILS 2

MU101 12841937 BERTH 6 UTILITIES - DRY DOCK 2 TUNNEL EXISTING

CONDITIONS, REMOVALS, AND STEAM PIPING PLANS

MU102 12841938 BERTH 6 UTILITIES - DRY DOCK 2 TUNNEL EXISTING

CONDITIONS, REMOVALS, AND CONDENSATE PIPING PLANS

DOCUMENT 00 01 15 Page 7

MU105 12841939 BERTH 6 UTILITIES - DRY DOCK 2 TUNNEL EXISTING

CONDITIONS, REMOVALS, AND PURE WATER PIPING PLANS

MU106 12841940 BERTH 6 UTILITIES - DRY DOCK 2 TUNNEL EXISTING

CONDITIONS, REMOVALS, AND HIGH PRESSURE AIR PIPING

PLANS

MU201 12841941 DRY DOCK 2 MECHANICAL UTILITY PIPING

MU501 12841942 BERTH 6 UTILITIES - DRY DOCK 2 UTILITY TUNNEL STEAM

PIPING DETAILS

MU502 12841943 DRY DOCK 2 PIPING SECTIONS AND ELEVATION

E-001 12841944 ELECTRICAL SYMBOLS, ABBREVIATIONS AND GENERAL NOTES

ED101 12841945 ELECTRICAL REMOVALS PLAN PART A

ED102 12841946 ELECTRICAL REMOVALS PLAN PART B

ED103 12841947 ELECTRICAL REMOVALS PLAN PART C

ED104 12841948 ELECTRICAL REMOVALS PLAN PART D

ED105 12841949 ELECTRICAL REMOVALS PLAN PART E

ED501 12841950 ELECTRICAL REMOVALS DETAILS

ED601 12841951 LOAD CENTER 10 REMOVALS ONE-LINE DIAGRAM

ES101 12841952 ELECTRICAL SITE PLAN PART A

ES102 12841953 ELECTRICAL SITE PLAN PART B

ES103 12841954 ELECTRICAL SITE PLAN PART C

ES104 12841955 ELECTRICAL SITE PLAN PART D

ES105 12841956 ELECTRICAL SITE PLAN PART E

ES106 12841957 ELECTRICAL SITE PLAN PART F

ES107 12841958 ELECTRICAL SITE PLAN PART G

ES108 12841959 ELECTRICAL SITE PLAN PART H

ES201 12841960 ELECTRICAL DUCTBANK PROFILES 1

ES202 12841961 ELECTRICAL DUCTBANK PROFILES 2

ES203 12841962 COMMUNICATIONS DUCTBANK PROFILES

ES401 12841963 LOAD CENTER 10 AND SUBSTATION YARD PART PLAN

DOCUMENT 00 01 15 Page 8

ES402 12841964 LOAD CENTER 22 AND SUBSTATION 6 YARD PART PLAN

ES403 12841965 LOAD CENTER 22 VAULT POWER AND LIGHTING PLANS

ES501 12841966 INDUSTRIAL POWER DETAILS

ES502 12841967 SHORE POWER STATION AT BERTH 6C DETAILS

ES503 12841968 SHORE POWER STATION POWER DETAILS

ES504 12841969 SUPER SHORE POWER STATION POWER DETAILS

ES505 12841970 LOAD CENTER 10 DETAILS

ES506 12841971 LOAD CENTER 22 DETAILS

ES507 12841972 HEAT TRACE DETAILS

ES508 12841973 VOLTAGE REGULATOR AND PAD MOUNTED TRANSFORMER

DETAILS

ES509 12841974 MEDIUM VOLTAGE SWITCH AND SECTIONALIZING CABINET

DETAILS

ES510 12841975 SITE ELECTRICAL DETAILS 1

ES511 12841976 SITE ELECTRICAL DETAILS 2

ES512 12841977 SITE ELECTRICAL DETAILS 3

ES513 12841978 SITE ELECTRICAL DETAILS 4

ES514 12841979 SITE ELECTRICAL DETAILS 5

ES520 12841980 MANHOLE FOLDOUT DETAILS 1

ES521 12841981 MANHOLE FOLDOUT DETAILS 2

ES522 12841982 MANHOLE FOLDOUT DETAILS 3

ES523 12841983 MANHOLE FOLDOUT DETAILS 4

ES601 12841984 PARTIAL ONE-LINE DIAGRAM

ES602 12841985 SHORE POWER ONE-LINE DIAGRAMS

ES603 12841986 LOAD CENTER ONE-LINE DIAGRAMS

ES604 12841987 PANELBOARD SCHEDULES

ES605 12841988 ELECTRICAL SCHEDULES

EL701 12841989 LIGHTING FIXTURE SCHEDULE AND DETAILS

ET401 12841990 BUILDING 343 TECHNOLOGY PART PLANS

DOCUMENT 00 01 15 Page 9

ET402 12841991 BUILDING 79 FIRST FLOOR TECHNOLOGY PART PLAN

ET501 12841992 TELECOMMUNICATIONS DETAILS

ET601 12841993 TELECOMMUNICATIONS RISER DIAGRAMS

1.3 SUPPLEMENTARY DRAWINGS

These supplementary drawings may not be a part of the contract but are included with the drawings for information.

1.3.1 Reference Drawings

The reference drawings are intended only to show the original construction. Drawings are the property of the Government and must not be used for any purpose other than that intended by the contract.

1.3.2 Boring Logs

The Government does not guarantee that borings indicate actual conditions, except for the exact locations and the time that they were made. Refer to Contract Drawings for boring logs.

1.3.3 Subsurface Data

Subsurface data is provided in APPENDIX B - Geotechnical Data Report Berth 6 Repairs and Improvements, Portsmouth Naval Shipyard, Kittery, Maine, PREPARED BY HALEY & ALDRICH.

-- End of Document --

DOCUMENT 00 01 15 Page 10

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Salvage Plan; G

Work Sequencing And Preparation Plan; G

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes all labor, material, equipment, transportation, supervision and incidental related work required to complete repairs and improvements to Berth 6 at the Portsmouth Naval Shipyard (PNSY) to create two UFC compliant outfitting berths.

The project includes the following:

a. Installation of concrete curb along the offshore face of Berth 6.

b. Providing the required electrical, communication, and utility improvements.

c. Providing a raised concrete utility trench.

d. Providing mooring hardware along the berth.

e. Providing concrete pads for the Shipyard equipment.

f. Providing miscellaneous appurtenances.

1.2.2 Project Milestone Requirements

Complete milestones to the limits shown on the Contract Drawings.

Milestone work elements include installation, testing, and acceptance by the Government of each component of the work.

a. Milestone 1 Berth 6B/C - 08/15/2022

b. Milestone 2 Berth 6A/B - 04/30/2023

1.2.3 Location

The work is located along Berth 6 at Portsmouth Naval Shipyard located in Kittery, Maine.

1.3 PROJECT SEQUENCING REQUIREMENTS

a. Phase 1 - Berth 6B/C

b. Phase 2 - Berth 6A/B

c. Phase 2A - Berth 6A/B Repairs

SECTION 01 11 00 Page 1

1.3.1 Work Sequencing and Preparation Plan

Submit a Work Sequencing and Preparation Plan. All phasing must be in accordance with the Contract Drawings. The work sequencing and preparation plan must consider the following:

a. It is anticipated that several other projects will be in construction during this project including projects that have work within the limits of this project. Coordinate all work and access with other contractors through the Contracting Officer.

b. Coordinate the construction schedule with the Shipyard's berthing schedule. Waterside work is not permitted within 100 feet of a berthed vessel. Landside work is not permitted within 50 feet of a berthed vessel.

c. No outages to emergency access is permitted, including crane rail crossings.

1.4 OCCUPANCY OF PREMISES

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.5 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.6 LOCATION OF UNDERGROUND UTILITIES

Verify location of underground utilities in accordance with Section

01 35 26.00 22 GOVERNMENTAL SAFETY REQUIREMENTS (PWD ME).

1.6.1 Notification Prior to Excavation

Notify the Contracting Officer at least 15 days prior to starting excavation work.

1.7 SALVAGE MATERIAL AND EQUIPMENT

Items designated to be salvaged remain the property of the Government.

Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area.

Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials

SECTION 01 11 00 Page 2 and equipment until disposition by the Contracting Officer.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 3

SECTION 01 14 00.00 22

WORK RESTRICTIONS (PWD ME) PNSY PROJECTS

3/2020

PART 1 GENERAL

This specification applies to all Design-Bid-Build and Design-Build projects located on the Portsmouth Naval Shipyard.

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 241 (2019) Standard for Safeguarding Construction, Alteration, and Demolition Operations

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel; G

1.3 SPECIAL SCHEDULING REQUIREMENTS (PNSY)

a. The facility will remain in operation during the entire construction period. Conduct operations so as to cause the least possible interference with normal operations of the Portsmouth Naval Shipyard.

b. Permission to interrupt any Portsmouth Naval Shipyard roads, crane rail, railroads, and/or utility services must be submitted to the Contracting Officer in writing a minimum of 15 calendar days prior to the desired date of interruption.

1.3.1 Project Restrictions

a. It is anticipated that several other projects will be in construction during this project including projects that have work within the limits of this project. Coordinate all work and access with other contractors through the Contracting Officer.

b. Coordinate the construction schedule with the Shipyard's berthing schedule. Waterside work is not permitted within 100 feet of a berthed

SECTION 01 14 00.00 22 Page 1 vessel. Landside work is not permitted within 50 feet of a berthed vessel.

1.4 ACCESS AND USE OF PREMISES (PNSY)

Notify the Contracting Officer 30 days in advance for any wide loads.

Contact the Contracting Officer to determine if there are other access limitations at the Portsmouth Naval Shipyard.

Ensure that all personnel employed on the Portsmouth Naval Shipyard become familiar with and obey Portsmouth Naval Shipyard regulations. Keep within the limits of the work and avenues of ingress and egress. Do not enter restricted areas unless required to do so and until cleared for such entry.

All equipment must be conspicuously marked with company signage for identification.

1.4.1 Subcontractors and Personnel Contacts

Furnish a list of contact personnel to include subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.4.2 Identification Badges and Installation Access

a. Application for and use of badges will be as directed.

Contact the Facility's Installation Visitor Control Center to obtain the appropriate credentials for access to the Portsmouth Naval Shipyard.

Additional information may be found in Attachment A and at the Commander, Navy Installations Command website at https://www.cnic.navy.mil/om/dbids.html.

All personnel without appropriate credentials, will need two forms of approved identification for access to the Portsmouth Naval Shipyard.

See Attachment B for the list of acceptable identification documents.

b. One-Day Passes: Personnel will have to obtain daily passes, be subject to daily mandatory vehicle inspection, and will have limited access to the Portsmouth Naval Shipyard. The Government will not be responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred.

1.5 STATION REGULATIONS

1.5.1 Radiological Indoctrination (PNSY)

All Contractors working at the Portsmouth Naval Shipyard are required to view a 15 minute video briefing on radiological postings and controls in use at the Portsmouth Naval Shipyard. The briefing will be given at the Pass Office prior to issue of security badges and vehicle passes.

Any Contractor employee who disregards, alters, moves, or otherwise tampers with a radiological posting, or who disobeys a radiological instruction, may be removed from the Portsmouth Naval Shipyard and denied future access.

SECTION 01 14 00.00 22 Page 2

1.5.2 Yellow Materials (PNSY)

Contractors working at the Portsmouth Naval Shipyard must not use yellow or orange-yellow colored materials for the following purposes: Protective clothing, hoods, sheeting, tarpaulins, polyethylene bottles or other containers, tapes, bags, banding, identification marks on tools, boundary markers, ribbons, vent ducts, temporary erosion control devices, survey ribbon, etc. Contact the Contracting Officer for a list of yellow items that have been approved for use on the Shipyard. Dispose of generated yellow colored waste off-yard. Shipyard refuse containers must not be used for disposal of yellow colored waste materials. Yellow colored items such as described above are of special significance within the Shipyard and are subject to strict controls. Yellow colored contract generated debris must be bagged in non-translucent containers, and promptly removed from Portsmouth Naval Shipyard.

1.5.3 Smoke Detectors (PNSY)

Ionization type smoke detectors and duct smoke detectors contain radioactive material and are prohibited from use on the Portsmouth Naval Shipyard. Photoelectric smoke detectors are the only type authorized for use on the Shipyard.

1.5.4 Radioactive Sources (PNSY)

All contracts involving radiation generating devices must conform to the requirements listed in Section 01 35 26.00 22 GOVERNMENTAL SAFETY REQUIREMENTS (PWD ME) and U.S. Army Corps of Engineers Safety Manual EM 385-1-1 . All requirements are to be submitted to the Contracting Officer at least 14 days prior to commencement of operations involving radiation generating devices. A requirements checklist will be provided by NAVFAC (COTs) Contractor Oversight Technician.

1.5.5 Laser Control

Comply with laser safety requirements under 21 CFR 1040 and ANSI 2136.1-1986 for any work under this contract utilizing lasers.

1.5.6 Energy Conservation

In cooperation with Government representatives, participate in an active program directed toward the efficient use of energy.

1.5.7 Fire Prevention (PNSY)

Require all employees to become familiar with fire prevention regulations within the Portsmouth Naval Shipyard to include the proper method of turning in a fire alarm, storage of flammable and combustible materials and control of combustible waste and trash. Any HOT WORK (welding, burning, grinding, cutting, etc.) requires a HOT WORK PERMIT prior to commencing such work. This permit is obtained from the Portsmouth Naval Shipyard's Fire Department via the Contracting Officer.

1.5.8 Identification and Control of Seamed (Welded) Pipe and Tubing (PNSY)

Submarine Safety regulations prohibit the use of seamed (welded) pipe or tubing within the Portsmouth Naval Shipyard, unless such pipe or tubing is identified and controlled so as to prevent its inadvertent substitution

SECTION 01 14 00.00 22 Page 3 for seamless pipe or tubing. The following requirements apply and will be strictly enforced:

Any seamed (welded) copper-nickel, carbon steel, carbon-moly steel, stainless steel, nickel-chromium-iron alloy, or nickel-copper pipe or tubing intended for use on the Shipyard must be identified in the following manner PRIOR TO DELIVERY TO THE SHIPYARD:

Use a lead-free white paint, to mark a 24-inch long stripe and the word "welded" alternately along the entire length of the pipe or tubing. Apply a one-half inch wide stripe unless the size of the pipe or tubing requires use of a narrower stripe.

Maintain positive control over seamed pipe or tubing until worked into place or removed from the Shipyard.

Seamless pipe or tubing may be substituted for any seamed (welded) pipe or tubing specified in the technical specifications.

The above requirements do not apply to square or rectangular tubing, copper or brass pipe or tubing, they also do not apply to piping or tubing which has been incorporated into equipment or fixtures prior to delivery to the Shipyard.

1.5.9 Pesticide and Herbicide Control

Do not apply pesticides nor herbicides unless specifically required by this contract. Where application of pesticides or herbicides is required, provide the submittals required by the specification and obtain written approval prior to any application. Contracting Officer will require review and approval of pesticides or herbicides submittals.

1.5.10 Smoking Policy

In accordance with NAVFAC policy, smoking is prohibited inside all buildings and other facilities except those areas specifically identified as smoking areas (e.g., smoking shelters). Smoking is not permitted within 20 feet of air intakes, doorways or windows.

1.5.11 Portal Crane Clearance Zone (PNSY)

Ensure there is no construction debris or materials within the Crane Clearance Zone (i.e., between the painted yellow lines on each side of the rail) unless a rail outage has been approved.

1.6 WORKING HOURS (PNSY)

Regular working hours must consist of a period established by the Contracting Officer between 7 AM and 3:30 PM, Monday through Friday, excluding Government holidays. The regular working hours must be confirmed with the Contracting Officer.

Work outside regular working hours requires Contracting Officer approval.

Provide written requests fifteen (15) Calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress and to allow scheduling of full time escorts in the building(s) if required. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.

SECTION 01 14 00.00 22 Page 4

1.7 WORK IN OCCUPIED BUILDING(S)

Work under this contract may be located in an occupied building. Move unfixed furniture away from the working area as required to perform the work; protect; and replace in original locations upon completion of the work. Leave fixed equipment in place and protect against damage or temporarily disconnect, relocate, protect, and reinstall at completion of work. If determined necessary by the Contracting Officer, the Government will remove and relocate other Government property in the areas of the buildings scheduled to receive work. After providing written notification, allow 15 calendar days for the Government to relocate Government property.

1.8 UTILITY CUTOVERS AND INTERRUPTIONS

Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays as approved by the Contracting Officer. Conform to procedures required in the paragraph "Work Outside Regular Hours." Anticipated costs must be included in the bid.

Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

Interruption to Water, Sanitary Sewer, Storm Sewer, Telephone Service, Electric Service, Air Conditioning, Heating, Fire Alarm, Compressed Air, and other utilities must be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours." This time limit includes time for deactivation and reactivation.

Operation of Shipyard Utilities: Do not operate nor disturb the setting of control devices in the Shipyard's utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. Notify the Contracting Officer in writing within 15 calendar days when such operation is required. The Contracting Officer will provide the Outage Request Form.

1.9 CRANE AND RAILROAD TRACKAGE INTERRUPTIONS (PNSY)

Crane and railroad trackage are considered utilities, and as such are subject to strict scheduling approvals. Where the following contract work is planned, submit written requests for Outages & Securements a minimum of 15 calendar days prior to the desired date of interruption to the Contracting Officer:

a. Track Outage:

Any excavation, that is within 10 feet of a rail that will extend below the grade of the cross ties.

Any work performed that will penetrate a track foundation.

Any work involving trackage replacement or repair.

Any work affecting the load bearing capacity of the trackage.

No work must be conducted in affected areas until a written approval to the request for outage is received.

b. Track Securement:

SECTION 01 14 00.00 22 Page 5

Track Securement differs from Track Outage in that it does not affect track certification. Track Securement requests must be prepared and submitted to the Contracting Officer to obtain scheduling approval from Code 740.2 before work that would curtail the use of tracks (e.g., placing equipment or hoses within the crane envelope or within the defined Crane Clearance Zones).

No work must be conducted in affected areas until a written approval to the request for securement is received.

1.10 WORK ADJACENT TO CIA SECURITY FENCING (PNSY)

Work adjacent to Portsmouth Naval Shipyard Controlled Industrial Area (CIA) fencing is strictly controlled to ensure security is maintained at all times.

Work which will breach CIA fencing is prohibited unless approval has been obtained from Head of Security Operations (Code 1122) and a Shipyard Police representative is at the worksite during the period that the fence has been breached.

A minimum of 30 calendar days prior to performing work which requires breaching the CIA security fence, arrange through the Contracting Officer to obtain Head of Security Operations approval and scheduling of the Shipyard Police representative. "Breaching the fence" is any repair, alteration, or other work which would allow access into the CIA either over, under, or through an opening in a CIA fence.

Conditions which breach the fence must be eliminated during all non-work periods to the satisfaction of the Shipyard Police representative. Do not leave the worksite until such conditions are eliminated. All materials used to close openings in fencing and method of installation must be the same type and construction as adjacent, undisturbed CIA fencing.

Except for temporary off-loading of materials, the clear zone adjacent to CIA fencing must remain clear of vehicles, materials, and equipment.

Personnel must be at the site throughout the entire time of any off-loading.

1.11 WORK ADJACENT TO AN OVERHEAD CRANE

Provide a minimum vertical clearance of three (3) inches between the highest point of the crane and the lowest overhead obstruction. For buildings where truss sag becomes a factor, increase the clearance as necessary to maintain the minimum required clearance.

The horizontal clearance between the end of the crane and the building columns, knee braces or any other obstructions must not be less than two

(2) inches with the crane centered on the runway rails. Pipes, conduits, etc. must not reduce this clearance.

The vertical clearance beneath a bridge crane is to be at least three (3) inches. This clearance is not applicable to the hook block unless it is in its up most position.

For work involving installation, adjustment, or replacement of rail fasteners (e.g. clips/bolts), verify the existing crane envelope and clearance measurements around the rail head prior to beginning work.

SECTION 01 14 00.00 22 Page 6

Notify the Government if the work will reduce the clearance between the bridge crane and rail fasteners and ensure newly installed items will not obstruct bridge crane travel.

Notify the Government to verify that crane clearance has been maintained when the work performed may have changed any physical dimensions of objects or structures adjacent to the crane (e.g., changing or servicing lighting fixtures/pendant assemblies, removal and reinstallation of pipes, conduits, junction boxes, etc.). If the crane is not available (e.g., undergoing maintenance, inspection, etc.), verify crane clearance by taking measurements using reference points (e.g., vertical and horizontal distance from the top of crane rail with respect to the crane envelope, vertical distance from the floor with respect to the crane envelope, etc.).

1.12 FIRE PROTECTION

1.12.1 Compliance (PNSY)

Comply with COE EM 385-1-1 , NFPA 241 and Portsmouth Naval Shipyard fire regulations. Obtain approval from the Portsmouth Naval Shipyard Fire Chief via the Contracting Officer prior to commencement of hot work operations.

1.12.2 Fired Kettles

Melt kettles for tar, asphalt, and similar materials must not be closer than 25 feet to buildings or combustible materials. Final location of the materials must be approved by the Portsmouth Naval Shipyard Fire Department. Provide a minimum of two 20 pound ABC all-purpose type extinguishers at the melting kettle and the area of hot material application. Equip kettles with proper heat controls and means of agitation to assure controlled uniform temperatures throughout contents to prevent spot heating. Do not heat contents above flash point.

1.13 SECURITY REQUIREMENTS

1.13.1 General

Employees and representatives performing work under this contract are required to be United States citizens. If naturalized, the individual must present their naturalization papers to the Security Officer for inspection. Foreign born personnel must present evidence of citizenship regardless of citizenship of parents, as required by immigration laws.

1.13.2 Access to the Portsmouth Naval Shipyard (PNSY)

Contract Clause "FAR 52.204-2, Security Requirements and Alternate II" and the following apply:

Access to areas designated as restricted NAVSEA spaces will require an escort by a Government Representative. Notify the Contracting Officer at least 14 Calendar Days in advance of the date access is required.

Obtain security badges and vehicle passes to enter the Portsmouth Naval Shipyard at the Portsmouth Naval Shipyard's Pass/Security Office. Furnish proof that employees are U.S. citizens to obtain badges to enter the Portsmouth Naval Shipyard.

Complete Department of Homeland Security Form I-9; Employment Eligibility

SECTION 01 14 00.00 22 Page 7

Verification for each employee and furnish proof that employees are U.S.

citizens to obtain badges to enter Portsmouth Naval Shipyard.

1.13.3 Application and Issue of Security Badges

"Temporary" Security Badges will be issued to personnel requiring access for less than two (2) work days upon satisfactory proof of U.S.

citizenship, in the form of an original or certified birth certificate, passport, or naturalization papers. A picture ID is required in addition to satisfactory proof of citizenship. See Attachment B.

"Permanent" (photo) Standard Access Control Badges will be issued to personnel requiring access for two (2) or more work days. Personnel will be required to complete an authorization application form for local record check, and a personal information sheet. The forms will be furnished following award of any contract resulting from this solicitation, at time of pre-performance or pre-construction conference.

In the event access is required to contract work areas not permitted by the level of security badge issued, such need must be demonstrated and an escort obtained.

STANDARD ACCESS CONTROL BADGES MUST BE ATTACHED TO THE OUTER GARMENT AND

DISPLAYED AT ALL TIMES WHILE ON THE PORTSMOUTH NAVAL SHIPYARD.

PERSONNEL MUST NOT ENTER AREAS FOR WHICH THEY HAVE NOT BEEN CLEARED.

WHERE A NEED HAS BEEN DEMONSTRATED TO ENTER SUCH AREAS, PERSONNEL WILL BE

UNDER CONSTANT ESCORT BY PERSONNEL WHO HAVE BEEN CLEARED. FAILURE TO

ADHERE TO POSTED SECURITY REQUIREMENTS MAY RESULT IN REMOVAL OF THE

EMPLOYEE FROM THE PORTSMOUTH NAVAL SHIPYARD WITH FUTURE ACCESS DENIED.

1.13.4 Application and Issue of Vehicle Passes (PNSY)

Vehicle passes will be issued upon satisfactory proof of a valid Operator's License, Vehicle Insurance, and State Vehicle Registration.

Temporary passes will be issued for short term or single trip requirements on a case by case basis. All vehicles permitted to enter or park on the Portsmouth Naval Shipyard must comply with the Portsmouth Naval Shipyard's traffic and parking regulations and must only park in assigned areas, which may or may not be in the vicinity of the site of the contract work.

Do not park a vehicle in such a manner that crane tracks, railroad tracks, and vehicle access routes are blocked. Vehicles left unattended which are blocking such access routes are subject to towing and loss of vehicle passes. Parking on the Portsmouth Naval Shipyard may be in excess of one-half mile from the worksite.

1.13.5 Application and Issue of Vehicle Passes for Entry into Portsmouth Naval Shipyard's Controlled Industrial Areas (CIA)

Vehicular access to the CIA will be minimized and all vehicles must comply with the following requirements:

Vehicles must visibly display a CIA vehicle entry pass and inspection pass from the Commercial Vehicle Inspection Station (CVIS), Building 386. CIA passes will only be issued to company owned or leased vehicles, rental vehicles rented in the company name, or privately owned vehicles the company has certified in writing, to be necessary in the performance of contracted work. CIA passes will be issued on weekends and holidays at Building 29, from the Watch Supervisor. Personnel not possessing the

SECTION 01 14 00.00 22 Page 8 level security badge required for CIA access must be accompanied by a properly badged escort to obtain the CIA vehicle pass.

Vehicles will only be allowed in the CIA for the transportation of tools, parts, and materials to and from the worksite. An exception to this policy, employees may be transported to and from the worksite after full vehicle inspection at CVIS if a specific security plan has been developed and approved by the Shipyard Security Officer.

Parking of privately owned or company owned vehicles not utilized in the execution of construction activities (e.g. not a working truck or specialty vehicle) within the CIA or in any project laydown space is prohibited.

1.13.6 Application and Issue of Crane Passes (PNSY)

Comply with EM 385-1-1 . For Cranes Passes at the Portsmouth Naval Shipyard to be valid, the Certificate of Compliance (FORM 16-1) must be completed and accepted.

1.13.7 Return of Badges and Vehicle Passes

Ensure all vehicle access permits and personnel badges are returned to the Security Officer when the need has ended. Account in writing for each missing pass or badge prior to final payment being made on the contract.

1.13.8 Security Responsibilities (PNSY)

Employees must not transport, drink, or have in their possession any alcoholic beverages. Possession of any controlled substances without a physician's prescription is also prohibited. Any employee appearing to be under the influence of intoxicating liquor or narcotics will be apprehended by Shipyard Police, escorted off of the Portsmouth Naval Shipyard, and turned over to the local Police Department.

Any vehicle found to contain controlled substances, including usable residue, may be seized and impounded. Within 24 hours of the work day following any vehicle seizure, the Portsmouth Naval Shipyard Police will have determined whether forfeiture of the vehicle is required. If not, the vehicle will be returned to the owner or authorized agent. If the vehicle is determined to be appropriate for forfeiture, the Portsmouth Naval Shipyard's Legal Officer will notify the Drug Enforcement Administration of such seizure and impoundment, for initiation of forfeiture proceedings pursuant to Title 2l, U.S. Code, Section 88l. Such actions may be taken regardless of whether the owner/operator of the vehicle had knowledge of the presence of drugs in the vehicle. The Government may pursue criminal or other disciplinary actions pursuant to Title l8, U.S. Code, Section l382.

Possession of firearms, ammunition and/or explosives is prohibited. In the event explosives are required for construction work, specific handling requirements and approvals must be obtained from the Security Officer via the Contracting Officer.

Cameras, video equipment, or similar photographic equipment must not be introduced into nor removed from the Portsmouth Naval Shipyard. In the event such equipment is required for performance of contract work, approvals must be obtained from the Security Officer via the Contracting Officer.

SECTION 01 14 00.00 22 Page 9

Weapons (firearms, personal knives with blades 2-1/2 inch long or greater, Mace, Pepper Spray etc.) are not permitted aboard the Shipyard.

The following are the penalties for any personnel that are found to be in possession of a camera or cell phone equipped with a camera taking pictures outside NAVSEA spaces:

1st Offense with pictures: Full investigation with security forces and NCIS, camera or cell phone confiscation, and depending on results of investigation 30 days restriction.

2nd Offense with pictures: The offender will be permanently barred from access to NAVSEA spaces.

Cameras, or cell phones equipped with cameras, are not allowed in any NAVSEA space such as the CIA, NWA, CNIA or Security Island.

If personnel is found with a camera equipped cell phone in a NAVSEA space, the Standard Access Control Badge (SACB) and Defense Biometric Identification System card (DBIDS) will be confiscated. Access to the installation will be denied and a Security Deficiency Log (SDL) will be issued.

General Process:

Cell phones with no pictures of NAVSEA spaces:

1st Offense: There is a 10 day deadline for completion of the SDL.

Credentials will be reissued to the offender once the SDL response is received from the contracting company, reviewed and accepted by the Security office.

2nd Offense: The offender will be permanently barred from access to NAVSEA spaces.

Cell phones with pictures of NAVSEA spaces:

1st Offense: The offender will be permanently barred from access to NAVSEA spaces.

At a minimum, all Superintendents & SSHO (and anyone acting in this capacity) must have a CIA compliant mobile phone on their persons any time while work is occurring at the contract jobsite(s). The phone number(s) associated with these phones must be provided during the pre-con meeting and work will not be allowed to proceed without one.

Laptops and any other computer, regardless of form factor, must not be introduced nor removed from Portsmouth Naval Shipyard without authorization. Only business use computers are allowed. Personally owned computers are not authorized on the Shipyard. If a computer is required to perform work on the Shipyard, a Visitors Portable Computer Equipment Registration form must be completed and submitted for approval. These forms can be obtained and completed at the pass office upon entrance to the Shipyard or through the Shipyard POC.

Any computing devices that also have or had an installed camera, must follow the same requirements as cell phones. If the computing device is visiting a NAVSEA space, it cannot have a camera. If the device has a

SECTION 01 14 00.00 22 Page 10 camera, the only acceptable remediation is that the camera be professionally removed or drilled out and the resulting void must be filled with an opaque epoxy.

In the event that a camera is required for the performance of the contracted work, approval must be obtained from the C1120 security office. In the event of any deviation from the requirement to remove and epoxy the camera, authorization must be sought from C1120. All requests for camera use and deviations should come to C1120 through your COR or Shipyard POC. Authorizations and approved computer registrations must remain with the devices and be presentable upon request. Devices without a documented approval or observed being used in a manner that violates the terms of the Visitor Portable Computer Equipment Registration agreement are subject to search and seizure.

Use of wireless networking and communication on the Shipyard requires prior authorization. Communication devices such as cellular hotspots and wireless routers must also be registered using the same Visitors Portable Computer Equipment Registration. This does not include air-cards and straight cellular data. It does include any device that transmits or broadcasts Wi-Fi, including cellular phones with the personal hot-spot feature enabled.

Broadband internet connections must be authorized prior to use on the Shipyard. All requests for physical cable service from an internet service provider (ISP) must be authorized and coordinated through C109.

Work through COR to request broadband access.

Driver use of a hand-held cellular phone in a moving vehicle on the Portsmouth…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .