Attachment A1- Professional Services and Construction Change Log.xlsx

XLSX spreadsheet 57 KB Posted

Attached to
Site Improvements at St. Aubin, Belle Isle, and Baby Creek CSO Facilities
Solicitation number
REQ - 0009198
Issued by
Wayne County, Michigan

About this file

This file is a Professional Services and Construction Change Log in Excel format associated with the Site Improvements project at St. Aubin, Belle Isle, and Baby Creek CSO Facilities in Michigan. The change log serves as a tracking document for modifications, amendments, and updates to the professional services and construction components of the project during its implementation. The document functions as an administrative record to document changes throughout the project lifecycle, including adjustments to scope, schedule, budget, and specifications for the study, design, and construction assistance services at the four designated facilities (St. Aubin, Belle Isle, Baby Creek, and St. Aubin Outfall site).

The change log captures essential project management information including the nature of each change, dates of change requests and approvals, affected cost impacts, schedule modifications, and responsible parties. This type of documentation is critical for maintaining project transparency, ensuring all stakeholders are informed of modifications, and providing an audit trail for contract administration purposes. The file enables project managers and contractors to track deviations from the original contract specifications and budget allocations, facilitating effective communication and documentation of any variations to the original scope of work.

View the file

Other files

File Type Posted
Attachment C2- CS-299_CSO_NA_Report_Vol_6_Appendices.pdf PDF
Attachment A2- Environmental Compliance and Permits Plan Form.xlsx XLSX spreadsheet
Attachment A3- GLWA PMP.docx DOCX document
Attachment B2 - Specification Section 01 78 40.A - OnBase Document Upload Template.XLS XLS spreadsheet
Attachment C3 - CSO Design Coordination_Key Decision Tracking Log.xlsx XLSX spreadsheet
Attachment B4 - Spec Section 01 79 23 - Instruction of Operation and Maintenance Personnel.PDF PDF
Attachment A4 - GLWA CAD BIM Standards - Version 0.0.pdf PDF
2-Attachment No. 2 - REQ-0009198- Vendor Certifications Solicitation.pdf PDF
6-Attachment No. 6 - REQ-0009198 - Task Cost Matrix.xlsx XLSX spreadsheet
8-Attachment No. 7 - REQ-0009198 - Statement of Minimum Qualifications (2).docx DOCX document
Attachment B1 - Specification Section 01 78 40 - OnBase Digital Document Turnover.PDF PDF
Attachment B5 - GLWA Master Division 01 Specifications.zip ZIP file
4-Attachment No. 4 - REQ-0009198 - B.I.D. Requirements.pdf PDF
3-Attachment No. 3 - REQ-0009198 - Scope of Work.pdf PDF
1-Attachment No. 1 - REQ-0009198 - GLWA Engineering Design Services Contract Rev 4-1-2026.pdf PDF
Attachment B3 - Specification Section 01 33 30 Asset Turnover Feb 2024.PDF PDF
Attachment C1 - CS-299_CSO_NA_Report_Vol_2_Sect_04-14.pdf PDF
5-Attachment No. 5 - REQ-0009198 - Solicitation Subcontractor List.pdf PDF
9-REQ-0009198 - Solicitation Cover - Instructions to Vendors.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION CHANGE

Construction Change Log
Project Name:Date Updated:MM/DD/YYYY
Contract #:Updated By:
Contractor:Today's Date:10/10/24
GLWA Project Manager:PCML:
Change Type/#Description of ChangeProposed Schedule Impact (days)Proposed Cost Impact ($)Negotiated Schedule Impact (days)Negotiated Cost
Impact ($)CategoryDate InitiatedDate CompletedChange
StatusDays OpenCO
No.CO Approval

Date

(MM/DD/YYYY)

CR 0140$10,00025$10,0003/12/20184/15/2018Closed34N/AN/A
CD 010$25,0000$18,0003/20/20184/15/2018Approved2615/10/18
FO 0110$12,50010$15,0003/25/20185/28/2018Approved642TBD
CR 0245$037$04/2/20184/15/2018Approved1315/10/18
CD 0220$8,5006/5/20187/15/2018Closed403TBD
FO 0210$015$07/1/20187/15/2018Approved143TBD
125$56,00087$43,000
NOTES:
CHANGE TYPE: CR (Change Request), CD (Change Directive), FO (Field Order)
CHANGE STATUS: Potential, Proposed, Approved, Closed
CHANGE CATEGORY: OR (Owner Request), DSC (Differing Site Conditions), DE (Design Error), DO (Design Omission), RR (Regulatory Requirements), Other
Auto Calculating Cell or Cell with Dropdown Menu

PROFESSIONAL SERVICES

Professional Services Contract Change Log
Project Name:Date Updated:MM/DD/YYYY
Contract #:Updated By:
Consultant:Today's Date:
GLWA Project Manager:PCML:
Change Type/#DescriptionDate InitiatedProject PhaseTaskTask NameSubtaskSubtask NameEstimated ImpactNegotiated ImpactDate CompletedDays OpenStatusCO NumberCO Approval DateComments
PlanningDesignProc.Constr.Time$Time$NumberNumber
Task Change Impact
CD 01
Task Change Impact
CR 02
Task Change Impact
Contract Change Impact0$00$0
NOTES:
CHANGE TYPE: CR (Change Request), CD (Change Directive), FO (Field Order)
CHANGE STATUS: Potential, Proposed, Approved, Closed
Auto Calculating Cell or Cell with Dropdown Menu

DROPDOWNS

CHANGE STATUSCHANGE CATEGORY
PotentialOR
ProposedDSC
ApprovedDE
ClosedDO
RR
Other