Attachment 8 - Monthly Progress Report Format.pdf
PDF 119 KB Posted
- Attached to
- FRP MATOC Midwest Region W912DY-20-R-0068 Federal contract opportunity
- Solicitation number
- W912DY20R0068
About this file
This document provides the monthly progress report format for demolition and abatement projects under the Facilities Reduction Program Midwest Multiple Award Task Order Contract. The report requires contractors to submit updates on schedule status, percentage completion for key activities including abatement, demolition, site restoration and cleanup, debris disposal and recycling. Additional details include mobilization and start dates for work, work scheduled in the current month and next 30-60 days, safety issues and events, and miscellaneous notes. Contractors must attach all required documentation and provide remarks on progress.
The related federal contract opportunity is a solicitation for the FRP Midwest Region Multiple Award Task Order Contract to provide demolition and abatement services at Department of Defense and other federal agency locations across 10 Midwestern states. General work includes planning, coordination and execution of building and facility removal along with emergency response to disasters. The North American Industry Classification code is 238910. The solicitation is issued by the Department of the Army Corps of Engineers Engineering Support Center Huntsville to establish on-call contracts for streamlined, low-cost demolition and abatement services in support of excess facility removal.
View the file
Other files for this federal contract opportunity
Show all 50
FRP MATOC Midwest Region W912DY-20-R-0068 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 8– Monthly Progress Report Format
FORMAT FOR MONTHLY PROGRESS REPORT (Attach All Required Documentation)
MONTHLY PROGRESS REPORT FOR: (MONTH / YEAR)
CONTRACTOR:
CONTRACT NUMBER/TASK ORDER: PROJECT TITLE:
LOCATION:
Contractor’s Project Manager: (Name/phone number) Customer Point of Contact: (e.g., DPW or USACE QA): (Name / phone number) Site Supervisor: (Name / phone number)
Basic Award: Mod 1: Mod 2:
Date: Date: Date:
Type: Type: Type:
Amount: Amount: Amount:
Schedule Status (ahead/behind): Describe pertinent points; attach updated schedule
ACTIVITY PERCENT
COMPLETE
CURRENT
COMPLETION
DATE
ORIGINAL
COMPLETION
DATE
Work Plans and Related Docs
Mob/Demob & Site Setup
ACM/ORM Abatement/ Removal:
Bldg/Groups of Bldgs
XXX1
XXX2
XXX3
Utility Cut/Cap/De-Energize:
Bldg/Groups of Bldgs
XXX1
Demolition:
XXX1
Site Restoration / Cleanup:
XXX1
Site Restoration / Cleanup:
XXX1
Debris Disposal: C & D
ACM ORM
Diversion/Re-use
Estimated Tons Tons this Month Tons to Date
Salvage Credits Estimated $ Value this Month
Value to Date
Final Report
DATE MOBILIZED TO SITE:
DATE EXECUTION STARTED:
WORK SCHEDULED THIS MONTH:
WORK SCHEDULED NEXT 30-60 DAYS: RECYCLING ACTIVITY:
SAFETY ISSUES/EVENTS: MISCELLANEOUS/TRAVEL:
REMARKS:
Attachment 8– Monthly Progress Report Format