Attachment 8 - Echo Amphitheater Parking Lot Pavement Preservation SOW.docx

DOCX document 10 MB Posted

Attached to
R3 National Forest’s Roads IDIQ
Solicitation number
127EAX26R0006
Issued by

About this file

This is a Statement of Work (SOW) for the Echo Amphitheater Pavement Preservation project within the Carson National Forest's Canjilon Ranger District in northern New Mexico. The project encompasses the preservation and maintenance of approximately 7,100 square yards of existing pavement at the Echo Amphitheater Recreation Site parking lot and site entrance, including paved surface cleaning, asphalt crack and joint sealing, asphalt patching, asphalt slurry seal application, permanent pavement markings, and permanent traffic control signage. The work is located at coordinates 36.3587, -106.5215 and involves intersection improvements at US Highway 84. The contractor must ensure all equipment is clean before entering Forest Service land, obtain a New Mexico Department of Transportation permit for highway right-of-way work, and submit a spill containment plan prior to construction. No fuel storage is permitted on-site, and the contractor must provide all materials, labor, equipment, tools, transportation, and supplies necessary for completion.

The period of performance is 45 calendar days from issuance of the Notice to Proceed, with the site remaining open weekends and federal holidays. The project must adhere to FP Standard Specifications (FP-24 U.S. Customary Units) for road and bridge construction, Forest Service Supplemental Specifications (FSSS), and project-specific requirements. Key submittals required within 30 days of contract award include a Work Execution Schedule, Safety Plan, and Hazardous Spill Plan, with a Public Traffic Control Plan due 30 days prior to Notice to Proceed. The contractor must minimize work during unsuitable weather conditions, protect existing features from damage during slurry seal and asphalt placement, obtain water commercially at its own expense, and coordinate with the Contracting Officer and Contracting Officer's Representative regarding any campground closures with three-week advance notice.

View the file

Other files

File Type Posted
127EAX26R0006 R3 Roads QA6.docx DOCX document
127EAX26R0006 R3 Roads QA5.docx DOCX document
127EAX26R0006 0002.pdf PDF
Attachment 13 - Echo Amphitheatre Wage Determination NM20260011 18 May 2026.pdf PDF
127EAX26R0006 R3 Roads QA4.docx DOCX document
Attachment 14 - NFSR 307-310 Road and Parking Lot Wage Determination NM20260011 18 May 2026.pdf PDF
127EAX26R0006 0001.pdf PDF
Attachment 4 - NFSR 307-310 Road and Parking Lot Reconstruction Plans (signed) v2.pdf PDF
Attachment 5 - NFSR 307-310 Road and Parking Lot Reconstruction Specifications v2.pdf PDF
Attachment 6 - NFSR 307-310 Road and Parking Lot Reconstruction SOI v2.pdf PDF
127EAX26R0006 R3 Roads QA3.docx DOCX document
127EAX26R0006 R3 Roads QA2.docx DOCX document
127EAX26R0006 R3 Roads QA1.docx DOCX document
Attachment 11 - Echo Amphitheater Parking Lot Pavement Preservation Schedule of Items.pdf PDF
Attachment 10 - Echo Amphitheater Parking Lot Pavement Preservation FS Supplement Specs.docx DOCX document
127EAX26R0006 Final.pdf PDF
Attachment 2 - Past Performance Questionnaire.docx DOCX document
Attachment 7 - NFSR 307-310 Road and Parking Lot Reconstruction Fire Plan.docx DOCX document
Attachment 9 - Echo Amphitheater Parking Lot Pavement Preservation Drawings.pdf PDF
Attachment 3 - NFSR 307-310 Road and Parking Lot Reconstruction SOW.pdf PDF
Attachment 4 - NFSR 307-310 Road and Parking Lot Reconstruction Plans (signed).pdf PDF
Attachment 5 - NFSR 307-310 Road and Parking Lot Reconstruction Specifications.pdf PDF
Attachment 6 - NFSR 307-310 Road and Parking Lot Reconstruction SOI.pdf PDF
Attachment 1 - Task Order Proposal Request Forms (TOPR).doc DOC document
Attachment 12 - Echo Amphitheater Parking Lot Pavement Preservation Fire Plan.docx DOCX document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

SOUTHWESTERN REGION

CARSON NATIONAL FOREST,

CANJILON RANGER DISTRICT

ECHO AMPHITHEATER PAVEMENT PRESERVATION

U.S. Department of Agriculture (USDA)

Contents

PROJECT SCOPE1
PROJECT LOCATION1
PERIOD OF PERFORMANCE2
TECHNICAL REQUIREMENTS2
FP Standard Specifications2
Forest Service Supplemental Specifications2
Special Project Specifications3
GOVERNMENT FURNISHED3
SUBMITTALS/DELIVERABLES3
ATTACHMENTS3
APPENDIX A4

Project Name

ECHO AMPHITHEATER PAVEMENT PRESERVATION

Project Scope

This construction project includes Base and Optional items for preservation of approximately 7100 square yards of existing pavement including maintenance activities; paved surface cleaning, asphalt pavement crack and joint sealing and filling, asphalt pavement patching, asphalt slurry seal, permanent pavement markings and permanent traffic control signing at the Echo Amphitheater Recreation Site Parking Lot and Site Entrance with intersection of US Highway 84. See Appendix A for existing conditions pictures.

The Campsites and Day Use areas at this site provide public access to camping, trails, and picnic areas at the Echo Amphitheater on the Canjilon Ranger District of the Carson National Forest.

All equipment shall be clean prior to entering Forest Service land to ensure cleanliness of seeds and other debris for weed control, subject to inspection. No fuel storage on site is permitted. Fuel trucks must be equipped with spill containment kits and portable berms that meet all state and federal regulations. A spill containment plan must be submitted and approved prior to construction.

All work shall be completed with minimal damage to resources. Entire area shall be restored to natural looking conditions upon completion of construction work. Contractor will provide all materials and labor necessary to protect streams or drainages during construction activities. Any flagged or otherwise identified sites of archeological significance shall be avoided.

All required permitting and locates shall be the responsibility of the contractor, including New Mexico Department of Transportation (NMDOT) permit for work performed within the right-of-way of US HWY-84.

The site may be closed during construction operation. Scheduling campground closures will be coordinated with the CO and COR given a three week notice. All sites undergoing pavement preservation will be open weekends (Friday at 5 p.m. to Monday at 7 a.m.) and all Federal holidays. Staging of equipment may occur within the paved area of the site. Any additional staging location needs may be discussed at the pre-construction meeting.

Contractor shall perform all measures necessary to protect existing features, i.e., curb, sidewalks, valley gutter, wheel stops etc. from spattering and marring during slurry seal application or asphalt placement. Corrective measures shall be performed in the event of spattering or marring.

Water needed for construction operations shall be obtained commercially at the contractor’s expense.

The Contractor shall furnish labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract.

Project Location

This project is located in Northern New Mexico in the Carson National Forest within the Canjilon Ranger District. See Attachment D for map.

The project site entrance coordinates are: 36.3587, -106.5215

Figure 1. Echo Amphitheater Site Overview

Period of Performance

The period of performance for this project is 45 calendar days upon issuance of Notice to Proceed.

The Contractor shall minimize maintenance activity during rainy periods or periods not suitable for outlined work and the CO may pause operations.

Technical Requirements

The requirements contained in the following specifications are hereby made a part of this solicitation and any resultant contract. No changes to the specifications, terms, or conditions of this statement of work shall be made without the prior written approval of the Contracting Officer.

FP Standard Specifications The Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-24) U.S. Customary Units), are included by reference, applicable to this project, and are hereby made a part of this solicitation and any resultant contract. The specifications document entitled “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-24 U.S. Customary Units), is available from: https://highways.dot.gov/federal-lands/specs/fp-24

The following Standard Specifications (FP-24) and those referenced contain the technical requirements of this project:

DIVISION 100 - GENERAL REQUIREMENTS (ALL)

DIVISION 150 - PROJECT REQUIREMENTS (ALL)

DIVISION 400 - ASPHALT PAVEMENTS AND SURFACE TREATMENTS (AS APPLICABLE)

DIVISION 600 - INCIDENTAL CONSTRUCTION (AS APPLICABLE)

DIVISION 700 - MATERIAL (AS APPLICABLE)

Forest Service Supplemental Specifications Forest Service Supplemental Specifications (FSSS) are made part of this solicitation and any resultant contract. FSSS modifies the FP-24. They may add to, delete from, or modify the FP-24 standard specifications.

The following Forest Service Supplemental Specifications (FSSS), contained in Attachment A, amend Standard Specifications contained in FP-24:

101 - Terms¸ Format¸ and Definitions 102 - Bid¸ Award¸ and Execution of Contract 103 - Scope of Work 104 - Control of Work 105 - Control of Material 106 - Acceptance of Work 107 - Legal Relations and Responsibility to the Public 108 - Prosecution and Progress 109 - Measurement and Payment 152 - Construction Survey and Staking 153 - Contractor Quality Control 155 - Schedules for Construction Contracts 156 - Public Traffic 157 - Soil Erosion and Sediment Control 633 - Permanent Traffic Control

Special Project Specifications

Special Project Specifications (SPS) are made part of this solicitation and any resultant contract. SPS are specifications that are unique to this project. No SPS as part of this contract.

Government Furnished

No government furnished items as part of this project.

Submittals/Deliverables

Contractor shall submit the following items for review or as deliverable(s). This list is not all inclusive. Submittals requiring Forest Service approval shall be submitted according to the timelines specified to allow adequate review time. Submittals must be submitted via email to the CO and COR.

Item No.
Description
Timeline
1
Work Execution Schedule
30 days following Contract Award.
2
Safety Plan
30 days following Contract Award.
3
Hazardous Spill Plan
30 days following Contract Award.
4
Public Traffic Control Plan
30 days prior to the Notice to Proceed.
5
Material Invoices
As procured.

Attachments

Attachment A - Schedule of Items Attachment B - Forest Service Supplemental Specifications (FSSS) Attachment C - Forest Fire Plan and Guidelines Attachment D - Echo Amphitheater Plans

Appendix A

Echo Amphitheater Site Pictures: Existing Conditions Figures 2 – 11

Figure 2. Site Entrance into Parking Lot

Figure 3. Site Entrance up to intersection with US-HWY 84

Figure 4. Site Entrance Transition to Parking Lot

Figure 5. Beginning of Parking Lot Loop

Figure 6. Parking Lot Loop

Figure 7. Accessible Parking Lot Section

Figure 8. Top of Parking Lot and Portion of Crosswalk

Figure 9. Main Parking Lot Area

Figure 10. Intersection with US-HWY 84 and Site Entrance

Figure 11. Site Entrance Overview image1.png image2.png image3.jpeg image4.jpeg image5.jpeg image6.jpeg image7.jpeg image8.jpeg image9.jpeg image10.jpeg image11.jpeg image12.jpeg