This document is a Permit Tracking Sheet for the Eastern Federal Lands Highway Division (EFLHD) project AR FW BLD 11(1), dated September 30, 2025. The document outlines the current status of various environmental and regulatory permits required for the project, with Jatinder Bains as the Project Manager and Trenton Craig/Teri Acree as the main permit contacts.
The only permit currently approved is the No Highway Occupancy Permit from White County Roads Department, received on April 21, 2025, with a specific requirement to notify Edward Covington prior to construction. Other critical permits, including Corps of Engineers Section 404 Permit, National Pollutant Discharge Elimination System Permit, State 401 Water Quality Certification, Erosion and Sediment Control Permit, and Stormwater Permit, are currently marked as "To Be Determined" (TBD). The document emphasizes that any modifications to the project beyond the original contract plans will require permit modifications, and all permit conditions must be strictly followed.
View the file
Other files for this federal contract opportunity
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1 EFL-FM-PMB-02(03)
Date: Sep 30, 2025 Eastern Federal Lands Highway Division (EFLHD) - PERMIT TRACKING Project: AR FW BLD 11(1)
Project Manager: Jatinder Bains EFLHD Main Permit Contact(s): Trenton Craig/Teri Acree
The following permits have been obtained for this project. Any modification to the work beyond what is shown in the contract plans and specifications may require modification to the permits. While notes regarding permit conditions are provided below to emphasize certain restrictions and requirements, all of the conditions for all of the permits must be fully adhered to as stated in the permit or approval document.
Permit/Approval Agency Received Date Expiration Date Remarks/Notes
No Highway Occupancy Permit required-approved per Edward Covington
White County Roads Department, AR
Apr 21, 2025 N/A
Prior to construction notify Edward Covington, Road Supervisor enabling him to notify public ofroad work. Phone: 501.278.0465, Email: roadsupervisor9@yahoo.com
Corps of Engineers, Section 404 Permit TBD
National Pollutant Discharge Elimination System Permit, TBD
State 401 Water Quality Certification TBD
Erosion and Sediment Control Permit
TBD
Stormwater Permit TBD