Amendment 0004 - South IDIQ RFP 693C73-25-R-000082.pdf
PDF 144 KB Posted
- Solicitation number
- 693C73-25-R-000082
About this file
This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for a Federal Highway Administration project at Bald Knob National Wildlife Refuge. Amendment No. 0004 addresses Request for Proposal No. 693C73-25-R-000082 for the South Region Construction Multiple Award Task Order Contract (MATOC). The amendment provides responses to potential offerors' technical questions, including clarifications about wood chip disposal from fiber rolls, the absence of a geotechnical report, potential reuse of excavated materials, and CAD file availability. The proposal due date remains unchanged: Tuesday, November 4, 2025, at 2:00 pm EST. Key technical clarifications include that wood chips from fiber rolls can be spread on shoulders if they meet FP-24 requirements, existing pavement materials may be reused for embankment construction per specific guidelines, and CAD files will be provided only after task order award.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
693C7325R000082 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ASHBURN VA 20147
ATTN: Acquisitions
693C73
SUITE E2-3-300
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
See Block 1410/28/20250004
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
10/01/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
South Region Construction MATOC:
The purpose of this Amendment is to provide a summary of responses to questions/clarifications asked by interested offerors.
The proposal due date of Tuesday, November 4, 2025, at 2:00 pm EST remains unchanged.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Amendment No. 0004
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
AR FW BLD 11(1)
Bald Knob National Wildlife Refuge
Request for Proposal No: 693C73-25-R-000082
The purpose of this Amendment is to provide a summary of responses to questions/clarifications asked by interested offerors.
The proposal due date of Tuesday, November 4, 2025, at 2:00 pm EST remains unchanged.
Questions / Clarifications
The following questions and issues were submitted via email. The Government response or clarification is provided.
1. This project includes approximately 28,000 LF of fiber rolls, which is a significant quantity. After the completion of the project, when all erosion control measures are removed, can the wood chips inside the fiber rolls be left on site? If so, what are the acceptable methods for doing so? For example, would it be permissible to dig a shallow trench along the alignment and bury the material on site? Please advise.
Response: Wood chip inside the fiber roll is allowed to spread on the shoulders after completion of the construction work as long as material meets the FP-24 requirements.
If the material is not bio-degradable than it is contractors’ responsibility to remove from the project site. Burying the material is not allowed on this project.
2. Is there a geotechnical report available for this project?
Response: There is no geotechnical report developed for this project.
3. Also, can the roadway excavation (CUYD) material be reused in the embankment? I believe having the geotechnical report would help us determine whether the existing aggregate pavement material can be used as fill to prepare the embankment, if suitable.
Response: Geotechnical Report was not developed for this project. Please refer to
Section 204 of the FP-24 and Special Contract Requirements (SCR’s), suitable excavated material can be used for embankment construction according to Subsections
204.09, 204.10, and 204.15.
4. I am reaching out to see if we could get the CAD files for the solicitation referenced above?
Response: CAD Files will be provided to the awardee after the task order has been awarded.
File details come from the government source that posted it. Updated .