This is a Statement of Work (SOW) for Project 24Z5AU6 at the Federal Correctional Institution (FCI) Three Rivers in Texas, approved by the Federal Bureau of Prisons Facilities Management on February 17, 2026.

The contractor shall replace two existing backup generators, transformers, and associated electrical infrastructure at FCI Three Rivers. The facility will remain operational throughout the project, requiring the contractor to submit a phasing plan that minimizes electrical outages and provides temporary power supply for any outages exceeding 24 hours. All equipment, labor, materials, and related services are contractor-provided, except for water, restroom access, and minimal 120V electricity for small hand tools. The contractor must notify the Contracting Officer Representative (COR) five days prior to final system testing, provide a manufacturer's field representative inspection report before start-up, and deliver operation/maintenance manuals and training for a minimum of two Bureau of Prisons employees upon completion. Equipment submittals describing recommended items must be provided within 15 days of Notice to Proceed, with FBOP allowing 10 working days for review. Work hours are 7:00 AM to 3:00 PM, Monday through Friday, excluding weekends and federal holidays. The contractor must plan for two staff escorts daily, maintain daily tool inventory, store materials in designated secure lockable containers, and submit security clearance documentation for all employees and subcontractors within 14 working days of Notice to Proceed. All construction materials and equipment deliveries are restricted to 8:00 AM to 2:00 PM, Monday through Friday, with the contractor responsible for loading, unloading, and ensuring no driveway obstruction. Additional requirements include mandatory personal protective equipment, prohibition of cell phones and cameras, compliance with federal smoking restrictions, daily employee checklist verification, and adherence to institution Lock-out/Tag-out procedures for electrical systems.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of Justice Federal Bureau of Prisons

Facilities Management

Washington, DC 20534

February 17, 2026

MEMORANDUM FOR SEAN O’BRIEN, CONSTRUCTION REPRESENTATIVE

PROJECT RESOURCES SECTION

FROM: Kimberly Hudson, Chief

Construction and Environmental Review Section

SUBJECT: Statement of Work Approval

Project 24Z5AU6, Replace Generators, Transformers, and Electrical Infrastructure, FCI Three Rivers

The Construction and Environmental Review Section, Facilities Management, has reviewed the Statement of Work (SOW), construction drawings and project specifications to be used for solicitation services for the subject project.

The SOW, drawings and specifications are approved. Please proceed with contract solicitation.

If you have any questions, please contact Jason McNeill, Mechanical Engineer, at email jpmcneill@bop.gov or call at (202) 598-7179.

cc: Regional Facilities Administrator SCR mailto:jpmcneill@bop.gov

STATEMENT OF WORK

FCI Three Rivers - B&F PROJECT

Replace Generators 1 & 2, Infrastructure, Transformer

I. SPECIFICATIONS:

A. INTRODUCTION

The Federal Bureau of Prisons (FBOP), Federal Correctional Institution (FCI) Three Rivers, located at Highway 72 West, Three Rivers, Texas 78071, intends to award a single contract to a qualified contractor. The contractor shall provide all equipment, labor, materials, and related services required to replace the facility’s two existing back-up generators, transformers and electrical infrastructure.

Bids for this project shall be complete and provide a fully operational installation in accordance with the requirements herein.

B. SCOPE OF WORK

The intent of this project is to replace existing two back-up generators and associated electrical infrastructure as noted in attached construction drawings and specifications.

FCI Three Rivers will remain operational during the entire project. The contractor shall submit a phasing plan for approval that minimizes electrical outages to the greatest extent possible, while providing the labor and resources necessary to accomplish work that requires those outages in the shortest timeframe possible. For all outages exceeding 24 hours, the contractor shall provide temporary means to supply affected facilities with electrical power during the construction process.

C. REFERENCE DOCUMENTS

Attached reference drawings/specifications are provided for work requirements and the Contractor’s benefit. Actual equipment installation and existing conditions may vary.

ATTACHMENT A – Construction Drawing Documents ATTACHMENT B – Project Manual

C. QUALITY ASSURANCE/INSTALLATION REQUIREMENTS

C.1 Quality Assurance:

As noted in attached specifications.

4.2 WARRANTY

As noted in attached specifications.

D. UTILITIES

The FBOP will provide water, use of restrooms and minimal electricity service (120V) for small hand power tools including battery chargers. The contractor will provide all other equipment, supplies and materials needed to complete this project.

bop42322 Approved

E. TESTING AND ACCEPTANCE

The Contractor shall notify the COR five (5) days prior to the final system tests of and certification of each phase so that arrangements can be made to have BOP staff available to observe testing. Testing requirements as noted in attached specifications.

Provide the services of the manufacturer's field representative to inspect system after installation and submit report prior to start-up, verifying installation is in accordance with specifications and manufacturer's recommendations.

F. HOUSEKEEPING AND MATERIAL DISPOSAL

The contractor awarded the contract shall ensure the premises are always kept clean and free from accumulations of waste materials and rubbish. The contractor will remove all debris, scrap, and rubbish from the work area daily. Surplus materials and all equipment shall be promptly removed from the site upon completion of the work. The Contractor shall be responsible to remove all debris and waste materials from the job site at FCI Three Rivers upon conclusion and acceptance of each project phase. These items must be disposed of in accordance with all Federal, State, and local laws.

G. SUBMITTALS & TRAINING

Submittals:

1. The contractor shall provide written submittals to the COR describing recommended equipment within (15) days from receiving the Notice to proceed for approval. FBOP will have a 10 working day review period for acceptance or denial of proposed equipment. A working day is defined as Monday – Friday excluding weekends and holidays. All submittals shall be in compliance with the attached specifications, which includes all action/product data, information, and closeout documentation.

2. All security clearance paperwork/documentation shall be submitted to the COR a minimum of (14) working days prior to the start of work (see below).

3. The Contractor shall prepare and provide to the COR for approval, PDF file specifications as required by the contract specifications. Submittals will be prepared as PDF package and transmit to Government by sending via email.

Contractor should also provide three (3) copies of the Safety Data Sheets (SDS) on all materials and substances that may be used during the course of the project. In the event the material is not approved by the Safety Manager, it shall be the responsibility of the Contractor to locate and procure an alternative product. The Contractor shall create and maintain a comprehensive submittal register using form ENG 4288-R or similar, to track status and disposition of all submittals, anticipated and already provided, to the FBOP. All submittals shall be transmitted to the COR in electronic PDF format, except sample installations and panels, using transmittal form ENG 4025-R or similar.

4. Submittals containing deviations from contract requirements shall be clearly marked, require CO approval, and may be considered where advantageous to the FBOP in the form of improved quality, time, or cost.

5. FBOP approval of a submittal shall not relieve the Contractor of responsibility for meeting contract requirements or for any error that may exist, as the Contractor is solely responsible for ensuring information contained within each submittal accurately conforms to the requirements of the contract documents.

6. For security and safety purposes, 7-day advance notice in writing, prior to disruption to the system must be given to the Contracting Officer and COR and in accordance with requirements of attached specifications.

7. The contractor shall provide an Installation Certification of the completed and tested systems that contains all requirements as noted in the attached specifications and drawings.

8. Any deviations from this Statement of Work, attached specifications and drawings will be considered a Change Order Request and must be authorized through the institution’s Contracting Officer prior to the implementation of the requested change.

9. It is the Contractor’s responsibility to repair and/or replace any Government property damaged by contractors/subcontractors employees. Damage will be corrected and restored to previous condition at no cost to the Government.

10. It shall be the Contractor’s responsibility for obtaining all measurements and data requirements to comply with any related manufacturer’s installation recommendations not here specified. All installations must be in accordance with product manufacture’s recommendations and attached specifications/drawings.

Training:

Upon completion of the installation, testing, and acceptance by the Government, the contractor shall provide operation/maintenance manuals for each piece of equipment/system installed.

As noted in the attached specifications, the contractor shall furnish training and provide system certification. The referenced training shall be for a minimum of two (2) Bureau of Prisons employees and shall provide detailed instruction on how to maintain and repair all newly installed equipment and systems.

II. CONTRACTOR SECURITY/WORKING REGULATIONS

A. Work Hours:

Work Hours for the contractor are 7:00 AM – 3:00 PM, Monday - Friday, excluding weekends and federal holidays. Any work required to be completed at any other time than noted above must be requested in writing to the COR five (5) working days prior to the start of the work. In the event of any equipment being replaced that would result in downtime of the normal orderly running of the institution, alternate work hours may be authorized in accordance with the time frame stated above.

Access to the site will be available during normal working hours except during emergencies. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional facility, as working hours may not constitute a full eight-hour workday. The Government assumes no responsibility to the Contractor nor to any of his subcontractors for shorter hours due to institutional emergencies or entry and/or exit of workers necessitated by normal institution routines.

Contractors should plan for a minimal amount of time accrued for security considerations, i.e., check-in screening, delay due to inmate movements, institution lock-down, institution emergencies, etc. In the event of an institution emergency, the Contractor will be instructed to secure all work, secure, and stow all tools, equipment and materials, and the Contractor will be escorted out of the institution. Work will resume once the institution emergency passes.

A2. Escorts:

Contractor shall plan work for two staff escorts daily. This will allow the contractor to work at two different locations daily.

B. Delivery of Materials:

All construction materials/equipment required for work on this project is required to be processed by the Contractor and coordinated with the institution COR for temporary storage.

Any construction related deliveries which are directly shipped to the contractor can be received between the hours of 8:00 a.m. to 2:00 p.m., Monday through Friday, excluding Federal Holidays. At no point will a Bureau of Prisons (BOP) staff member receive or sign for a delivery if the contractor or his representative is not present to verify and accept the delivery.

Under no circumstances will FCI Three Rivers or its staff be responsible for the acceptance of any Contractor or company deliveries. The contractor shall be responsible for providing their own means of loading and unloading contractor material or equipment.

The contractor shall not use the institution entry/driveway for the loading, unloading, or storage of any materials and equipment. The contractor will not impede/block the driveway at any time during or after the work shift.

C. Storage of Materials and Equipment:

All construction materials/tools shall be stored in a designated area mutually agreed upon between the COR and the contractor. The storage area will be a secure lockable gang box or similar, size to be determined by the contractor and the COR. If required, the contractor shall provide a securable, single point access storage container, such as a Job or Gang Box that will be left in the agreed upon storage area for the duration of the project. Size of the storage container will be determined by the contractor and the COR. The container will be secured using a padlock protocol with two locks to secure it. One shall be a contractor lock and the other lock provided by the institution. If necessary, a heavy-duty chain provided by the contractor may be used to facilitate the locking requirement. All materials and equipment stored within the container will be maintained in a safe an orderly fashion.

All tools will be inventoried prior to entering the institution and will be inventoried back in to ensure accurate accountability when exiting the institution at the end of each workday. The contractor shall account for approximately 1 hour per day for entering and exiting the institution each day.

Materials cannot be stored at a height that would create a fall hazard. All tools will be inventoried prior to entering the Institution. At the start of each workday all tools will be inventoried out on a daily tool inventory sheet and at the end of the workday all tools will be inventoried back in to ensure accurate accountability of all tools at the end of each workday.

All contractor owned extension cords that will be used during the project, regardless of length, shall be in good condition with no broken outer Insulation. Extension cords are considered a “high risk” tool having a Federal Bureau of Prisons’ tool classification of Double A. All contractor owned extension cords used for this project will be required to exit the institution at the end of every workday for the duration of the project.

All contractor owned ladders approved for use within the institution, regardless of the size, shall be stored in a pre-determined area and secured to a stationary fixture with a heavy link chain and lock which would prevent removal.

D. Security Clearance/Contractor Badges:

The contractor shall provide the COR with all the necessary security clearance documents for all contractors and subcontractor employees accessing the institution within 14 days of receiving the Notice to Proceed, as stated above.

Security clearance documents will only be accepted from the prime contractor. If submitted by a sub-contractor, they will be rejected. It is the prime contractor’s responsibility to review security clearance submissions to ensure they are complete.

In the event a contractor or subcontractor employee cannot pass the security clearance process, it will be the contractor’s responsibility to provide another candidate. By law the BOP cannot, and will not, release any information to the contractor concerning the nature of why a contractors or subcontractor employee was not able to pass the security clearance process.

All contractors/subcontractors working at FCI Three Rivers will be issued and required to wear a picture ID/contractor badge provided by the institution. For security reasons, the badge will be worn in a visible manner as directed by the

COR.

All contractors and subcontractor employees will provide a check list of all employees on site each day to the COR, verifying the number of workers on site each day and that all workers are approved to be on site.

E. Safety and Personal Protective Equipment:

All contractors and employees shall have and wear the required personal protective equipment (PPE) always prescribed by industry standards while on the job site. It is the responsibility of the contractor to provide all PPE equipment. All ladders regardless of the size shall be stored and secured to a stationary fixture with a chain and lock in a predetermined area, in a way that they cannot be removed. If ladders are required, immediately consult with the COR to ensure that he or she can make timely notification to appropriate institution staff. All extension cords regardless of length shall be in good condition with no broken outer insulation and will be secured in a locked construction gang box. Should a system require Lock-out/Tag-out, the system will be required to have both Contractor and FPC Bryan locks on the isolation point to prevent shock. All Lock-out/Tag-out procedures will follow the institution Lock-out program.

F. Additional Considerations:

1. Contractors will NOT be allowed to bring cell phones, cameras or two-way pagers into FCI Three Rivers. The Facilities Department maintains a digital camera that will be utilized by BOP staff to document the project work. The Contractor may request copies of these documentation photos for record keeping.

2. Contractor will be permitted to wear jeans in the institution, however, shorts, green or khaki-color clothing will not be allowed. The clothes will be proper and suitable for the services that are being provided.

3. Lunches will be consumed at the work site. Contractor shall ensure they have everything they need for their lunch when they check-in first thing in the morning.

4. Federal smoking policy on Federal property states that smoking is only allowed in outdoor designated areas. This policy will be strictly enforced.