Attachment 1 - Solicitation No. 15BNAS27Q00000002.pdf

PDF 254 KB Posted

Attached to
FCI Three Rivers-Replace Generators, Transformers, and Electrical Infrastructure
Solicitation number
15BNAS27Q00000002
Issued by

About this file

Solicitation Summary

Document Type: This is a sealed bid Invitation for Bid (IFB) for construction services issued by the Federal Bureau of Prisons (BOP), National Acquisitions Section.

Scope of Work and Requirements: The contractor shall provide all materials, labor, supervision, engineering coordination, demolition, construction, installation, testing, commissioning, training, documentation, warranties, and closeout necessary to replace Generators 1 and 2, associated infrastructure, and a transformer at FCI Three Rivers in Three Rivers, Texas. The work must be performed in accordance with contract drawings, specifications, Statement of Work, and attachments. The contract price includes all costs for labor, supervision, materials, equipment, bonds, insurance, permits, overhead, profit, travel, freight, testing, commissioning, security-processing costs, and closeout. All required closeout documentation, as-built drawings, operation and maintenance manuals, training, testing certifications, and warranties are included in the firm fixed price.

Key Dates and Performance Period: Sealed offers are due by 11:00 AM Eastern Time on November 30, 2026. The contractor must begin performance within 10 calendar days of award and complete all work within 450 calendar days after receiving award or notice to proceed. Offers must provide at least 90 calendar days for Government acceptance after the offer due date.

Bonding and Insurance Requirements: A bid bond in the amount of 20 percent of the bid price or $3,000,000, whichever is less, is required with the bid. Within 10 days of award, the contractor must furnish performance and payment bonds, each with a penal sum equal to 100 percent of the original contract price. Required insurance includes workers compensation and employer's liability ($100,000), comprehensive general liability ($500,000 per occurrence for bodily injury), and comprehensive automobile liability ($200,000 per person, $500,000 per occurrence for bodily injury, $20,000 per occurrence for property damage).

Contract Type and Set-Aside: This is a firm fixed price contract awarded under the Small Business Administration (SBA) 8(a) program as a direct award between the contracting activity and the 8(a) contractor. The magnitude of the project is estimated between $10,000,000 and $20,000,000.

Labor Standards and Compliance: The contract is subject to prevailing wage requirements, construction wage rate requirements, and federal labor standards including the Davis-Bacon Act. The contractor must comply with statutory labor standards, payroll submission requirements, subcontractor responsibilities, and institution work schedules. A pre-construction conference will be held with the contractor, subcontractors, facility management, and other interested personnel to discuss labor standards, prevailing wage requirements, institutional policies, contraband policies, parking, and equipment storage.

Special Requirements: The contractor must obtain security clearances for all employees working on the contract through the BOP using specified forms (Criminal History Check, CJIS Name Check Request Form, BOP Contractor Pre-Employment Questionnaire, and Authority for Release of Information). A 140-day allowance has been included in the performance period for security clearance processing. Progress meetings will be held monthly at the project site. Payment will be made via progress payments based on work accomplished, with a 10 percent retainage allowable if satisfactory progress has not been made. All invoices must include AIA Form G-702 or equivalent documentation.

Buy American Requirements: Domestic construction materials must be used except where the Contracting Officer determines the cost of domestic material is unreasonable (exceeding foreign material by more than 20 percent) or domestic materials are unavailable. The contractor must submit requests with detailed cost breakdowns and market surveys for any foreign construction material requests.

Contractor Contact and Award Administration: Offers should be submitted to the Federal Bureau of Prisons, National Acquisitions Section, 320 First Street NW, Suite 5005, Washington, DC 20534, with inquiries directed to Heather Buck at hbuck@bop.gov. Contract administration will be performed by FCI Three Rivers at HWY 72 WEST, Three Rivers, TX 78071, with payment coordination through Corey Villarreal at cvillarreal@bop.gov.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

15BNAS27Q00000002 Page 1 of 44

SOLICITATION,OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NUMBER

15BNAS27Q00000002

SEALED BID (IFB)

INVITATION FOR BID

NEGOTIATED (RFP)

REQUEST FOR PROPOSAL

2. TYPE OF SOLICITATION 3. DATE ISSUED

10/15/2026

PAGE OF PAGES

1 44

IMPORTANT -The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

26Z5AU4

CODE 15BNAS

Federal Bureau of Prisons National Acquisitions Section 320 First Street NW Suite 5005 Washington, DC 20534

7. ISSUED BY

Federal Bureau of Prisons National Acquisitions Section 320 First Street NW Suite 5005 Washington, DC 20534

Heather Buck hbuck@bop.gov

8. ADDRESS OFFER TO

9. FOR

INFORMATION CALL:

a. NAME

Heather Buck hbuck@bop.gov

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

The contractor receiving award shall provide all materials, labor, and equipment for replace Generators 1 and 2, Associated Infrastructure, and Transformer, FCI Three Rivers, in accordance with the attached Statement of Work and Specifications.

PLEASE COMPLETE THE FOLLOWING ITEMS:

UNIQUE ENTITY IDENTIFIER:_____________________________

TAX IDENTIFICATION NUMBER: ____________________________

CAGE CODE:________________________________

CONTRACTOR EMAIL:_______________________________

System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in

SAM.

11. The Contractor shall begin performance within calendar days and complete it within calendar days after receiving10 450 award, X notice to proceed. This performance period is X mandatory negotiable. (See __________________________.)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12b).

X YES NO

12b. CALENDAR DAYS

Sealed offers in original and copies to perform the work required are due at the place specified in item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

11:00US/

Eastern a.

11/30/2026

b. An offer guarantee X is, is not required.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.c.

90d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d)

15BNAS27Q00000002 Page 2 of 44

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

CODE FACILITY CODE

The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ___________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

17.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified) 27

ITEM

10 U.S.C. 3204(a) ( ) X 41 U.S.C. 3304(a) ( 5 )

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE

UNITED STATES CODE AT

26. ADMINISTERED BY 15B516

Federal Bureau of Prisons FCI Three Rivers

HWY 72 WEST

Three Rivers, TX 78071

Federal Bureau of Prisons FCI Three Rivers

HWY 72 WEST

Three Rivers, TX 78071

Corey Villarreal cvillarreal@bop.gov

27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return __________ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

X 29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a.NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

Heather Buck

31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA

BY

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

15BNAS27Q00000002 Page 3 of 44

Table of Contents

Section Description Page Number

1 Solicitation, Offer and Award 2 Commodity or Services Schedule 3 Special Contract Requirements 4 Contract Clauses

52.246-12 Inspection of Construction (Aug 1996) 52.211-13 Time Extensions (Sept 2000) 52.236-15 (DEV) Schedules for Construction Contracts (Apr 1984) (DEVIATION AUG 2025) 52.242-14 Suspension of Work (Apr 1984) 52.204-14 (DEV) Service Contract Reporting Requirements (Oct 2016) (DEVIATION NOV 2025) 52.209-6 (DEV) Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded (Jan 2025)

(DEVIATION NOV 2025)

52.222-1 (DEV) Notice to the Government of Labor Disputes (Feb 1997) (DEVIATION DEC 2025) 52.222-4 (DEV) Contract Work Hours and Safety Standards--Overtime Compensation (May

2018) (DEVIATION DEC 2025)

52.222-6 (DEV) Construction Wage Rate Requirements (Aug 2018) (DEVIATION AUG 2025) 52.222-7 (DEV) Withholding of Funds (May 2014) (DEVIATION DEC 2025) 52.222-8 (DEV) Payrolls and Basic Records (Jul 2021) (DEVIATION DEC 2025) 52.222-9 (DEV) Apprentices and Trainees (July 2005) (DEVIATION DEC 2025) 52.222-10 (DEV) Compliance with Copeland Act Requirements (Feb 1988) (DEVIATION DEC 2025) 52.222-11 (DEV) Subcontracts (Labor Standards) (May 2014) (DEVIATION DEC 2025) 52.222-12 Contract Termination - Debarment (May 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014) 52.222-14 (DEV) Disputes Concerning Labor Standards (Feb 1988) (DEVIATION DEC 2025) 52.222-15 Certification of Eligibility (May 2014) 52.222-19 (DEV) Child Labor-Cooperation with Authorities and Remedies (Jan 2025)

(DEVIATION MAR 2026)

52.222-54 (DEV) Employment Eligibility Verification (Jan 2025) (DEVIATION DEC 2025) 52.222-55 (DEV) Minimum Wages for Contractor Workers Under Executive Order 14026 (Jan

2022) (DEVIATION DEC 2025)

52.222-62 (DEV) Paid Sick Leave Under Executive Order 13706 (Jan 2022) (DEVIATION

DEC 2025)

52.223-2 (DEV) Reporting of Biobased Products Under Service and Construction Contracts (May 2024) (DEVIATION DEC 2025) 52.225-10 Notice of Buy American Requirement-Construction Materials (May 2014) 52.225-12 Notice of Buy American Requirement--Construction Materials Under Trade Agreements (May 2014) 52.227-1 Authorization and Consent (Jun 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Jun 2020) 52.227-4 Patent Indemnity-Construction Contracts (Dec 2007) 52.228-2 Additional Bond Security (Oct 1997) 52.228-5 Insurance-Work on a Government Installation (Jan 1997) 52.228-11 Individual Surety-Pledge of Assets (Feb 2021) 52.228-12 Prospective Subcontractor Requests for Bonds (Dec 2022) 52.228-14 Irrevocable Letter of Credit (Nov 2014) 52.228-15 Performance and Payment Bonds-Construction (Jun 2020) 52.229-12 (DEV) Tax on Certain Foreign Procurements (Feb 2021) (DEVIATION AUG 2025)

15BNAS27Q00000002 Page 4 of 44

52.232-5 Payments under Fixed-Price Construction Contracts (May 2014) 52.232-23 Assignment of Claims (May 2014) 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer-System for Award Management (Oct 2018) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.233-1 (DEV) Disputes (May 2014) (DEVIATION NOV 2025) 52.236-2 (DEV) Differing Site Conditions (Apr 1984) (DEVIATION AUG 2025) 52.236-3 (DEV) Site Investigation and Conditions Affecting the Work (Apr 1984) (DEVIATION

AUG 2025)

52.236-5 (DEV) Material and Workmanship (Apr 1984) (DEVIATION AUG 2025) 52.236-6 (DEV) Superintendence by the Contractor (Apr 1984) (DEVIATION AUG 2025) 52.236-7 (DEV) Permits and Responsibilities (Nov 1991) (DEVIATION AUG 2025) 52.236-8 (DEV) Other Contracts (Apr 1984) (DEVIATION AUG 2025) 52.236-9 (DEV) Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984) (DEVIATION AUG 2025) 52.236-10 (DEV) Operations and Storage Areas (Apr 1984) (DEVIATION AUG 2025) 52.236-11 (DEV) Use and Possession Prior to Completion (Apr 1984) (DEVIATION AUG 2025) 52.236-12 (DEV) Cleaning Up (Apr 1984) (DEVIATION AUG 2025) 52.236-13 (DEV) Accident Prevention (Nov 1991) (DEVIATION AUG 2025) 52.236-14 (DEV) Availability and Use of Utility Services (Apr 1984) (DEVIATION AUG 2025) 52.236-17 (DEV) Layout of Work (Apr 1984) (DEVIATION AUG 2025) 52.236-21 (DEV) Specifications and Drawings for Construction (Feb 1997) (DEVIATION AUG 2025) 52.240-92 Alt II (DEV) Security Requirements - Alternate II (DEVIATION NOV 2025) 52.242-5 Payments to Small Business Subcontractors (Jan 2017) 52.242-13 Bankruptcy (July 1995)

52.242-71 EVALUATION OF CONTRACTOR PERFORMANCE UTILIZING CPARS (APR

2011) 52.243-4 (DEV) Changes (June 2007) (DEVIATION JUL 2025) 52.246-21 Warranty of Construction (Mar 1994) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (Apr 2012) 52.249-10 Default (Fixed-Price Construction) (Apr 1984) 52.253-1 (DEV) Computer Generated Forms (Jan 1991) (DEVIATION NOV 2025) 52.215-21 Alt IV (DEV) Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data-Modifications (Nov 2021) - Alternate IV (DEVIATION DEC 2025) 52.219-17 Section 8(a) Award (Oct 2019) 52.219-70XX Section 8(a) Direct Award (Aug 1998) 52.225-9 (DEV) Buy American-Construction Materials (Oct 2022) (DEVIATION DEC 2025) 52.225-11 (DEV) Buy American-Construction Materials under Trade Agreements (Nov 2023)

(DEVIATION DEC 2025)

52.248-3 Value Engineering-Construction (Oct 2025) 52.252-6 Authorized Deviations in Clauses (Nov 2020)

5 Attachments 6 Solicitation Provisions

52.212-1 (DEV) Instructions to Offerors-Commercial Products and Commercial Services (Sep

2023) (DEVIATION NOV 2025)

52.214-34 Submission of Offers in the English Language (Apr 1991) 52.214-35 Submission of Offers in U.S. Currency (Apr 1991) 52.222-5 (DEV) Construction Wage Rate Requirements - Secondary Site of the Work (May

2014) (DEVIATION DEC 2025)

52.228-17 Individual Surety-Pledge of Assets (Bid Guarantee) (Feb 2021) 52.233-2 (DEV) Service of Protest (Sep 2006) (DEVIATION NOV 2025) 52.216-1 (DEV) Type of Contract (Apr 1984) (DEVIATION DEC 2025) 52.228-1 Bid Guarantee (Sept 1996) 52.252-5 Authorized Deviations in Provisions (Nov 2020)

15BNAS27Q00000002 Page 5 of 44

52.212-2 (DEV) Evaluation-Commercial Products and Commercial Services (Nov 2021)

(DEVIATION NOV 2025)

7 Representations and Certifications 52.203-11 Certification And Disclosure Regarding Payments to Influence Certain Federal Transactions (Sept 2024) 52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements--Representation (Jan 2017) 52.240-90 (DEV) Security Prohibitions and Exclusions Representations and Certifications

(DEVIATION NOV 2025)

52.209-13 (DEV) Violation of Arms Control Treaties or Agreements--Certification (Nov 2021)

(DEVIATION NOV 2025)

52.229-11 (DEV) Tax on Certain Foreign Procurements--Notice and Representation (Jun

2020) (DEVIATION AUG 2025)

15BNAS27Q00000002 Page 6 of 44

Section 2 - Commodity or Services Schedule

Replace Generators 1 & 2, Associated Infrastructure, & Transformer, FCI Three Rivers. The contractor shall provide the applicable line item numbers, extended prices & any discounts offered to government.

Firm Fixed Price

SCHEDULE OF SUPPLIES/SERVICES

CONTINUATION SHEET

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 Selected contractor shall provide all materials, labor, and equipment to replace Generators 1 & 2, associated infrastructure, and transformer at FCI Three Rivers in accordance with the contract drawings, specifications, Statement of Work, & attachments.

Provide all labor, supervision, engineering coordination, demolition, construction, installation, testing, commissioning, training, documentation, warranties, and closeout necessary to replace Generators 1 and 2, associated infrastructure, and transformer at FCI Three Rivers in accordance with the contract drawings, specifications, Statement of Work, and attachments.

Performance and payment bonds- Not Separately Priced (NSP)— included in CLIN 0001

All required closeout documentation, as-built drawings, operation and maintenance manuals, training, testing certifications, and warranties-Not Separately Priced (NSP)—included in CLIN 0001

The contract price includes all costs necessary to perform the complete construction requirement, including labor, supervision, materials, equipment, bonds, insurance, permits, overhead, profit, travel, freight, testing, commissioning, security-processing costs, and closeout.

PSC: Z2NZ

1 JB $________ $_________________

NOTE: The successful contractor shall be responsible for all applicable federal, state, and local taxes. No tax exemption certification will be issued. The total bid price shall be written in block 17 of the Standard Form 1442.

SPECIAL CONTRACT REQUIREMENTS

Clause Text

BONDS

(a) Bid Guarantee. Each bidder shall submit with his bid a Bid Bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the Government, or other security as provided in provision 52.228-1, in the form of twenty percent (20) of the bid price or not to exceed $3,000,000. The bid bond penalty may be expressed in terms of a percentage of the bid price or may be expressed in dollars and cents. A bid bond is not required for bids of $150,000 or less. (FAR 28.102-1)

(b) Performance and Payment Bonds. Within 10 days after award the contractor shall execute and submit to the Contracting Officer two bonds, each with good and sufficient surety or sureties acceptable to the Government, as follows; a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25A). The penal sums of such bonds will be as follows: (Not required for contracts of $150,000 or less)

15BNAS27Q00000002 Page 7 of 44

(1) Performance Bond: The penal sum of performance bonds at the time of contract award shall be 100 percent of the original contract price.

(2) Payment Bond: The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

(c) For construction contracts greater than $35,000 but not greater than $150,000, the Contracting Officer shall select two or more of the following payment protections, giving particular consideration to inclusion of an irrevocable letter of credit as one of the selected alternatives (FAR 28.102-1(b)(1)):

(1) A Payment Bond;

(2) An irrevocable letter of credit (ILC);

(3) A tripartite escrow agreement;

(4) A Certificate of Deposit; or

(5) A deposit of the types of security listed in 28.204-1 and 28.204-2.

(d) Individual Sureties.

(1) Bidders may elect to furnish individual surety bonds. If individual surety bonds are furnished for bid guarantees, payment or performance bonds, the individual sureties must submit their bonds proof of ownership and value of the assets which they claim in their net worth at time of bid opening. The Government's preferred method of proof is to have a statement of net worth prepared by a Certified Public Accountant (CPA) in accordance with Generally Accepted Accounting Principles (GAAP). Statements from a CPA that contain disclaimers are not acceptable. The statement of net worth on the Standard Form 28, Affidavit of Individual Surety, is insufficient and will not be accepted without additional proof of value and ownership.

(2) Bidders are cautioned that individual sureties must provide complete and detailed information in Block 9 of Standard Form 28 concerning other contracts on which they have provided bonds. This information shall include contract number, contract location, amount, and type of bond and telephone number of the involved contracting office. Failure to provide the proof and information required may result in rejection of the bid or termination of the contract for failure to provide adequate bonds.

MAGNITUDE

The magnitude of this project is between $10,000,000 to $20,000,000.

REQUIRED INSURANCE

See FAR 52.228-5, Insurance - Work on a Government Installation.

The Contractor shall, at its own expense, provide and maintain during the entire performance period of this contract, at least the kinds and minimum amounts of insurance required in the Schedule or elsewhere in the contract.

TYPE AMOUNT

(1) WORKERS COMPENSATION & EMPLOYER'S LIABILITY $100,000

15BNAS27Q00000002 Page 8 of 44

The required Workmen's Compensation Insurance shall extend to cover employee's liability for accidental bodily injury or death and for occupational disease with a minimum liability of $100,000.

(2) COMPREHENSIVE GENERAL LIABILITY with a minimum limit of:

PER ACCIDENT OR

OCCURRENCE FOR BODILY INJURY $500,000

This insurance shall include contractor's protective and contractual liability

(3) COMPREHENSIVE AUTOMOBILE LIABILITY with the following minimum limits:

PER PERSON $200,000

PER OCCURRENCE FOR BODILY INJURY $500,000

PER OCCURRENCE FOR PROPERTY DAMAGE $ 20,000

PRE-CONSTRUCTION CONFERENCE

(a) Prior to the start of construction, Contracting Officers shall call a conference with the contractor, subcontractor(s), Warden, Controller/Business Administrator, Safety Manager, Facilities Administrator, Project Representative, A&E firm, Captain and other interested personnel to discuss the statutory labor standards, prevailing wage requirements, submission of the contractor's payrolls, subcontractor's responsibil ities, institution work schedules, local policies, contraband, parking, storage of vehicles and equipment, etc.

Minutes of the conference shall be recorded, listing the names and titles of all attendees, and the subject matter of all items covered. The minutes shall be signed by the contractor and the Contracting Officer, and a signed copy placed in the contract file.

(b) The Contractor shall familiarize himself/herself with all procedures involved in normal institution routines. Any requirements which may constitute a problem or result in conflict, will be brought to the attention of the Contracting Officer or his representat ive for determination.

SUBMITTALS

Within 10 calendar days after commencement of work or as otherwise established by the Contracting Officer, all materials and articles requiring approval, as contemplated by the Materials and Workmanship clause, shall be submitted by the contractor.

The submittal process is in place to allow the Government the opportunity to determine whether materials or procedures used by the contractor are in accordance with contract requirements. It is ultimately the Contractor's responsibility via the quality control process to ensure submittal items installed under the contract and work performed on site are in accordance with industry standards and general practices.

(a) The types of submittal requirements specified in this contract may include, but is not limited to; shop drawings, product data, samples, certificates of conformance or compliance, certified test or inspection reports, equipment, materials, and miscel laneous work related submittals for construction. Individual submittal requirements are generally specified in applicable sections for each unit of work in the specifications and/or as a whole in one section in the statement of work.

(b) The Bureau of Prisons (BOP) Contracting Officer’s Representative (COR) shall act for the Contracting Officer in the review and acceptance of all submittals. The

15BNAS27Q00000002 Page 9 of 44

Contractor shall submit submittals as required by the contract/specifications to the COR for transmittal to the Contracting Officer. Fabrication of any work or purchase or use of any submittals (such as materials for which samples are required or equipment, etc.) shall not take place until written acceptance is given by the COR, except at the Contractor's own risk.

(c) The Contractor shall submit all shop drawings and submittals sufficiently in advance (unless otherwise specified in the specifications) of the construction requirements to allow ample time for checking, re-submitting, and re-checking.

(d) Failure of any materials to pass their specified tests shall be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. The Government reserves the right to disapprove any material or equipment which has previously proven unsatisfactory in service.

(e) The Contracting Officer’s or designee’s approval or acceptance of submittals is not to be construed as a complete check. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor is responsible for the satisfactory construction of all work. The Contractor is responsible for delivering a final product/system that is operational as intended by the contract requirements, regardless of any Government approvals or acceptance of submittals.

The Government assumes no liability during the submittal approval/acceptance process. It is the sole responsibility of the Contractor to deliver a properly functioning product or system.

CONTRACTOR USE OF PERMISES

Work Hours The project schedule is based on a normal forty (40) hour work week, eight (8) hours per day, Monday through Friday, excluding Federal holidays. The Contracting Officer’s Representative (COR) shall establish the work hour time frames for the duration of the project, subject to the approval of the Contracting Officer. Work hours and work days may be altered only with a 48 hour advance approval of the Contracting Officer.

NOTE: Access to the site will be available during normal working hours except during emergencies. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional facility, as working hours may not constitute a full eight hour day. The Government assumes no responsibility to the Contractor, nor to any of his subcontract ors, for shorter hours due to institutional emergencies or entry and/or exit of workers necessitated by normal institution routines. The procedures and institutional entrance/ exit routines applicable to this project will be explained at both the pre-bid conference/ site visit and the pre-construction meeting.

Contraband The Contractor shall inform his employees that intoxicating beverages, drugs, weapons, etc., will not be allowed on the site. Introduction of contraband shall be subject to the penalties prescribed by Title 18 USC-1791.

Explosives The use of explosives is absolutely forbidden without written authorization from the Contracting Officer.

Parking and Temporary Office

15BNAS27Q00000002 Page 10 of 44

Parking will be available at the site to the extent it does not interfere with construction activities. Otherwise, parking shall be provided for by the Contractor, at his expense, off the site for workmen employed on the project. Any temporary field office used by the Contractor shall be located in an area approved by the COR.

Safety and Accident Prevention In performing work under this contract the contractor shall:

(a) Conform to the specific safety requirements established by this contract;

(b) Comply with the safety rules of the Government institution that concern related activities not directly addressed in this contract;

(c) Take all reasonable steps and precautions to prevent accidents and preserve the life and health of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and

(d) Take such additional immediate precautions as the Contracting Officer and/or COR may reasonably require for safety and accident prevention purposes.

PAYMENT SERVICES

(a) Original application for payment shall be prepared on AIA (American Institute of Architects) Form G-702 "Application and Certificate for Payment" and submitted to the Contracting Officer. The contractor may use another form; however, it shall contain similar information as the AIA Form G-702. The Contracting Officer’s Representat ive (COR) will approve the amount of payment by signing. The approved application for payment shall be forwarded as follows: Original to Accounting; Copy for Contract Award File.

(b) All small business contractors are required to self-certify on all invoices their small business status.

(c) The following information is required with each application for payment:

• Name and address of contractor

• Contract number

• Contractor invoice/application for payment number

• Description, price, and quantity of construction completed/rendered

• Payment terms (reference the contract payment clause)

• Other substantiating documentation or information required by the contract

• Name, title, and phone number of official to be notified in the event of a defective invoice

• Contractor TIN (Tax ID Number)

REQUEST FOR FINAL INSPECTION

The Contractor shall give the Contracting Officer’s Representative (COR) a minimum of ten (10) working days advanced written notice of the date on which the work will be fully completed and ready for the Government’s final inspection.

CONSTRUCTION CONTRACT SECURITY

In addition to the information contained in clause “DOJ-03 Personnel Security Requirements For Contractor Employees (Nov 2021); (Alt. I) -- Classified Information

15BNAS27Q00000002 Page 11 of 44

Cleared Contractors”, the following additional security is required to be completed and submitted for all contract employees who will be working under the terms of the contract:

Criminal History Check – BP-A0660 (May 2018) CJIS Name Check Request Form BOP Contractor Pre-employment Questionnaire BOP Authority for Release of Information The contactor should be aware that the time required for contractor security clearances to be completed may vary. For the purposes of this solicitation, __140_ calendar days [contracting officer to insert the number of days based on performance period memo] have been included in the performance period specified in FAR clause 52.211-10. The number of days listed above is contingent upon the contractor providing completed clearance packages for their employees within 10 calendar days of the Notice to Proceed. For any subsequently awarded subcontract, completed security clearance packages for subcontractor workers shall be submitted in conjunction with the completed SF-1413.

**A form package will be issued by the Administrative Contracting Officer or Contracting Officer's Representative (COR) at the institution upon contract award. Completed packages shall be submitted by the PRIME CONTRACTOR ONLY to obtain clearance for each prime and sub-contract employee. Security Clearance packages will NOT be accepted from sub-contractors. Upon clearance being obtained the contractor will be notified. Should a contract employee NOT be cleared to enter the facility for this project, the contractor will be notified immediately. The contractor will be responsible to submit another contract employee as soon as possible for clearance. Be advised, the Federal Bureau of Prisons cannot disclose why an individual does not pass the security clearance process, as it is a violation of law.**

ASSIGNMENT OF CONTRACT ADMINSTRATION OFFICE AND FUNCTIONS

Pursuant to FAR 42.201 and 42.202, the assigned Contract Administration Office is listed in Block 26 of the Standard Form 1442 Back. This assignment carries with it the authority to perform all of the contract administration functions listed in FAR 42.302(a) and 42.302(b) to the extent that those functions apply to the contract.

The Contract Administration Office is required, however, to obtain written authorization from the Procuring Contracting Officer (PCO) to perform any function listed under 42.302(b). Specifically, the Administrative Contracting Officer (ACO) is required to obtain written authorization to perform the below referenced functions FOR

CONSTRUCTION CONTRACT AWARDS:

(1) Negotiate or negotiate and execute supplemental agreements incorporating contractor proposals resulting from change orders issued under the Changes clause.

Before completing negotiations, coordinate any delivery schedule change with the contracting office.

(2) Negotiate prices and execute priced exhibits for unpriced orders issued by the contracting officer under basic ordering agreements.

(3) Negotiate or negotiate and execute supplemental agreements changing contract delivery schedules.

15BNAS27Q00000002 Page 12 of 44

(4) Complete Contractor Performance Assessment Report System (CPARS) evaluations of contractor performance in accordance with FAR Subpart 42.15.

Should any other function under FAR Subpart 42.15 not listed above be required, the ACO is required to contact the PCO for authority.

SCHEDULE OF VALUES

The Contractor shall prepare a Schedule of Values (SOV) for the project and submit to the Contracting Officer for approval prior to submitting the first application for payment.

The SOV shall be correlated with the construction schedule. The SOV shall be formatted per the Construction Specification Institute Master Format structure. The Contractor may propose an alternate organizational format to the Contracting Officer for approval.

(a) The SOV shall include:

(1) Project name, location, and contract number;

(2) Contractor’s name and address;

(3) Date of submittal.

(b) The SOV shall be arranged in a tabular form with separate columns to indicate the following for each item listed:

(1) Description of Work or Material;

(2) Related specification section, if applicable;

(3) Name of subcontractor, if applicable;

(4) Name of manufacturer or fabricator, if applicable;

(5) Name of supplier, if applicable;

(6) Change orders (modifications) that have affected value, if applicable;

(7) Dollar value;

(8) Percentage of Contract sum rounded to the nearest percent, adjusted to total 100 percent.

(c) The SOV shall breakdown the contract sum in sufficient detail to facilitate continued evaluation of applications for payment and progress reports. The contractor should separate principal subcontract amounts down into several line items.

(d) SOV amounts shall be rounded to the nearest whole dollar. The total of all SOV amounts shall equal the total contract amount.

(e) The contractor shall progress the percentage of completion, with the concurrence of the Contracting Officer’s Representative, for each value in conjunction with the preparation of each monthly application for payment. The progressed value percentages shall directly correlate to the calculated total amount due for each monthly progress payment.

(f) The SOV shall remain fixed for the duration of contract performance. Any revisions to the SOV must be requested in writing, with justification, for approval by the Contracting Officer.

PROGRESS MEETINGS

The Administrative Contracting Officer (ACO) shall conduct progress meetings at the project site on a monthly basis, or at intervals as determined by the ACO.

(a) At a minimum, the attendees shall include but is not limited to:

15BNAS27Q00000002 Page 13 of 44

(1) FBOP: Administrative Contracting Officer, Contracting Officer’s Representat ive (COR), Facility Administrator/Manager, Architect/Engineer (if applicable), Other Personnel (Executive Staff, Captain, Safety Manager, etc.).

(2) Contractor: Project Manager, Superintendent, and technical support disciplines as appropriate (Subcontractors, Manufacturers, Suppliers, etc.).

(b) The meeting should include, but is not limited to issues such as:

Administrative Contracting Officer:

(1) Old business from previous progress meeting(s);

(2) Status of modifications, certified payrolls, submittals, requests for information

(RFI);

(3) Review of payments made to date and review/approve current payment request;

(4) Status of modification proposal requests;

(5) Discuss new business.

COR:

(1) Status of escort coverage;

(2) Review gate or sallyport entrance/exit issues;

(3) Discuss other delays contractor may be experiencing;

(4) Discuss performance/quality issues.

Contractor:

(1) Review/discuss updated progress schedule;

(2) Provide 30 day outlook;

(3) Discuss other issues affecting performance.

CONTRACT CLOSEOUT PROCEDURES (FOR CONSTRUCTION CONTRACTS

EXCEEDING THE SAT)

Contract Closeout must be completed within six (6) months of physical completion of the work.

Prior to payment of final invoice:

The contractor shall submit the following documents:

(1) Contractor’s Affidavit of Release of Liens (AIA Document G706A);

(2) Contractor’s Affidavit of Payment of Debts and Claims (AIA Document G706);

(3) All as-built drawings/shop drawings, if applicable;

(4) Contractor’s final invoice;

(5) Release of Claims (GSA Form 1142);

(6) Consent of Surety to Final Payment (AIA Document G707);

(7) Letter establishing warranty dates;

(8) Complete list of subcontractors with telephone numbers and points of contact;

(9) Guarantees and warranties;

(10) All balance and test reports;

(11) All operation/maintenance manuals;

(12) All permits and certifications.

AIA forms can be obtained from The American Institute of Architects at www.aiabook store.com.

GSA forms can be obtained from the General Services Administration at www.gsa.gov (click on the “Forms Library” link).

15BNAS27Q00000002 Page 14 of 44

CHANGES

(a) Changes will be in accordance with the Changes clause 52.243-4 or Changes and Changed Conditions clause 52.243-5 whichever applies to this contract.

(b) When changes are made in the work that requires an equitable adjustment to the contract, the Contractor shall submit to the Contracting Officer, through the Contracting Officer’s Representative (COR), a written proposal for adjustment of the amount of increase or decrease. With the proposal, the Contractor shall submit an itemized breakdown in at least the following detail:

(1) Material quantities and unit cost

(2) Labor costs by material item

(3) Construction equipment cost

(4) Workmen's compensation and public liability insurance

(5) Overhead

(6) Profit or commission

(7) Employment taxes (FICA and FUTA)

(c) The maximum allowable overhead, profit and commission percentages are contained below. The percentages for overhead, profit and commission shall be negotiated and may vary according to the nature, extent and complexity of the work involved, but in no case shall exceed the following:

(1) To the Contractor, on work performed by other than his own forces. The commission is 10% in the first $20,000, 7 1/2% on the next $30,000, 5% on the balance over $50,000.

(2) To the Contractor, and/or the Subcontractors for that portion of the work performed with their respective forces. The commission is 10% overhead and 10% profit on the first $20,000, 7 1/2% overhead and 7 1/2% profit on the next $30,000, and 5% overhead and 5% profit on the balance over $50,000.

Not more than three (3) percentages, not to exceed the maximum percentage amounts shown above, will be allowed regardless of the number of Subcontractors (i.e., the mark up on work subcontracted by the Subcontractor will be limited to the overhead percentage and one profit percentage in addition to the prime Contractor's commission percentage). On proposals covering both increases and decreases in the amount of the contract, overhead, profit and commission will be allowed on the net increase only.

(d) When certified cost or pricing data are required under FAR 15.403-4 for proposals over $2,000,000, the cost or pricing data shall be submitted in accordance with FAR 15.408, Table 15-2. No itemized breakdown will be required for proposals amounting to less than $1,000.

(e) When the necessity to proceed with a change does not allow sufficient time to negotiate a modification or because of failure to reach an agreement, the Contracting Officer may issue a change order instructing the contractor to proceed on the basis of a tentative price based on the best estimate available at the time, with the firm price to be determined later. Furthermore, when the change order is issued, the contractor shall submit a proposal for cost of changes in work within 30 calendar days.

(f) The Contracting Officer will consider issuing a settlement by determination to the contract, if the contractor's proposal required by paragraphs (a) and (b) of this clause is not received within 30 calendar days, or if agreement has not been reached.

15BNAS27Q00000002 Page 15 of 44

(g) Where a change involves credit items only, a proper measure of the amount of downward adjustment in the contract price is the reasonable cost to the contractor if he/she had performed the deleted work. A reasonable allowance for overhead and profit are properly includable as part of the downward adjustment for a deductive change. The amount of such allowance is subject to negotiation.

(h) Overhead and contractor's fee percentages shall be considered to include insurance other than mentioned herein, field and office supervisors and assistants, security police, use of small tools, incidental job burdens, and general home office expenses and no separate allowance will be made therefor. Assistants to office supervisors include all clerical, stenographic and general office help. Incidental job burdens include, but are not necessarily limited to, office equipment and supplies, temporary toilets, telephone and conformance to OSHA requirements. Items such as, but not necessarily limited to, review and coordination, estimating and expediting relative to contract changes are associated with field and office supervision and are considered to be included in the contractor's overhead and/or fee percentage.

(i) The Contractor shall submit with his proposal a request for time extension, if applicable.

(j) The COR shall review the proposal and check estimates in detail, utilizing unit prices where specified or agreed upon. If they are in agreement, the COR shall forward the proposal to the Contracting Officer. The Contracting Officer will forward copies to the Architect-Engineer (if applicable) and the Regional Project Manager for their review and recommendations. After their review, the Architect-Engineer and Project Manager will forward their comments to the Contracting Officer.

(k) If the Contracting Officer determines that an equitable adjustment is to be made, the contract shall be modified in writing utilizing the prescribed Standard Form 30 (Amendment of Solicitation/Modification of Contract)(SF-30). After the SF-30 has been signed by the Contractor and executed by the Contracting Officer, distribution shall be made as follows:

(1) Original: Contract file

(2) Copy to: Contractor Regional Project Manager Contracting Officer’s Representative (COR) Architect-Engineer Firm (if applicable) Accounting Supervisor Contracting Officer

EQUITABLE ADJUSTMENTS: WAIVER AND RELEASE OF CLAIMS

(a) When the Contractor, after receipt of notification of a change made pursuant to the clause of this contract entitled "Changes" or after affirmation of constructive change thereunder, submits any claim for equitable adjustment under this clause, such claim shall include all types of adjustments in the total amounts to which that clause entitles the Contractor, including but not limited to adjustments arising out of delays or disruptions or both caused by such change. Except as the parties may otherwise expressly agree, the Contractor shall be deemed to have waived (i) any adjustments to which it otherwise might be entitled under the aforesaid clause where such claim

15BNAS27Q00000002 Page 16 of 44 fails to request such adjustment, and (ii) any increase in the amount of equitable adjustments additional to those requested in its claim.

(b) Further, the Contractor agrees that, if required by the Contracting Officer, it will execute a release, in form and substance satisfactory to the Contracting Officer, as part of the supplemental agreement setting forth the aforesaid adjustment, and that such release shall discharge the Government, its officers, agents, and employees, from any further claims, including but not limited, to further claims arising out of delays or disruptions or both caused by the aforesaid change.

PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS

a. Payment of price. The Government shall pay the Contractor the contract price as provided in this contract.

a. Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.

1. The Contractor’s request for progress payments shall include the following substantiation:

1.

i. An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.

ii. A listing of the amount included for work performed by each subcontract or under the contract.

iii. A listing of the total amount of each subcontract under the contract.

iv. A listing of the amounts previously paid to each such subcontractor under the contract.

v. Additional supporting data in a form and detail required by the

Contracting Officer.

1. In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration.

Material delivered to the Contractor at locations other than the site also may be taken into consideration if-

i. Consideration is specifically authorized by this contract; and

ii. The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.

a. Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)

I hereby certify, to the best of my knowledge and belief, that-

1. The amounts requested are only for performance in accordance with the specif ications, terms, and conditions of the contract;

15BNAS27Q00000002 Page 17 of 44

2. All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

3. This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

4. This certification is not to be construed as final acceptance of a subcontractor’s performance.

__________________________________________________ (Name) __________________________________________________ (Title) __________________________________________________ (Date)

(d) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall-

1. Notify the Contracting Officer of such performance deficiency; and

2. Be obligated to pay the Government an amount (computed by the Contracting

Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until-

i. The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or

ii. The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.

(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.

(f) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as-

15BNAS27Q00000002 Page 18 of 44

1. Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work;

or

2. Waiving the right of the Government to require the fulfillment of all of the terms of the contract.

(g) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (e) of this clause shall not apply to that portion of progress payments attributable to bond premiums.

(h) Final payment. The Government shall pay the amount due the Contractor under this contract after-

1. Completion and acceptance of all work;

2. Presentation of a properly executed voucher; and

3. Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor’s claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of1940 ( 31 U.S.C.3727 and 41 U.S.C. 6305).

(i) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.

(j) Interest computation on unearned amounts. In accordance with 31 U.S.C. 3903(c) (1), the amount payable under paragraph (d)(2) of this clause shall be-

1. Computed at the rate of average bond equivalent rates of 91-day Treasury bills auctioned at the most recent auction of such bills prior to the date the Contractor receives the unearned amount; and

2. Deducted from the next available payment to the Contractor.

15BNAS27Q00000002 Page 19 of 44

Section 3 - Special Contract Requirements

This Section Is Intentionally Left Blank

15BNAS27Q00000002 Page 20 of 44

Section 4 - Contract Clauses

Clauses By Reference

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov

Clause Title Fill-ins (if applicable)

52.246-12 Inspection of Construction (Aug 1996)

52.211-13 Time Extensions (Sept 2000)

52.236-15 (DEV) Schedules for Construction Contracts (Apr 1984)

(DEVIATION AUG 2025)

52.242-14 Suspension of Work…