Attachment 13 Three Rivers RFI responses.pdf

PDF 266 KB Posted

Attached to
FCI Three Rivers-Replace Generators, Transformers, and Electrical Infrastructure
Solicitation number
15BNAS27Q00000002
Issued by

About this file

This is an Amendment No. 0001 to Solicitation No. 15BNAS27Q00000002, issued by the Federal Bureau of Prisons National Acquisitions Section. The amendment provides government responses to industry questions concerning the Replace Generators 1 & 2, Infrastructure, Transformer project at FCI Three Rivers, Three Rivers, Texas (Project No. 26Z5AU4). The solicitation uses a Best Value Tradeoff evaluation process and was extended to December 18, 2026, 11:00 AM Eastern for proposal submission.

Key project requirements include: three 1,000 kW generators rated at 480V connected to 1,250 kVA step-up transformers to 12.47kV; 13 medium-voltage transformers with mineral oil insulation; replacement of existing switchgear with new switchgear featuring automatic transfer capabilities using fused medium-voltage transfer switches; unarmored single-conductor medium-voltage cable; and generator feeders with adjustable breaker sizing for 1,900A. The 450-calendar-day performance period includes all contract-required work through final completion, testing, training, commissioning, and closeout requirements, with liquidated damages of $1,853.13 per calendar day for delays beyond completion. Contractors must work 7:00 AM to 3:00 PM Monday through Friday (excluding Federal Holidays), plan for two staff escorts daily allowing work at two locations, and submit security clearance documentation within 14 calendar days of Notice to Proceed. The contract requires NETA testing, power system studies, temporary load-bank testing per NFPA 110, and training for at least two BOP staff covering all operations and maintenance items per manufacturer recommendations. Work involves an occupied correctional institution with security constraints, 140 calendar days allocated for security clearances within the overall performance period, outage windows limited to 4 hours maximum with 7 days' written notice to the Contracting Officer and COR, and restriction of two-way radios within the secure perimeter fence line.

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT NO. 0001

SOLICITATION NO. 15BNAS27Q00000002

Replace Generators 1 & 2, Infrastructure, Transformer

FCI Three Rivers, Three Rivers, Texas

Project No. 26Z5AU4

ISSUED BY

Federal Bureau of Prisons National Acquisitions Section 320 First Street NW, Suite 5005 Washington, DC 20534

Contracting Officer: Heather Buck

SUBJECT

Questions and Answers

PURPOSE

The purpose of this Amendment is to provide Government responses to questions received from industry concerning Solicitation No. 15BNAS27Q00000002.

This Amendment forms part of the solicitation and shall be considered by all Offerors in preparing and submitting proposals.

NOTE TO OFFERORS

Questions are reproduced substantially as submitted by industry. The Government has not edited contractor questions except to remove true duplicate questions and proprietary identifying information. A single Government response may address multiple substantially identical questions.

Unless specifically revised by amendment, all other terms, conditions, specifications, drawings, attachments, and requirements remain unchanged.

SECTION I

SOLICITATION AND PROPOSAL

PREPARATION

Question 1

Project number: SF-1442 Block 6 and the pre-bid minutes header show 26Z5AU4, while the SOW, Attachment 2, and the drawings show 24Z5AU6. Please confirm the correct project number.

Government Response:

The governing project number for this procurement is 26Z5AU4. References to 24Z5AU6 are administrative carryover references. Offerors shall use Solicitation No. 15BNAS27Q00000002 and Project No. 26Z5AU4 for proposal preparation and correspondence

Question 2

Request for controlled plan set (Drawings, Project Manual, Light Calcs, and Basis of Design) so we can finish our electrical takeoff.

Government Response:

All requested documents are available on SAM.gov, previous locked documents have been unlocked.

Question 3

Cost Summary Spreadsheets: Is use of the attached Cost Summary Spreadsheets mandatory, or is a like format acceptable? The sample shows profit only on own-forces work and no prime markup line on subcontracted work. Please confirm how prime markup on subcontract work should be shown.

Government Response:

Use of the Cost Summary Spreadsheet provided with the solicitation is not mandatory. Offerors may submit pricing in a substantially similar format, provided the submission clearly identifies all costs necessary for the Government to evaluate the proposal, including labor, materials, equipment, subcontract costs, overhead, profit, and other direct costs.

If the Offeror elects to use a format other than the sample spreadsheet, the format shall provide sufficient detail to allow the Government to evaluate price reasonableness and completeness.

For subcontracted work, any prime contractor markup shall be shown as a separate and clearly identifiable line item. Offerors should follow the contract's changes and pricing provisions regarding subcontract markups, overhead, profit, and commission when preparing supporting cost information.

Question 4

Limitations on subcontracting: 52.219-14 is referenced only within 52.219-17. Please confirm the applicable clause version and that the 85 percent general-construction limit, excluding the cost of materials, applies.

Government Response:

FAR 52.219-14, Limitations on Subcontracting, applies to this procurement through its incorporation and reference within FAR 52.219-17, Section 8(a) Award. Offerors are responsible for complying with all applicable SBA and FAR subcontracting limitations in effect at the time of proposal submission and award.

For this construction procurement, the limitation on subcontracting is calculated excluding the cost of materials, consistent with applicable SBA regulations and FAR requirements governing construction contracts. Offerors are responsible for ensuring compliance with the applicable percentage limitations throughout contract performance.

The Government will evaluate compliance in accordance with the terms of the solicitation, FAR requirements, and applicable SBA regulations in effect at the time of award.

Question 5

Solicitation number: The cover letter cites RFQ 15BNAS26Q00000094. Please confirm that 15BNAS27Q00000002 is the governing solicitation number for all submissions.

Government Response:

Solicitation No. 15BNAS27Q00000002 is the governing solicitation number for all proposal submissions and related correspondence

Question 6

Minimum wage: The solicitation lists 52.222-55 (DEV), Minimum Wages Under EO 14026, but states no rate, and WD TX20260209 contains no EO 14026 note. Please state what minimum wage, if any, applies. Wage determination coverage: WD TX20260209 (Building) does not include lineman and several other electrical classifications. Please confirm the Building WD covers all work, including exterior duct bank and medium-voltage work, and whether conformances will be required.

Government Response:

The applicable labor standards for this procurement are contained in Wage Determination TX20260209 Revision 1 and the contract clauses incorporated into the solicitation. The wage rates applicable to covered construction classifications are those established by the Davis-Bacon wage determination included with the solicitation.

The wage determination included in the solicitation does not identify a separate minimum wage requirement under Executive Order 14026. Accordingly, contractors shall pay not less than the applicable wage and fringe benefit rates required by Wage Determination TX20260209 for covered classifications and shall comply with all contract clauses incorporated into the solicitation.

If a worker classification is not included in the wage determination, the contractor shall follow the applicable conformance procedures provided under the Davis-Bacon labor standards requirements.

If work required under the contract cannot be properly performed under an existing classification contained within the applicable wage determination, the contractor shall request an additional classification and wage rate in accordance with the Davis-Bacon conformance procedures contained in the contract labor standards provisions.

The Government recognizes that certain specialty electrical classifications associated with medium-voltage distribution work, cable splicing, or similar activities may not be expressly listed in Wage Determination TX20260209. As a result, conformances may be required for specific classifications not included in the wage determination. Determination of whether a conformance is necessary will be made in accordance with applicable Davis-Bacon procedures after award and based on the actual work to be performed.

Question 7

Magnitude and pre-bid minutes: The minutes state a magnitude of $10M to $20M but also note that a magnitude is no longer required per the RFO. Since the minutes state they do not change the solicitation, will an SF-30 amendment formalize the magnitude or any other items discussed at the pre-bid meeting?

Government Response:

The solicitation currently identifies a project magnitude of $10,000,000 to $20,000,000. Any revisions to solicitation requirements will be issued through a formal amendment. Pre-bid meeting minutes do not modify solicitation requirements.

Question 8

Evaluation basis: The Instructions to Offerors use sealed-bid terms (52.214-18, bid opening), and SF-1442 Block 13a references an original and copies, while Attachment 2 describes a best-value evaluation with a technical approach and the notice requires email submission. Which evaluation basis governs, and should the Technical Proposal and Price Proposal be submitted as separate files?

Government Response:

This acquisition will be evaluated using a Best Value Tradeoff process. The Government will evaluate Technical Approach and Project Execution, Relevant Experience and Technical Capability, Project Management, Safety and Security, Past Performance, and Price. Technical and Price proposals shall be submitted as separate items.

Question 9

Liquidated Damages and Performance Period Clause. Project Manual Section 01 29 00, paragraph J.10, requires a "final liquidated damages settlement statement" with the final payment application, and Solicitation p. 11 refers to the performance period specified in FAR 52.211-10. However, neither FAR 52.211-12 (Liquidated Damages—Construction) nor FAR 52.211-10 (Commencement, Prosecution, and Completion of Work) appears in the Section 4 clause list, and no daily rate is stated. Please confirm (a) whether 52.211-10 applies to this contract, and (b) whether liquidated damages apply and, if so, the daily rate and whether it is assessed against Substantial Completion or Final Completion. Please also confirm whether there are any interim milestones or required phase completion dates.

Government Response:

(a) The contract establishes a required performance period of 450 calendar days after Notice to Proceed, as identified in the solicitation. The 450-calendar-day performance period remains applicable to this procurement.

(b) The Government has determined that liquidated damages are appropriate for this project. A liquidated damages memorandum was prepared recommending incorporation of FAR 52.211-12, Liquidated Damages-Construction, at a rate of $1,853.13 per calendar day for delays beyond the required contract completion period.

However, the current solicitation does not include FAR 52.211-12 or identify a liquidated damages rate. The Government intends to issue a formal amendment addressing liquidated damages and any associated clause incorporation.

No interim contract milestones or separate phase-completion dates have been identified in the solicitation. Contractors remain responsible for completing all work within the overall contract performance period and in accordance with the approved phasing plan and project schedule.

Question 10

Proposal format: What format and page limits apply to the technical proposal, and is there a required past-performance reference form?

Government Response:

No page limitations have been identified within the solicitation package. Technical proposals shall address the evaluation factors identified in Attachment 2. Past-performance reference form has been identified within the Instruction to Offerors attachment.

Question 11

Would the Government consider moving the proposal due date to Monday 7 December 2026, given the Thanksgiving holiday falls in the week preceding the current due date?

Extension of time will be granted to December 18, 2026, 11AM eastern

Question 12

Is this project federal, state or contractor tax exempt? If no, which level of taxes are required?

As stated on the Solicitation no tax exemption certification will be issued

Question 13

The Instructions to Offerors address required forms but do not describe the Technical Proposal structure. The SAM notice identifies five technical elements. Absent further direction, the Offeror intends to submit Volume I Technical addressing technical and management approach, construction schedule with milestones, key personnel, quality control and safety approach, and assumptions impacting performance; Volume II Price and Forms/Certifications. Please confirm this structure is acceptable and advise of any page limits.

Government Response:

The proposed volume structure is generally consistent with the evaluation approach identified in Attachment 2. Technical proposals shall address all evaluation factors identified in Attachment 2.

Price proposals should be submitted separately. No page limits have been identified. Past-performance reference form has been identified within the Instruction to Offerors attachment.

Question 14

The solicitation's Clause 52.219-70XX states that joint ventures are allowable on competitive and sole-source 8(a) awards but requires the joint venture agreement to be submitted to SBA before the proposal due date and approved before award. However, 13 CFR §124.513(e)(1) states that SBA will not approve joint ventures in connection with competitive 8(a) awards.

Further, 13 CFR §124.501(g) provides that, for competitive 8(a) awards, SBA determines the eligibility of the 8(a) partner but does not review the joint venture agreement for compliance with §124.513. Please clarify the applicable requirements for a mentor-protégé joint venture submitting an offer under this procurement, including whether advance SBA submission or approval of the joint venture agreement is required. Joint venture past performance: For an 8(a) joint venture offeror, will the Government consider the past performance and experience of the individual joint venture members

Government Response:

For this competitive 8(a) procurement, the requirements of current SBA regulations govern.

Offerors submitting as an SBA-approved mentor-protégé joint venture are not required to obtain SBA approval of the joint venture agreement prior to proposal submission or prior to award.

SBA does not approve joint venture agreements for competitive 8(a) procurements; however, the joint venture must be properly formed, comply with applicable SBA regulations governing mentor-protégé joint ventures and joint venture eligibility, and be eligible for award at the time of proposal submission and award.

The reference in Clause 52.219-70XX requiring SBA submission and approval of a joint venture agreement prior to award is applicable to circumstances where SBA approval is required by regulation and does not supersede current SBA regulations governing competitive 8(a) procurements. Offerors remain responsible for ensuring full compliance with all applicable SBA eligibility, size, mentor-protégé, and joint venture requirements. Any necessary eligibility determinations will be made in accordance with SBA regulations.

SECTION II

SECURITY AND SITE ACCESS

Is the 450 calendar-day performance period measured to Substantial Completion or to Final Completion/acceptance? Does it include closeout items such as O&M manuals, training, as-builts and warranty documentation? We understand the Government's 450-calendar-day performance period accounts for anticipated equipment lead times. However, manufacturer lead times are subject to frequent change, and it is unclear when the lead-time estimates used to establish the performance period were obtained. Based on discussions with manufacturers over the past two weeks, current lead times appear to exceed those estimates and may not support completion within 450 calendar days. Would the Government consider adjusting the performance period at the time of award to reflect verified manufacturer lead times current at that time? In light of the potential discrepancy between current manufacturer lead times and the established 450-calendar-day performance period, please clarify how the Government expects offerors to address equipment procurement and delivery in their proposed construction schedules. Should offerors develop schedules based on currently available manufacturer lead times, even if those schedules extend beyond 450 calendar days, or is the Government expecting all proposed schedules to demonstrate completion within the stated performance period?

Government Response:

The government considers it to final completion to include all closeout items. Submit your proposed construction schedule at the time you estimate the project to be complete. An extension of the 450 period of performance will not be extended prior to award.

Using historical data, approximately how many days should be planned in the 450-day schedule for emergency shutdowns? If it is already figured in the 450-day performance period, could it be shared how many of these days are anticipated? Please provide number of weather days BOP estimated when developing the 450-day schedule. Institutional Delays. Will time lost to lockdowns and institutional emergencies be granted as excusable delay? How should it be documented?

The Government did not establish the 450-calendar-day performance period using a predetermined number of emergency shutdown or institutional lockdown days. The 450-calendar-day performance period represents the Government's estimated overall duration for completion of the project, including anticipated security and operational constraints associated with performing work at an operating correctional institution. Offerors shall develop their proposed schedules based on their own means and methods, sequencing, and assessment of project risks. No specific number of emergency shutdown days is being provided for planning purposes, and no guarantee is made regarding the frequency or duration of institutional emergencies that may occur during contract performance. The Government did not assign a specific number of weather days when establishing the 450-calendar-day performance period. The performance period represents the Government's estimate for completion of the work, considering the overall scope, anticipated procurement durations, security requirements, coordination requirements, and construction activities associated with an occupied correctional institution. Offerors shall develop their proposed schedules based on their own assessment of weather impacts, seasonal conditions, and construction means and methods. No extra time will be given for Institutional Lockdowns/Emergencies, the time fram of 450-calendar days has already taken this into consideration.

Security packages: Are security packages due within 10 days of NTP (solicitation page 11) or 14 working days before start of work (SOW I.G / II.D)? If the work is phased, must all employee names be submitted within 14 days after NTP, or may clearance packages be submitted at least 14 days before each employee’s phase begins?

Government Response:

Security clearance documentation shall be submitted within fourteen (14) calendar days following Notice to Proceed and sufficiently in advance to satisfy the requirement that personnel be processed a minimum of fourteen (14) working days before access is required. Prime contractors shall submit all security packages, including subcontractor personnel.

Will two-way radios for the contractors be allowed inside or outside for the contractors to communicate with one another while working?

Two-way radios will not be allowed within the secure confines of the FCI Perimeter fence line.

Will the Electrical assessment report referenced on Sheet C-301 be distributed?

Yes, the assessment has been added to the solicitation attachments.

Please confirm if contractor can triple hat the project i.e. have 1 person cover the role of superintendent, QA and Safety manager as long as they meet the qualification or will the government require 3 individuals for each qualifying position?

Yes this is acceptable as long as they are qualified to serve in each role.

The Statement of Work lockout/tagout paragraph refers to FPC Bryan locks. Please confirm this should read FCI Three Rivers.

Government Response:

Yes. References to FPC Bryan should be interpreted as applying to FCI Three Rivers. Contractors shall comply with the institution Lockout/Tagout program.

Will the Government provide a bidders list or attendance roster following the 29 October site visit?

Yes, attendance roster will be posted with the Q&A amendment.

The solicitation states that 140 calendar days for contractor security clearances have been included in the performance period specified in FAR 52.211-10, contingent on the contractor submitting completed clearance packages within 10 calendar days of NTP. The SOW states that clearance documents shall be submitted within 14 days of NTP (Section D) and a minimum of 14 working days prior to the start of work (Section G.2). Please clarify:

1. Is the 140 calendar-day clearance allowance correct as stated, and is it included within the 450 calendar-day performance period? If not, what is the correct clearance processing duration?

2. What is the required deadline for submitting completed clearance packages: 10 calendar days after NTP, 14 days after NTP, or 14 working days prior to the start of on-site work?

3. For subcontractors awarded after NTP, does the 14-working-day lead time before their start on site govern their clearance submittals (submitted by the prime with the SF-1413)?

4. May the prime submit clearance packages for prime and subcontractor personnel after award but before NTP to shorten the clearance period?

Government Response:

• Yes. The 140-calendar-day security clearance allowance identified in the solicitation is included within the overall 450-calendar-day contract performance period and was used for solicitation planning purposes. The actual clearance processing duration may vary by individual and workload.

Contractors should not assume that all clearances will require the full 140 days.

• The Government will accept completed security clearance packages submitted within 14 calendar days after Notice to Proceed (NTP). In addition, personnel shall not begin on-site work until their clearance has been processed and approved. Contractors are responsible for ensuring packages are submitted sufficiently in advance of the planned start date to satisfy the requirement for processing before site access. To the extent there is a conflict between references, the Government intends the prime contractor to submit packages as early as possible following NTP and at least 14 working days before personnel require site access.

• Yes. For subcontractors added after NTP, the prime contractor shall submit completed clearance packages, including the applicable SF-1413 documentation, sufficiently in advance of the subcontractor's planned on-site start date. The minimum 14-working-day lead time before site access applies.

• Yes. The Government will accept security clearance packages after award and before NTP, when practicable, to facilitate processing and potentially reduce delays to the construction schedule.

Submission of packages prior to NTP does not constitute approval for site access, and personnel may not enter the institution until clearance has been granted and authorization has been provided by the Government.

SECTION III

SITE LOGISTICS, ESCORTS, AND STORAGE

If there is an emergency shutdown, does the contractor also have to evacuate the unsecured areas?

Government Response:

Yes, but depending on the type of emergency this will be on a case by case basis and determined by the institution Captain.

Submittal Review Period. SOW Section I.G.1 provides a 10 working-day FBOP review period for proposed equipment. Project Manual Section 01 33 00, paragraph D, states only that review will be taken with "reasonable promptness," with no fixed duration. Please confirm the review period for all submittals and resubmittals so it can be shown in the schedule as Section 01 32 00, paragraph 1.05.B.3 requires.

Government Response: Submittals review period shall follow the SOW, “FBOP will have a 10 working day review period for acceptance or denial of proposed equipment.”

Construction Sequence. Is the sequence shown on drawing E-001 binding, or may the contractor propose an alternate sequence in the phasing plan required by the SOW? Phasing Plan. When is the phasing plan due, what is its review period, and is its approval a prerequisite to starting on-site work?

Sequence of operation is intended to provide guidance. Actual sequence of construction shall be coordinated with the site and presented to EOR prior to construction. Refer to spec 260010 Supplemental Requirements for Electrical, for pre-construction submittals. Government to confirm preference.

Equipment Submittals and Fabrication Release. SOW Section I.G.1 requires equipment submittals within 15 days of NTP. Is that product data only, with shop drawings to follow, or a complete package? May the contractor release long-lead equipment (generators, switchgear, transformer) for fabrication once product data is approved, before shop drawings are approved? Industry standard shop drawings estimated at 8-10 weeks. Pre-NTP Submittals. May equipment submittals be made after award but before NTP to start procurement of long-lead equipment earlier?

Government Response:

This refers to product data only. NTP will be issued during Pre-Construction meeting as determined by the Contract Specialist.

Please clarify if a space will be available to use as a laydown yard/job office. And if so, what would the dimensions be and approximately where would it be located within the work area?

Government Response:

A lay down area will be provided. A site map showing the location has been added to the solicitation attachments.

What are the maximum dimensions allowed for a secured job / tool storage box or shed (gang box) inside of the secured area, if allowed?

Government Response:

There is no specific required dimensions. Suggest utilizing a Gang Box that fits through a door opening of 36”.

Will any equipment be able to stay inside of the secured area or will it need to be removed at the end of every workday?

Government Response:

A gang box will be allowed at the work site in side the secured area but will required to have one contractor lock and one FBOP lock and secured to a permanent object (ie. Pillar etc…)

Escorts: SOW Section II.A2 says to plan for two staff escorts daily, allowing work at two locations. Does "location" mean two crews, or two work areas that may each hold several crews? May the contractor request additional escorts during peak periods, and at what cost?

Government Response:

Two escorts mean two locations. Multiple crews will be allowed to work at each location. Request can be requested for additional escorts, but the FBOP is only obligated to supply two escorts.

Will there be an area on-site and outside of the secured facility that could be used to redistribute the trench excavation spoils instead of hauling it off-site? Drawing E-002 states that removed electrical equipment remains Government property, while the demolition requirements address off-site disposal. Please identify which generators, transformers, switchgear, and panels must be retained by the Government and where they are to be delivered or stored.

Government Response:

Inside the secured perimeter, it is necessary to backfill immediately. Excessive spoils shall be extracted outside of the secured perimeter. Outside areas, depending on the amount of material being excavated, it can be laid out behind the powerhouse, but excessive amounts must be removed from site.

SECTION IV

WORK HOURS, PHASING, AND OUTAGES

Work Hours. Three documents set work hours differently. The SOW sets 7:00 AM–3:00 PM Monday through Friday, with 5 working days' written notice to the COR for other hours. The solicitation bases the schedule on 8-hour days Monday through Friday, with hours set by the COR and changes requiring 48 hours' CO approval. Project Manual Section 01 11 00, paragraph 1.03, states the site is open to the Contractor seven days a week, with the Contractor establishing the normal work week, and changes requiring 48 hours' CO approval.

Please confirm (a) the governing work hours and days, (b) whether the schedule should assume 8 productive hours per day, and (c) the governing notice requirement for alternate hours.

A) The work hours are 7:00AM-3:00PM Monday through Friday excluding Federal Holidays.

B) Please reference the SOW:

II. CONTRACTOR SECURITY/WORKING REGULATIONS

A. Work Hours: “Access to the site will be available during normal working hours except during emergencies. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional facility, as working hours may not constitute a full eight-hour workday.”

“Contractors should plan for a minimal amount of time accrued for security considerations, i.e., check-in screening, delay due to inmate movements, institution lock-down, institution emergencies, etc.”

c) Alternative work hours may be required after award and only on a case by case basis.

Potential bidders should not a assume and alternative work schedule will be granted

Please clarify the security measures needed to work in the powerhouse/warehouse area and areas outside of the secured facilities. Will this access also be limited to 7:00 a.m. to 3:00 p.m.

or will longer working hours be acceptable? Will the powerhouse/warehouse area and areas outside the perimeter fence require and escort at all times counting toward our two-count escort allotment?

Government Response:

All areas, including outside the secured perimeter area, require escorts. Staff will be available as stated in the SOW. Inventory of all tools must be kept by staff. In regard to cells phones outside of the secured perimeter, such as the powerhouse and warehouse area, we ask that they are always kept on your person. No cell phones inside the camp itself, to include beyond the camp administrative building and into the housing units. Operation times are as specified in the SOW.

Extended work hours may be requested on a case by case basis through the project COR. Extended work hours is not guaranteed.

Deliveries and Laydown. Deliveries are limited to 8:00 AM–2:00 PM. May oversize equipment deliveries (generators, switchgear, transformer) be scheduled outside those hours? Is laydown available inside the secure perimeter, or must large equipment be staged outside and escorted in?

All delivery times shall be per the SOW.

Performance Period. Is the 450 calendar-day performance period measured to Substantial Completion or to Final Completion/acceptance? Does it include closeout items such as O&M manuals, training, as-builts and warranty documentation?

Government Response:

The 450-calendar-day performance period includes all contract-required work necessary to achieve project completion, including testing, training, commissioning, submittals, and closeout requirements unless otherwise modified by amendment.

Outage Windows and Notice. Outage notice requirements differ: 7 days' written notice to the CO and COR (SOW Section I.G.6), a minimum of 5 days' notice to FBOP for major outages (Project Manual Section 01 00 02), and not less than 2 days' notice for utility interruptions.

Please confirm the governing notice period. Please also identify the allowable days and times for outages, any maximum outage durations or blackout periods (holidays, summer peak, institutional events), and whether outages may occur after hours or on weekends with escorts available.

Government Response:

The outage windows shall adhere to the SOW: 7 days' written notice to the CO and COR (SOW Section I.G.6). There should not be any outage periods that exceed 4 hours. Exceptions would have to be approved by Project COR, Facility Manager and Warden.

What are the maximum outage duration and the allowable outage windows (nights or weekends)? Will escorts be available outside the 7:00 AM to 3:00 PM work hours for outage work?

Government Response:

7-3 are the normal daily operation hours. Any time outside of that, will be authorized on a case by case basis through the project COR with a minimum 5 day prior notice of request.

Temporary power: For outages over 24 hours (SOW I.B), which facilities require temporary power, and are there existing temporary-generator connection points? Temporary Generator Connection. May rental temporary generators connect to the existing temporary-generator connection? Serving Utility. Who is the serving utility? Will the Government coordinate utility work, and are there known utility lead times for metering, cutovers or service changes (including the 30-day metering period)? The drawings require temporary generators to be sized from 30-day peak demand measurements or the building transformer capacity. Please provide any existing demand records available for the affected buildings, or confirm that preconstruction access for the required 30-day metering will be permitted.

Government Response: Government Response: All facilities require temporary power. We do have existing temporary connection points where temporary generators can be connected. Contractor will be responsible to coordinate with utility providers. Our water is provided by the City of Three Rivers and our electricity is provided by Karnes Electric.

Deferred Tests and Post-Completion Activities. Project Manual Section 01 91 13, paragraph I, allows approved deferred tests after Construction-Phase Commissioning Completion. Please confirm whether deferred tests and post-completion activities such as the 90-day TAB re-verification fall outside the 450 calendar-day performance period Government Response:

Government Response

All tests fall within the 450 days.

SECTION V

GENERATORS AND FUEL SYSTEMS

The SOW references replacement of two existing generators, while the drawings and design narrative identify three new generators. Please confirm that the base bid requires three (3) new 1,000 kW generators.

Government Response:

The base bid shall include three (3) new 1,000 kW generators and associated infrastructure in accordance with the drawings and specifications. References to two generators are legacy references.

Drawing ES602 refers to 1,000 kW, 12.47 kV generators, while the Basis of Design and generator specification describe 480 V generators connected through step-up transformers.

Please confirm the required generator output voltage and transformer arrangement.

Government Response: Generators shall be rated for 480V and be connected to transformers to step-up the voltage to 12.47kV.

Given the required runtime capacity, the sub-base tanks will likely be in excess of 36 inches tall. Are platforms required (OSHA requirement at that height) and who's scope would that fall under? Could a drawing be issued showing the desired design?

Government Response:

The design team believes that the platforms should be required. The generator manufacturer can provide these. FBOP to confirm that these should be added to design

Is a factory witness test of the fully assembled generator, tank & sound enclosure required at the packager's facility prior to shipment? If so, what are the test parameters? Is a load bank test required and duration?

Government Response:

Refer to spec 263213.13 Diesel-Engine-Driven Generator Sets for testing requirements and parameters. Generator shall be factory assembled and factory tested and a report of factory tests showing evidence of compliance with specified requirements shall be provided. Load bank testing is required per NFPA 110.

Please confirm the overall sound attenuation level desired for the enclosed package. The silencer section indicates 85 dBA at 25 ft. Should the overall package attenuation be the same?

Government Response:

Basis of design of enclosure’s sound attenuation level is 92dBA confirm acceptance with Government.

Please confirm gallons of usable fuel required. Drawings indicate 72 hours of operation. Full load fuel consumption at 1,000 kW is 70 gallons per hour. Total fuel required at full load and 72 hours operation is 70 gallons per hour x 72 hours = 5,040 gallons. 5,040 gallons x 133% = 6,703 gallons usable fuel. Tank nameplate capacity would be approximately 10% higher at 7,373 gallons.

Government Response: 72-hour UL142 fuel tank for a KD1000 ( Kohler / Rehlko basis of design model ) is 5,120 useable gallons. The tank volume is approximately 6400 gallons.

The two existing 10,000-gallon fuel storage tanks are to be cleaned and reused, but their condition is identified as unknown. Please provide available inspection or integrity-testing reports and confirm how a tank found unsuitable for reuse will be addressed. The drawings require cleaning the existing storage tanks and polishing the existing fuel. Please confirm whether off-site disposal and replacement of existing fuel that fails the required quality testing is included in the base contract or will be handled separately. Drawing M-601 requires new fuel-system alarms and status points to be tied into the existing BAS. Please confirm the intended Government BAS interface, whether existing capacity is available, and whether modifications to Government-owned BAS software or licensing are included in the base scope.

Government Response:

Both tanks were in use at the time of survey, so it is believed that they are in usable condition. Furthermore, FBOP asked that they be reused for value engineering. The base bid should assume inspection / testing of the tanks – verifying they are fit for reuse.

Is closed transition operation with utility a requirement for this project? If so, is the design for a soft load/unload system or a 100 ms short overlap? A soft load approach is preferred to avoid excessive transients on the generators.

Government Response:

Closed transition approach should be discussed and approved with utility provider. Discuss with utility provider if a soft load approach is preferred.

The existing kitchen panels appear recessed, while the Basis of Design calls for surface-mounted NEMA 3R replacements and Drawing E-402 requires the new panels to match the existing openings. Please confirm whether new panels are to remain recessed or be surface-mounted, including any required enclosure or wall modifications. The Basis of Design recommends replacement of the deteriorated switchgear serving the FCI kitchen, but that replacement is not clearly identified on the construction drawings. Please confirm whether this upstream switchgear replacement is included in the base bid.

Per spec 262416 Panelboards, kitchen and wash-down area panelboards shall be NEMA 4X. Design intent is to keep all panels recessed and should fit in existing wall cutouts. Refer to drawings for dimensions of equipment and wall openings and field verify all dimensions and wall openings.

Replacement of FCI kitchen switchgear is a future recommendation only. FBOP shall confirm this approach.

Question 10

For the 600A dual feed interrupter switches, is the design intent to run fiber back to the main switchgear and monitor and/or operate those switches remotely?

Government Response:

Per direction from FBOP during design phase, the interrupter switches are to be manually operated only.

Question 11

The Basis of Design recommends reorganizing critical loads onto dedicated emergency panels.

Please confirm whether this work is part of the contract or is only a future recommendation.

This is only a future recommendation.

Question 12

The Basis of Design anticipates limited sprinkler work, while FP101 calls for relocation of piping as needed and drip pans where relocation is impractical. Please confirm whether sprinkler piping modifications and drip pans are both to be carried in the base bid, or whether one is the intended design approach.

Include in base bid

Question 13

New fire pump controller feeders are designed around an anticipated 75 HP motor, and the drawings indicate a recent controller replacement. Please provide the actual installed motor horsepower, controller rating, and any available equipment data for pricing the required feeder connections.

Fire pump 1000 gpm @ 75 psi, 75 HP, 1800 rpm 60Hz 230/460V, Solid-State

Question 14

The Basis of Design calls for 25% spare breaker space, while Drawing E-402 requires replacement panels to match the existing panel dimensions and wall openings. Please confirm which requirement governs if the specified spare capacity cannot fit within the existing enclosures.

Panels need to fit in existing wall openings to prevent cutting of existing masonry walls.

Question 15

The generator specification lists a load bank, and the switchgear design includes a spare section for temporary load-bank connection. Please clarify whether a permanent load bank is required under this contract or only temporary load-bank equipment for testing. Switchgear and ATS: Are the existing ATSs and switchgear to be replaced or reused? Please confirm the scope boundary at the utility service point and at building distribution

Government Response:

Per electrical design narrative, load bank spare section is intended for a temporary load-bank for NFPA generator testing,. Per electrical design narrative, design intent is to replace existing switchgear with new switchgear with automatic transfer capabilities, this can be achieved via switchgear controls/relays. It is Coffman’s understanding that the utility boundary is the fenced in substation and outside the fenced area is the customer’s responsibility.

Question 16

Sheet E-605 shows neutral grounding resistors on each generator. A low-resistance grounding is typically not used at the 480V level. Please confirm if we are to supply & install high resistance grounds inside the generator enclosure. Please confirm that SEL-351 can be proposed as alternative to SEL-751. This is due to the extremely long lead time on the SEL-751 series. Is there an approved alternative for SEL-587? SEL-587 is not in production any longer.

Government Response:

Concur for neutral impedance device to be high resistance grounding as part of initial bid, but charging current and protection should be coordinated with the generator manufacturer. Impedance device can be a separate device. Coffman’s basis of design is using the SEL-751, the SEL-351 appears to be a possible substitution, but it will likely need extra modules to configure all protection, metering, control, comm, i/o, ground fault functionality, 27/59 voltage function, communications coordination, compatibility with the HRG, and ensuring its equipped with arc flash light detection function; this will require coordination with the switchgear manufacturer. The SEL787 is the direct replacement of the discontinued SEL587 as recommended by Schweitzer.

Question 17

If it is determined after a thorough inspection of the existing fuel tanks that the fuel tanks are not in the ideal condition for reuse what would be the course of action?

FBOP expects the tanks to be reused.

SECTION VI

TRANSFORMERS AND MEDIUM

VOLTAGE DISTRIBUTION

Transformers: CLIN 0001 says transformer (singular) while the title says Transformers. How many transformers are in scope and what are their ratings?

13 transformers as listed on the drawings.

Please confirm the transformer fluid (mineral oil vs. less-flammable FR3) and provide the liquid-containment detail.

Government Response:

Per spec 261219 Pad-mounted, liquid-filled, medium-voltage transformers, insulating liquid shall be mineral oil.

The Basis of Design indicates that Building W's existing transformer is not being replaced, but the construction sequence includes Building W among the transformer cutovers. Please confirm whether Building W requires a new transformer, new medium-voltage switch, and associated secondary feeder work.

Building W transformer to remain but be refed and connected to campus electrical loop system.

Refer to drawings.

The civil narrative indicates a possible existing secondary electrical loop, while the electrical narrative states Loop B was never installed. Please confirm whether any usable Loop B duct bank, conduits, or cables exist and identify what is intended to remain.

Loop B was not installed.

If there are spare conduits available from the existing building transformers to the building main breaker rooms, would it be acceptable to intercept and use that spare conduit for the new secondary feeders? Is there a possibility of getting photographs of where the secondary feeders terminate inside each building? Is there a possibility of getting some photographs of the interior on the manholes near the transformers?

Any existing spare conduit is assumed to be unusable and in poor condition.

SECTION VII

EXISTING CONDITIONS, HAZARDOUS

MATERIALS, AND UTILITIES

Existing conditions: Are as-builts or utility locates of existing underground lines available? Are there known rock, groundwater, or contamination conditions along the duct bank route?

No as-builts/utility locates available. No known rock, groundwater/contaminated conditions.

Please provide any available PCB or hazardous-material testing records for the existing transformers and electrical equipment scheduled for removal.

All transformers are FR3. No PCBs

If contaminated soil is discovered, is the contractor responsible for cleaning and removing of the contaminated soil or will that be on the government?

Government Response:

FBOP does not anticipate encountering contaminated soil. If contractor discovers contaminated soil notify project COR.

Has the Government confirmed the PCB status of the 13 existing transformers to be removed?

All transformers are FR3. No PCBs`

SECTION VIII

TESTING, TRAINING, AND

COMMISSIONING

Testing and studies: Is a third-party (for example, NETA) testing agency required? Are short-circuit, coordination, or arc-flash studies the contractor's responsibility?

Government Response:

NETA testing agency required per division 26 specifications. Refer to spec 260573 Power System Studies for contractor required studies.

Are factory witness tests required for the generators, MV switchgear and transformers? How many Government witnesses, and who pays travel?

Refer to division 26 specifications for testing requirements.

Training is required for at least 2 BOP staff. Please confirm the training hours per system and whether video recording is required.

Government Response:

There is not a training time requirement if all operations and maintenance items are covered as per the manufacture’s recommendations. And conducted by qualified personnel. Video is not required but may be conducted by the FBOP.

1. Generators: are they 480V? ES602 note 1 says 12.47 kV. The ES602 generator tags and spec 263213.13 say 480V.

Government Response: Generators shall be rated for 480V and be connected to transformers to step-up the voltage to 12.47kV.

2. Step-up transformers: 1000 kVA or 1250 kVA? ES602 shows 1000 kVA. The Basis of Design says 1250 kVA.

Government Response: Transformers on one-line should be updated to 1250kVA.

3. MV switches: fused (ES602) or vacuum with automatic transfer and SCADA (spec 261329)? If SCADA, who gives the two 120V power sources and the SCADA master station?

Government Response: Design intent is to use fused medium voltage transfer switches.

4. Switchgear: ES602 and spec 261326 say 65 kA. Spec 261326 also says 104 kA peak close-and-latch. That fits a 40 kA rating, not 65 kA. Which rating should we price?

A rating of 40kA may be used for pricing.

5. MV cable: single conductor (ES602) or 3-conductor armored (spec 260513 2.02 I and J)?

Government Response:

Design intent is unarmored single conductor medium voltage cable. Other cable requirements per spec are still applicable.

6. Generator feeders: ES602 note 9 shows 5 sets of 3#400 kcmil and no ground. That is too small for the 2000A breaker. What is correct?

Cable sizes are correct. Provide adjustable breaker size for 1900A.

7. Loop A: new cable or reuse the existing? ES102 note 1 says new cable. ES602 note 3 says the existing wire stays.

Government Response: Loop A is to remain in place and be extended/spliced with new cable to medium voltage switches.

8. Fuel tank: the Basis of Design says 5,000 gallons for 72 hours. Spec 263213.13 says at least 133% of the fuel needed. Which size do we price?

May use basis of design 5,000 gallon tank for 72 hours. Additionally price the reconditioning of the (2) existing tanks and provide bid alternate for the case where the (2) existing tanks are beyond there serviceable life, need to be demolished, and need to be replaced. 133% fuel requirement will be removed from Spec 263213.13.

AMENDMENT NO. 0001
SOLICITATION NO. 15BNAS27Q00000002
Replace Generators 1 & 2, Infrastructure, Transformer
FCI Three Rivers, Three Rivers, Texas
Project No. 26Z5AU4
ISSUED BY
SUBJECT
PURPOSE
NOTE TO OFFERORS
SECTION I
SOLICITATION AND PROPOSAL PREPARATION
Question 1
Question 2
Question 3
Question 4
Question 5
Question 6
Question 7
Question 8
Question 9
Question 10
Question 11
Question 12
Question 13
Question 14
The solicitation's Clause 52.219-70XX states that joint ventures are allowable on competitive and sole-source 8(a) awards but requires the joint venture agreement to be submitted to SBA before the proposal due date and approved before award. However, ...
For this competitive 8(a) procurement, the requirements of current SBA regulations govern. Offerors submitting as an SBA-approved mentor-protégé joint venture are not required to obtain SBA approval of the joint venture agreement prior to proposal sub...
The reference in Clause 52.219-70XX requiring SBA submission and approval of a joint venture agreement prior to award is applicable to circumstances where SBA approval is required by regulation and does not supersede current SBA regulations governing ...
SECTION II
SECURITY AND SITE ACCESS
Question 1
Is the 450 calendar-day performance period measured to Substantial Completion or to Final Completion/acceptance? Does it include closeout items such as O&M manuals, training, as-builts and warranty documentation? We understand the Government's 450-cal...
Government Response:
The government considers it to final completion to include all closeout items. Submit your proposed construction schedule at the time you estimate the project to be complete. An extension of the 450 period of performance will not be extended prior t...
Question 2
Question 3
Question 4
Question 5
Question 6
Question 7
Question 8
Question 9
SECTION III
SITE LOGISTICS, ESCORTS, AND STORAGE
Question 1
If there is an emergency shutdown, does the contractor also have to evacuate the unsecured areas?
Government Response:
Yes, but depending on the type of emergency this will be on a case by case basis and determined by the institution Captain.
Question 2
Submittal Review Period. SOW Section I.G.1 provides a 10 working-day FBOP review period for proposed equipment. Project Manual Section 01 33 00, paragraph D, states only that review will be taken with "reasonable promptness," with no fixed duration. P...
Government Response: Submittals review period shall follow the SOW, “FBOP will have a 10 working day review period for acceptance or denial of proposed equipment.”
Question 3
Construction Sequence. Is the sequence shown on drawing E-001 binding, or may the contractor propose an alternate sequence in the phasing plan required by the SOW? Phasing Plan. When is the phasing plan due, what is its review period, and is its appro...
Government Response: