Attachment 6 -APP_E_-_LIGHT_CALCS.pdf
PDF 2 MB Posted
- Solicitation number
- 15BNAS27Q00000002
About this file
This document is a set of electrical calculation sheets prepared by Coffman Engineers for the Federal Bureau of Prisons Three Rivers facility project involving the replacement of Generators 1 and 2 with an enlarged site powerhouse. The calculations dated March 5, 2025 include lighting design analysis for the enlarged site powerhouse and switchgear room, along with voltage drop calculations for critical electrical loads.
The lighting calculations establish illuminance requirements for two zones: the site powerhouse (Z01 and Z02) and the switchgear room (Z04). For the site powerhouse, the calculations show average illuminance of 2.19 footcandles with a maximum of 8.2 footcandles and minimum of 0.4 footcandles, utilizing three DSX2 LED P2 40K 80CRI T1S fixtures and two DSX2 LED P2 40K 80CRI TFTM fixtures with 0.8 light loss factor. The switchgear room requires significantly higher illuminance levels with an average of 29.43 footcandles, maximum of 37.2 footcandles, and minimum of 13.7 footcandles, achieved through nine CLX L96 8000LM SEF FDL MVOLT fixtures at 0.88 light loss factor. Voltage drop calculations for 480-volt, 3-phase systems indicate acceptable performance across multiple circuits including sewer lights, exterior lights, and fire pump controller circuits, with voltage drops ranging from 0.0% to 10.49% and all loads terminating within acceptable limits of 277.0 to 429.6 volts.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1.2 1.6 2.4 2.6 2.4 1.6 1.0 1.7
1.5 0.0 2.8 2.2 2.2
1.2 1.5 0.1 2.7 0.3 1.7
1.2 0.1 0.1 2.2 0.3 2.1 2.1
1.1 0.1 0.2 1.8 2.5 2.4
0.1 0.1 0.2 0.3 0.5 0.7 0.9 1.2 1.4 0.8 1.1 1.6 3.1 2.5 2.9 2.8
0.1 0.2 0.3 0.4 0.5 0.7 1.0 1.1 1.2 0.8 1.1 1.4 2.5 1.9 2.7 3.1 2.7
0.2 0.2 0.3 0.4 0.6 0.9 1.1 1.1 1.3 1.2 1.4 1.4 2.1 1.4 1.9 2.2 1.8
0.2 0.3 0.4 0.5 0.8 1.3 1.3 1.4 1.7 1.6 1.6 2.1 2.0 1.4 1.6 1.8 1.4
0.3 0.4 0.5 0.7 1.2 1.6 1.9 2.1 2.1 1.8 1.8 2.0 1.9 1.3 1.1 0.9 0.8
0.1 0.1 0.1 0.1 0.2 0.2 0.3 0.3 0.4 0.0 0.3 0.3 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.3 0.3 0.4 0.5 0.6 0.7 0.8 1.1 1.9 2.5 2.4 2.5 2.1 1.8 1.9 1.6 1.0 0.8 0.7 0.5
0.1 0.2 0.2 0.2 0.2 0.3 0.4 0.6 0.8 0.0 0.7 0.5 0.4 0.3 0.3 0.2 0.3 0.3 0.4 0.5 0.7 0.8 0.7 0.7 0.7 0.9 1.3 2.0 2.4 2.4 2.5 2.1 1.8 1.6 1.3 0.8 0.6 0.5 0.6
0.3 0.4 0.4 0.5 0.6 0.7 0.6 0.7 1.1 1.2 0.9 0.6 0.5 0.4 0.3 0.3 0.3 0.4 0.5 0.8 1.1 1.2 1.0 0.8 1.0 1.5 1.9 2.3 2.7 2.7 2.5 2.1 1.7 1.3 1.0 0.8 0.6 0.4 0.4
0.5 0.6 0.8 1.0 1.2 1.3 1.2 1.5 2.0 2.0 1.7 1.1 0.9 0.8 0.7 0.6 0.6 0.7 0.7 1.0 1.6 2.0 1.8 1.6 1.9 2.6 2.7 2.8 2.9 2.7 2.3 1.8 1.4 1.0 0.7 0.5 0.4 0.3 0.3
0.6 0.8 0.9 1.2 1.4 1.6 1.7 1.9 2.0 2.0 2.0 1.6 1.6 1.6 1.4 1.3 1.3 1.5 1.4 1.7 2.2 2.2 2.3 2.3 2.6 2.9 2.9 2.8 2.7 2.4 1.9 1.4 1.0 0.7 0.5 0.4 0.3 0.2 0.2
0.6 0.8 1.0 1.2 1.4 1.6 1.9 2.2 2.2 2.2 2.3 2.1 1.9 1.9 1.8 1.8 1.9 2.0 2.0 2.1 2.3 2.3 2.6 2.8 2.8 2.8 2.8 2.6 2.3 2.0 1.5 1.1 0.8 0.5 0.4 0.3 0.2 0.2 0.2
0.6 0.7 0.9 1.1 1.3 1.5 1.7 2.0 2.1 2.2 2.2 2.1 2.0 2.0 2.0 2.0 2.1 2.1 2.2 2.4 2.5 2.5 2.6 2.7 2.6 2.6 2.5 2.2 1.9 1.5 1.1 0.8 0.6 0.4 0.3 0.2 0.2 0.2 0.1
0.5 0.6 0.7 0.9 1.0 1.2 1.4 1.6 1.7 1.8 1.9 1.9 1.9 1.9 1.9 1.9 2.0 2.0 2.1 2.1 2.2 2.3 2.3 2.3 2.2 2.1 1.9 1.7 1.4 1.1 0.8 0.6 0.4 0.3 0.2 0.2 0.1 0.1 0.1
Project
Date:10/14/2024
COFFMAN ENGINEERS
1505 LYNDON B JOHNSON FWY
SUITE 240, DALLAS TX
FEDERAL BUREAU OF PRISONS THREE RIVERS
REPLACE GENERATORS 1&2
ENLARGED SITE POWERHOUSE LIGHTING
CALCULATIONS
ELECTRICAL CALCULATION
COVERSHEET
THIS PAGE HAS BEEN INTENTIONALLY LEFT BLANK
1.0 1.7 1.9 1.9 1.6 1.4 1.1 1.6
1.5 2.3 1.0
1.3 2.2 2.4 1.6 2.1
0.7 1.7 1.7 1.7
0.6 1.3 2.1 2.0
0.6 1.2 2.3 2.3
1.2 1.8 1.5 1.6 1.9 2.4 2.4 2.3
1.4 1.8 1.3 1.2 1.2 1.7 2.2 1.9
0.5 1.2 1.7 2.1 2.1 1.4 1.1 1.0 1.3 1.6 1.3
0.7 1.4 2.5 3.2 2.9 2.2 1.3 1.0 0.8 0.8 0.9 0.8
0.8 1.7 3.6 5.4 4.7 2.7 1.6 1.0
0.5 1.4 3.7 7.4 7.0 3.5 1.6 1.0
1.2 2.8 6.2 7.9 4.1 1.8 1.1 0.7
0.4 0.6 0.8 1.1 1.4 1.7 2.0 2.2 2.1 1.5 1.0 0.8 0.6 0.4 0.4 0.4 0.4 0.5 0.7 1.1 1.6 1.6 1.6 2.0 2.7 4.2 6.2 4.6 2.1 1.3 0.8 0.4
0.6 0.9 1.2 1.8 2.5 3.7 5.3 6.6 6.3 4.6 2.9 2.0 1.4 1.1 1.0 1.0 1.2 1.6 2.3 3.6 4.8 5.0 4.4 3.9 3.9 4.6 4.4 2.5 1.6 1.0 0.5
0.7 1.0 1.3 1.9 2.7 3.8 5.4 6.8 7.3 6.2 4.6 3.1 2.2 1.7 1.6 1.7 2.1 3.1 4.8 7.0 8.2 7.5 5.9 4.7 4.2 3.9 3.0 1.9 1.2 0.7 0.4
0.6 0.8 1.0 1.2 1.5 1.6 1.8 2.1 2.4 2.7 2.8 2.6 2.2 2.0 1.9 2.1 2.6 3.4 4.2 4.4 3.8 3.2 2.9 2.9 2.9 2.6 2.0 1.3 0.8
0.4 0.5 0.6 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.5 1.6 1.7 1.8 1.9 2.0 2.0 1.8 1.6 1.5 1.5 1.6 1.7 1.7 1.6 1.2 0.8 0.5
Z01
Z01
Z01
Z02
Z02
Project
Date:03/05/2025
COFFMAN ENGINEERS
1505 LYNDON B JOHNSON FWY
SUITE 240, DALLAS TX
FEDERAL BUREAU OF PRISONS THREE RIVERS
REPLACE GENERATORS 1&2
ENLARGED SITE POWERHOUSE LIGHTING
CALCULATIONS
Project
Date:03/05/2025
COFFMAN ENGINEERS
1505 LYNDON B JOHNSON FWY
SUITE 240, DALLAS TX
FEDERAL BUREAU OF PRISONS THREE RIVERS
REPLACE GENERATORS 1&2
ENLARGED SITE POWERHOUSE LIGHTING
CALCULATIONS
23.7 27.7 28.8 31.2 33.3 35.0 35.7 36.0 36.2 36.2 36.1 35.7 35.1 34.5 33.6 32.2 30.3 28.6 27.5 27.3 28.0 28.4 28.4 27.9 27.3 26.2 24.4 21.5
27.0 30.8 26.8 29.5 32.4 34.4 35.4 36.0 36.5 36.7 36.7 36.2 35.7 34.8 33.8 32.4 30.0 29.9 29.3 29.6 31.1 31.7 31.8 31.3 30.7 29.6 27.6 24.4
28.5 28.3 26.9 30.4 32.6 33.6 33.8 33.3 32.6 31.5 29.4 25.8
22.2 22.3 19.1 23.4 30.1 32.5 33.5 33.1 32.5 31.4 29.3 25.6
22.4 22.7 18.1 21.9 28.4 30.6 31.2 30.6 30.1 29.2 27.3 24.0
25.4 21.9 16.3 23.1 27.0 26.5 26.9 26.7 26.5 25.7 24.1 21.2
27.3 30.5 22.0 25.0 27.5 29.2 30.5 31.3 31.8 32.0 31.8 31.4 30.5 29.4 27.6 25.4 22.3 19.6 24.1 18.0
25.7 29.4 27.5 29.9 32.4 34.4 35.3 35.9 36.3 36.4 36.2 35.5 34.6 33.3 31.5 29.0 27.0 25.4 22.6 14.7
23.3 27.0 28.5 31.2 33.6 35.6 36.4 36.9 37.2 37.2 36.9 36.5 35.4 34.2 32.5 30.2 27.4 24.6 19.9 14.7
20.4 23.8 27.1 29.9 32.2 33.6 34.4 34.8 35.0 35.0 34.7 34.2 33.2 32.2 30.6 28.4 25.8 21.7 17.5 13.7
Z04 Z04
Z04 Z04 Z04
Z04
Z04 Z04 Z04
Project
Date:03/05/2025
COFFMAN ENGINEERS
1505 LYNDON B JOHNSON FWY
SUITE 240, DALLAS TX
FEDERAL BUREAU OF PRISONS THREE RIVERS
REPLACE GENERATORS 1&2
ENLARGED POWERHOUSE SWITCHGEAR ROOM
LIGHTING CALCULATIONS
COFFMAN ENGINEERS
1505 LYNDON B JOHNSON FWY
SUITE 240, DALLAS TX
FEDERAL BUREAU OF PRISONS THREE RIVERS
REPLACE GENERATORS 1&2
ENLARGED POWERHOUSE SWITCHGEAR ROOM
LIGHTING CALCULATIONS
COFFMAN ENGINEERS
1505 LYNDON B JOHNSON FWY
SUITE 240, DALLAS TX
FEDERAL BUREAU OF PRISONS THREE RIVERS
REPLACE GENERATORS 1&2
VOLTAGE DROP CALCULATIONS
| Sheets and Views |
| Unsaved Drawing1-Layout1 |
| Unsaved Drawing1-Layout2 |
| Unsaved Drawing2-Layout1 |
| Unsaved Drawing2-Layout2 |
File details come from the government source that posted it. Updated .