This is a Corrective Action Request (CAR) Form template used in federal contract management to document and track quality or compliance deficiencies.
Section I, completed by the government, captures the problem identification and documentation. It requires a tracking number, contract number, CAR severity level (I, II, III, or IV), identification and issuance dates, the contractor site lead receiving the CAR, and a 45-day response deadline from the issue date. The government must document the problem description, supporting evidence, the contractual or performance requirement that was not met, and a statement of nonconformity. This section also indicates whether a Root Cause Analysis (RCA) is required, noting that RCAs may not be required for Level I CARs.
Section II is completed by the affected contractor if an RCA is required. The contractor must identify the root cause of the problem, specify whether corrective action is needed, document the immediate correction with completion dates, and describe corrective actions to prevent recurrence with an estimated completion date. The Site Lead confirms completion once actions are finished. Section III, completed by the initiating government official, evaluates the effectiveness of the contractor's corrective actions, reviews the RCA and proposed prevention measures, and determines whether the Corrective Action Plan is acceptable. The final closure requires signatures from the Unit GFR/AGFR and COR, with notification to PMA-266 GFR prior to formal closeout.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Corrective Action Request Form
Section 1: CAR Initiation This Section to be completed by the Government.
Tracking Number:
Contract Number:
CAR Level I/II/III/IV:
Date: Identified by (APT Member and Unit):
Date: Issued by (COR/GFR/AGFR):
Response Due Date (45 days from issue date):
Issued to (Contractor Site Lead):
Description of the problem (Filled out by APT Member):
Evidence:
Requirement:
Statement of Nonconformity:
Contractor’s Root Cause Analysis (RCA) needed? Yes No (RCA may not be required for Level I CAR)
Section II: Investigation and Action This section to be completed by the affected Contractor if RCA box directly above is checked “Yes”.
Root cause of the actual or potential problem: (How/Why did this happen?)
Action needed? Yes No (If “Yes” is checked, fill out the rest of Section II)
Correction (fix now) with completion dates:
Corrective Action (to prevent recurrence) to be taken:
Estimated completion date:
This section to be completed by the affected Site Lead - after initial correction is completed.
Action completed by: Date completed:
Section III Follow-Up and Closure This section is to be completed by initiating Government after action is completed.
Results of immediate action taken:
Was the action effective? Yes No Explain:
Document any further details if contractor’s initial action was not effective, their RCA was unacceptable, or their proposed action to prevent recurrence was unacceptable. If Corrective Action Plan is acceptable, state that clearly:
Results reviewed by: Date closed:
CAR form emailed to PMA-266 GFR with recommendation to close out? Yes No
Date:
Unit GFR/AGFR signature:
CAR form closed out (PMA-266 GFR/COR)? Yes No Date:
COR Signature:
| Tracking Number: |
| Contract Number: |
| CAR Level IIIIIIIV: |
| Date: |
| Identified by APT Member and Unit: |
| Date_2: |
| Issued by CORGFRAGFR: |
| Issued to Contractor Site Lead: |
| Description of the problem Filled out by APT Member Evidence Requirement Statement of Nonconformity: |
| Contractors Root Cause Analysis RCA needed: Off |
| Root cause of the actual or potential problem HowWhy did this happen: |
| Action needed: Off |
| Correction fix now with completion dates: |
| Corrective Action to prevent recurrence to be taken: |
| Estimated completion date: |
| Action completed by: |
| Date completed: |
| Results of immediate action taken: |
| Was the action effective Yes No Explain: |
| Was the action effective: Off |
| Document any further details if contractors initial action was not effective their RCA was unacceptable or their proposed action to prevent recurrence was unacceptable If Corrective Action Plan is acceptable state that clearly: |
| Results reviewed by: |
| Date closed: |
| out: Off |
| Date_3: |
| CAR form closed out PMA266 GFRCOR: Off |
| Date_4: |
| Text1: |
| Text2: |
| Text3: |
File details come from the government source that posted it. Updated .