Attachment 10 - Contractor Core Work Hours.docx
DOCX document 22 KB Posted
- Attached to
- Y1AZ--36C77621B0013 - Construct Administration Bldg. POD 1A (Minor) - Gainesville Federal contract opportunity
- Solicitation number
- 36C77621B0013
About this file
This document provides details for a federal solicitation to construct an administration building at the Malcom Randall VA Medical Center in Gainesville, Florida. The solicitation seeks a firm-fixed-price contract to construct a new 26,000 square foot administration building adjacent to an existing community living center. The scope of work includes architectural, site, structural, fire protection, HVAC, plumbing, electrical, earthwork, exterior utilities, demolition of existing structures, and all other construction aspects required by contract drawings and specifications. The Department of Veterans Affairs Technology Acquisition Center Austin issued the solicitation and aims to award a single contract. Normal core work hours for the project are from 7:00 AM to 5:00 PM Monday through Friday, and requests to perform work outside these hours require approval from the contracting officer and contracting representative with 72 hours' notice. Non-scheduled nights, weekends, and federal holiday work also require advance approval from the contracting representative.
View the file
Other files for this federal contract opportunity
Show all 32
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Malcom Randall VAMC Project 573-360 Construct Administration Building POD 1A
Contractor Core Work Hours
1. Normal working hours for this contract will be from 7:00 AM to 5:00 PM (local time) Monday through Friday except for weekends and established Federal Holidays.
2. Performing on-site work outside normal working hours will require approval from the Contracting Officer and the COR. Requests shall be submitted via email at least 72 hours before the requested date and at no additional cost to the Government. Approvals are subject to the availability of on-site staff.
3. Non-scheduled Nights and Weekends/Holidays work will need to be approved by the COR ahead of time, with as much advance notice as is practicable.
File details come from the government source that posted it. Updated .