ATTACHMENT 1 - Specifications.pdf

PDF 16 MB Posted

Attached to
Y1AZ--EHRM Infrastructure Upgrades Construction West Palm Beach Federal contract opportunity
Solicitation number
36C77623B0045
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This attachment provides specifications for infrastructure upgrades at the Department of Veterans Affairs medical center in West Palm Beach, Florida. The solicitation seeks a contractor to modernize key systems at the facility, including upgrades to the electronic health records platform, network infrastructure, telecommunications equipment, and security systems. Responses are due by January 15, 2023, with the contract to be awarded by March 1, 2023. The selected vendor will be responsible for replacing servers, storage arrays, switches and routers to improve network performance and reliability in supporting clinical operations. Additionally, the project involves deploying new access control and video surveillance solutions to enhance physical security. The work is to be completed within an 18-month performance period.

View the file

Other files for this federal contract opportunity

Other files attached to Y1AZ--EHRM Infrastructure Upgrades Construction West Palm Beach, newest first.
File Type Posted
36C77623B0045 0003.pdf PDF
Clarifications to Technical Questions 9-5-23.pdf PDF
Updated Drawings for Clarifications.pdf PDF
Cart Lift Motor Photos.pdf PDF
36C77623B0045 0002.pdf PDF
Technical Questions - FINAL - West Palm Beach 8-21-23.pdf PDF
Map of Wells Question 66.pdf PDF
Photos for Responses to Questions 124 and 127.pdf PDF
36C77623B0045 0001.pdf PDF
Site Visit Sign-in Sheet - West Palm Beach 7-19-23.pdf PDF
ATTACHMENT 24 - Construction Wage Rates - Palm Beach 7-7-23.pdf PDF
ATTACHMENT 4 - Civil 1 of 5.pdf PDF
ATTACHMENT 5 - Civil 2 of 5.pdf PDF
ATTACHMENT 16 - Telecom 1 of 6.pdf PDF
ATTACHMENT 18 - Telecom 3 of 6.pdf PDF
ATTACHMENT 19 - Telecom 4 of 6.pdf PDF
ATTACHMENT 23 - Limitations on Subcontracting - Construction.docx DOCX document
ATTACHMENT 24 - Construction Wage Rates - Palm Beach 3-24-23.pdf PDF
36C77623B0045 - 7-6-23.pdf PDF
ATTACHMENT 6 - Civil 3 of 5.pdf PDF
ATTACHMENT 11 - Mechanical 1 of 2.pdf PDF
ATTACHMENT 14 - Security.pdf PDF
ATTACHMENT 15 - Structural.pdf PDF
ATTACHMENT 17 - Telecom 2 of 6.pdf PDF
ATTACHMENT 21 - Telecom 6 of 6.pdf PDF
ATTACHMENT 25 - Contractor Safety - Environmental Form.docx DOCX document
ATTACHMENT 7 - Civil 4 of 5.pdf PDF
ATTACHMENT 10 - Fire Protection.pdf PDF
ATTACHMENT 22 - Contractor Core Work Hours.pdf PDF
ATTACHMENT 26 - Site Visit Instructions.pdf PDF
ATTACHMENT 2 - General.pdf PDF
ATTACHMENT 8 - Civil 5 of 5.pdf PDF
ATTACHMENT 9 - Electrical.pdf PDF
ATTACHMENT 12 - Mechanical 2 of 2.pdf PDF
ATTACHMENT 13 - Plumbing.pdf PDF
ATTACHMENT 20 - Telecom 5 of 6.pdf PDF
ATTACHMENT 3 - Architectural.pdf PDF
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ELECTRONIC HEALTH RECORD MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

PROJECT NAME:

7305 N. Military Trail

West Palm Beach, FL 33410

SITE ADDRESS:

VA PROJECT NUMBER:

548-22-700

SPECIFICATIONS

EHRM Infrastructure Upgrades – West Palm Beach, FL 100% Final Stamped

West Palm Beach VA Medical Center (VAMC) Bid Documents

VA Contract #36C77622C0034 03/31/2023

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawings 05-01

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21

01 32 16.15 Project Schedules 11-21

01 33 23 Shop Drawings, Product Data, and Samples 09-22

01 35 26 Safety Requirements 10-22

01 42 19 Reference Standards 11-20

01 45 00 Quality Control 02-21

01 45 29 Testing Laboratory Services 11-18

01 45 35 Special Inspections 06-21

01 57 19 Temporary Environmental Controls 01-21

01 58 16 Temporary Interior Signage 07-15

01 74 19 Construction Waste Management 04-22

01 81 13 Sustainable Construction Requirements 10-17

01 91 00 General Commissioning Requirements 04-22

DIVISION 02 – EXISTING CONDITIONS

02 21 13 Site Surveys 01-21

02 41 00 Demolition 08-17

DIVISION 03 – CONCRETE

03 30 00 Cast-in-Place Concrete 01-21

03 30 00.10 Portland Cement Pervious Payment 08-03

03 30 53 (Short-Form) Cast-in-Place Concrete 01-21

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18

05 36 00 Composite Metal Decking 01-21

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

06 16 63 Cementitious Sheathing 01-21

06 20 00 Finish Carpentry 01-21

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 13 00 Sheet Waterproofing 01-21

07 21 13 Thermal Insulation 01-21

07 22 00 Roof and Deck Insulation 01-21

07 24 00 Exterior Insulation and Finish Systems 01-21

07 27 26 Fluid-Applied Membrane Air Barrier, Vapor Permeable 01-21

07 54 23 Thermoplastic Polyolefin (TPO) Roofing 01-21

07 60 00 Flashing and Sheet Metal 01-21

07 72 00 Roof Accessories 01-21

VA Contract #36C77622C0034 03/31/2023

00 01 10-2

07 71 00 Roof Specialties

07 81 00 Applied Fireproofing 10-17

07 84 00 Firestopping 01-21

07 92 00 Joint Sealants 04-22

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21

08 14 00 Interior Wood Doors 01-21

08 31 13 Access Doors and Frames 04-22

08 33 00 Coiling Doors and Grilles 01-21

08 34 53 Security Doors and Frames 01-21

08 71 00 Door Hardware 05-22

08 90 00 Louvers and Vents 01-21

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 01-21

09 06 00 Schedule for Finishes 01-21

09 22 16 Non-Structural Metal Framing 06-18

09 29 00 Gypsum Board 04-20

09 51 00 Acoustical Ceilings 12-18

09 65 13 Resilient Base and Accessories 01-21

09 65 19 Resilient Tile Flooring 05-18

09 68 00 Carpeting 01-21

09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

10 14 00 Signage 01-21

10 26 00 Wall and Door Protection 01-21

10 28 00 Toilet, Bath, and Laundry Accessories 01-21

10 44 13 Fire Extinguisher Cabinets 08-18

DIVISION 21 – Fire Suppression

21 08 00 Commissioning of Fire Suppression Systems 11-16

21 13 13 Wet-Pipe Sprinkler Systems 06-15

21 13 16 Dry-Pipe Sprinkler Systems 01-15

21 22 00 Clean Agent Fire Suppression Systems 05-15

DIVISION 22 - PLUMBING

22 05 11 Common Work Results for Plumbing 09-20

22 05 19 Meters and Gages for Plumbing Piping 09-20

22 05 23 General-Duty Valves for Plumbing Piping 09-20

22 07 11 Plumbing Insulation 09-19

22 08 00 Commissioning of Plumbing Systems 11-16

22 11 00 Facility Water Distribution 05-21

22 13 00 Facility Sanitary and Vent Piping 09-20

22 14 36 Packaged, Submersible Sewerage Pump Units 09-15

22 40 00 Plumbing Fixtures 12-22

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 04-22

VA Contract #36C77622C0034 03/31/2023

00 01 10-3

23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment

02-20

23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment

02-20

23 05 93 Testing, Adjusting, and Balancing for HVAC 04-21

23 07 11 HVAC and Boiler Plant Insulation 02-20

23 08 00 Commissioning of HVAC Systems 04-22

23 09 23 Direct-Digital Control System for HVAC 09-11

23 10 00 Facility Fuel Systems 04-20

23 21 13 Hydronic Piping 02-20

23 21 23 Hydronic Pumps 02-20

23 23 00 Refrigerant Piping 04-22

23 31 00 HVAC Ducts and Casings 04-22

23 34 00 HVAC FANS 04-22

23 36 00 Air Terminal Units 02-20

23 37 00 Air Outlets and Inlets 02-20

23 64 00 Packaged Water Chillers 04-22

23 81 00 Decentralized Unitary HVAC Equipment 04-22

23 81 23 Computer-Room Air-Conditioners 03-20

23 81 43 Air-Source Unitary Heat Pumps 03-20

DIVISION 25 – INTEGRATED AUTOMATION

25 10 10 Advanced Utility Metering System 02-10

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16

26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17

26 05 26 Grounding and Bonding for Electrical Systems 01-17

26 05 33 Raceway and Boxes for Electrical Systems 01-18

26 05 41 Underground Electrical Construction 01-17

26 08 00 Commissioning of Electrical Systems 01-16

26 08 00.01 DVA/USACE Projects Commissioning of Electrical Systems 08-19

26 09 23 Lighting Controls 01-18

26 22 00 Low-Voltage Transformers 01-18

26 24 13 Distribution Switchboards 01-18

26 24 16 Panelboards 01-18

26 25 11 Busways 01-17

26 27 26 Wiring Devices 01-18

26 29 11 Motor Controllers 01-18

26 29 21 Enclosed Switches and Circuit Breakers 01-17

26 32 13 Engine Generators 01-18

26 33 53 Static Uninterruptible Power Supply 01-17

26 36 23 Automatic Transfer Switches 01-17

26 41 00 Facility Lightning Protection 01-17

26 43 13 Surge Protective Devices 01-17

26 51 00 Interior Lighting 01-18

26 56 00 Exterior Lighting 01-18

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19

27 05 26 Grounding and Bonding for Communications Systems 06-15

27 05 33 Conduits and Backboxes for Communications Systems 11-21

27 05 36 Cable Trays for Communication Systems 11-21

VA Contract #36C77622C0034 03/31/2023

00 01 10-4

27 05 53 Identification for Communication Systems 11-21

27 10 00 Structured Cabling 11-22

27 11 16 Communications Cabinets, Racks, Frames and Enclosures 11-21

27 11 19 Communications Termination Blocks and Patch Panels 11-21

27 11 26 Communications Rack Mounted Power Protection and Power

Strips

11-22

27 13 13 Communications Copper Backbone Cabling 11-21

27 13 13.13 Communications Copper Cable Splicing and Terminations 11-21

27 13 23 Communications Optical Fiber Backbone Cabling 11-21

27 15 13 Communications Copper Horizontal Cabling 11-21

27 15 13.13 Communications Optical Fiber Cable Splicing and

Terminations

11-21

27 16 19 Communications Patch Cords, Station Cords, and Cross

Connect Wire

11-21

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18

28 13 00 Physical Access Control System 10-11

28 23 00 Video Surveillance 06-22

28 31 00 Fire Detection and Alarm 10-11

DIVISION 31 – EARTHWORK

31 20 11 Earthwork (Short Form) 10-12

31 23 19 Dewatering 10-12

31 23 23.33 Flowable Fill 10-12

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 08-16

32 12 16 Asphalt Paving 09-15

32 17 23 Pavement Markings 08-16

23 31 40 Security Fences and Gates 08-16

23 90 00 Planting 07-16

DIVISION 33 – UTILITIES

33 08 00 Commissioning of Site Utility Systems 11-16

33 10 00 Water Utilities 03-17

33 30 00 Sanitary Sewer Utilities 06-136

33 40 00 Storm Sewer Utilities 12-17

33 46 13 Foundation Drainage 10-11

DIVISION 34 – TRANSPORTATION

34 71 13 Passive Vehicle Barriers 04-18

34 75 13.13 Active Vehicle Barriers 08-16

APPENDIX SECTION

Appendix A Hazardous Materials Survey

Appendix B GeoTech Boring Report

Appendix C NEPA CATEX Report

EHRM Infrastructure Upgrades – WBP, FL 100% Final Stamped

VA Contract #36C77622C0034 03/31/2023

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWINGS

For list of drawings please refer to the General Drawings sheet GI001 SHEET INDEX. These drawings are the official drawings of record.

- - - E N D - - -

VA Contract #36C77622C0034 03/31/2023

01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 GENERAL

1.2 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.3 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Electronic Health Record

Modernization (EHRM) Infrastructure Upgrades at the VA Health Care

System in West Palm Beach, Florida as required by drawings and specifications.

B. Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the Contracting

Officer.

C. Offices of Specialized Engineering Solutions, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the

Government without affirmations by Contracting Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.

1. Testing laboratory shall be approved by the VA before commencement of work.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

F. The VA will provide the Contractor direction, after being awarded the project, regarding Personal Identity Verification (PIV) submittal requirements for Contractor employees and Subcontractor employees for

VA Contract #36C77622C0034 03/31/2023

01 00 00 -2 the project. Submittals by the Contractor to the VA of this information must be provided within 15 days of the Contractor or

Subcontractor Employee coming on site.

1.4 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: BASE BID Work includes addition of new

Building 23 housing new data center and, infrastructure upgrades and reconfiguring and renovating existing spaces impacted by said improvements. Infrastructure upgrades include electrical, bonding, UPS, building management system interfaces, HVAC, communication, physical security upgrades, and fiber infrastructure backbone campus wide within and between buildings, including modification to impacted roads, walks, grading and drainage, and other existing utilities, WAN updates, and hazardous material abatement. Project Buildings include

1,3,4,6,7,10,12,14,15,18,19, 21,22, new building 23 and associated work in other buildings as indicated.

1.5 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.6 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security escort and or other arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

VA Contract #36C77622C0034 03/31/2023

01 00 00 -3

3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The VA will provide keys and cores for use by the contractor.

Contractor to pay for any new cores needed.

2. The General Contractor shall install all permanent cores at completion of the work. See Section 08 71 00, DOOR HARDWARE and coordinate.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting

Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS).

VA Contract #36C77622C0034 03/31/2023

01 00 00 -4

Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

1.7 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the

Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the

Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting

Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting

Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting

Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. The contractor shall not be allowed to store materials inside the building. Contractors shall provide their own storage containers. The

VA will coordinate an area on site for contractor storage, this area is anticipated to be at the construction area for new Building 24; however the VA reserves the right to establish a different location.

Environmental requirements of the storage units shall comply with the manufacturers guidelines for the products stored. Contractor to shield

VA Contract #36C77622C0034 03/31/2023

01 00 00 -5 storage site from public view. Working space and space available for storing materials shall be coordinated with and as determined by the

COR. Contractor responsible for security of their own materials and protection of materials from weather.

E. Workers are subject to rules of Medical Center applicable to their conduct.

F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

G. Execute work to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of

Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR . All such actions shall be coordinated with the COR or Utility Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

VA Contract #36C77622C0034 03/31/2023

01 00 00 -6

I. Phasing:

1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.

It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Since unpredictable variables may affect the construction sequence scheduling, a protocol for making changes due to unforeseen problems should be plainly stated. The Contractor shall update the

Construction Sequencing Plan as changes occur during the course of

Work. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center

Director, COR and Contractor.

3. Most buildings in this project will be fully occupied during

Construction. Contractor shall propose a sequence of work necessary on each floor and building so that disruption to the occupied portions of the floors can be minimized while progressing the Work.

Note that work done above and below occupied spaces will need to be carefully coordinated with the COR and Medical Center Director well in advance of the Work.

4. Access to occupied spaces will be limited since many areas will remain open and operational during construction. Only portions of each floor may be made available at any given time, which will require the sequencing of the work in many rooms on multiple occasions, potentially requiring completion of some on a room by room basis. Work may need to be limited to hours outside of normal business hours when spaces are unoccupied. The sequencing of access to spaces will be coordinated with the COR.

VA Contract #36C77622C0034 03/31/2023

01 00 00 -7

J. All project building(s) should be expected to be occupied during performance of work but immediate areas of alterations will be vacated.

1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of

Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.

Coordinate alteration work in areas occupied by Department of

Veterans Affairs so that Medical Center operations will continue during the construction period.

2. Immediate areas of alterations not mentioned in preceding

Subparagraph 1 will be temporarily vacated while alterations are performed.

K. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.

Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm

(one inch) above grade. Remove the fence when directed by COR.

L. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

VA Contract #36C77622C0034 03/31/2023

01 00 00 -8

M. Utilities Services: Maintain existing utility services for Medical

Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.

Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of, or discrepancy of, such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of the COR Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR

COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR

ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to

COR, in writing, 14 days in advance of proposed interruption.

Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, VA Contract #36C77622C0034 03/31/2023

01 00 00 -9 payment of such fee shall be the responsibility of the Government and not the Contractor.

1. Anticipated major utility shutdowns and estimated permitted downtime at campus and building level include:

a. Campus Wide:

1) In coordination with the government and the Main Computer Room

(MCR) migration project, the move of equipment from the old server room to new MCR will require a series of one to eight hour Telecommunication outages - Approximately (4) of such outages over the course of one month is expected.

2) The installation of new fibers on site will require some site utility outages for relocation - Approximately (6) one-hour outages throughout a three month duration is expected.

3) Mechanical/Plumbing/Fire Protection will have small relocates

– approximately one to two days outages per floor expected.

b. Building 1 - Main Hospital:

1) Tie-in of dedicated chilled water system for TR rooms into existing building 1 chilled water mains for TR room cooling redundancy. Work needs to be done on evenings and weekends.

Submit draft plan to COR 90 days in advance of proposed work date.

2) Substation A – installation of new circuit breaker -approximately 8 hours electrical shutdown is expected.

3) Substation G – installation of new circuit breaker – approximately 8 hours electrical shut-down is expected.

4) New Emergency Distribution Switchboard – installation of new circuit breaker – approximately 8 hours electrical shut-down is expected.

5) Vertical Busway Risers – installation of new circuit breaker – approximately 8 hours electrical shut-down is expected.

6) Distribution Panelboard NHGF – installation of new circuit breaker to serve new Building 6 electrical service – approximately 8 hours electrical shut-down is expected.

c. Buildings 3, CLC -Community Living Center:

1) Panelboard NLDB1 – installation of new circuit breaker to serve panelboard as a main and installation of new circuit breaker to serve TR panelboard – approximately 8 hours electrical shut-down is expected.

VA Contract #36C77622C0034 03/31/2023

01 00 00 -10

2) Panelboard CLDB1 – installation of new circuit breaker to serve new TR panelboard – approximately 4 hours electrical shut-down is expected.

3) Tie-in to existing chilled water lines to serve new fan coil unit. Work during night or weekend.

d. Building 4 – Fisher House:

1) Panelboard Interior – Installation of new circuit breaker to serve new panelboard – approximately 4 hours electrical shut-down is expected.

e. Building 6 – Union Trailer:

1) Existing trailer service load center – Disconnection and connection to new electrical service panelboard – approximately 4 hours electrical shut-down is expected.

f. Building 10 -VBA/VSO Building:

1) Panelboard NL4BG10 – installation of new circuit breakers to serve new TR panelboards – approximately 4 hours electrical shut-down is expected.

g. Building 12 – Human Resources:

1) Panelboard NLBDG12 – installation of new circuit breakers to serve new TR panelboards – approximately 4 hours electrical shut-down is expected.

h. Building 14:

1) Panelboard HP2 – installation of new circuit breakers to serve new TR panelboards – approximately 4 hours electrical shut-down is expected.

i. Building 16 – Mental Health/Outpatient:

1. Panelboard 16HEDP – installation of new circuit breaker to serve new TR panelboard – approximately 4 hours electrical shut-down is expected.

2) Panelboard 16L1NR – installation of new circuit breaker to serve new TR panelboard – approximately 4 hours electrical shut-down is expected.

j. Building 19 – Hospice:

2) Panelboard NLHU-1 – installation of new circuit breaker to serve new TR panelboard – approximately 4 hours electrical shut-down is expected.

VA Contract #36C77622C0034 03/31/2023

01 00 00 -11

1) Panelboard CHDPHU-1 – installation of new circuit breaker to serve new TR panelboard – approximately 4 hours electrical shut-down is expected.

2) New chilled water tie-ins of mains and reroute of heating hot water lines. Work to be done on nights and weekends.

k. Building 22 – Domiciliary:

1) Panelboard LB1 – installation of new circuit breaker to serve new TR panelboard – approximately 4 hours electrical shut-down is expected.

l. Parking Lot 18/19:

1) Parking Lot Lighting – disconnection and removal of two existing lighting poles and associated branch circuiting to accommodate revisions to site. Existing poles will be re-installed at new locations with new branch circuits for a complete system. Time of de-energization is unknown.

N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

O. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

P. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

VA Contract #36C77622C0034 03/31/2023

01 00 00 -12

1.8 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, Contractor and the COR or other Designated Authorized Government

Authority. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

VA Contract #36C77622C0034 03/31/2023

01 00 00 -13

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR or other

Designated Authorized Government Authority.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of the

COR or other Designated Authorized Government Authority, and/or Supply

Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by

Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-

2) and "CHANGES" (FAR 52.243-4).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of

Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately

VA Contract #36C77622C0034 03/31/2023

01 00 00 -14 protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.9 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags and/or noted on drawings or in specifications as items to be stored or salvaged. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS (FAR 52.236-9)

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those

VA Contract #36C77622C0034 03/31/2023

01 00 00 -15 facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the

Contractor fails or refuses to repair the damage promptly, the

Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and

"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge

Elimination System (NPDES) permit is required for this project. The

Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements.

Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the

Contractor's method of operations and operations planning and the

Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:

1. Designating areas for equipment maintenance and repair;

2. Providing waste receptacles at convenient locations and provide regular collection of wastes;

3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;

4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and

5. Providing adequately maintained sanitary facilities.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any

VA Contract #36C77622C0034 03/31/2023

01 00 00 -16 ducts, plumbing, steam, gas, or electric work without approval of the

COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"

(FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.11 PHYSICAL DATA – SOIL CONDITIONS

A. Data and information furnished or referred to below is for the

Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by the design team.

(FAR 52.236-4)

B. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration are shown diagrammatically on drawings.

C. A copy of the soil report will be made available for inspection by bidders upon request to the Engineering Officer at the VA Medical

Center, and shall be considered part of the contract documents.

D. There are existing arsenic wells on the site. A copy of the arsenic wells map will be made available for inspection by bidders upon request

VA Contract #36C77622C0034 03/31/2023

01 00 00 -17 to the Engineering Officer at the VA Medical Center and shall be considered part of the contract documents.

E. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of

Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.

1.12 PROFESSIONAL SURVEYING SERVICES

A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.

The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.

1.13 LAYOUT OF WORK

A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The

Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them.

If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.

(FAR 52.236-17)

B. Establish and plainly mark utility center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each

VA Contract #36C77622C0034 03/31/2023

01 00 00 -18 such structure , roads, and parking lots, are in accordance with lines and elevations shown on contract drawings.

C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:

1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.

D. During progress of work, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the COR before any major items of concrete work are placed. In addition, Contractor shall furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.

1. Lines of each building and/or addition.

2. Elevations of bottoms of footings and tops of floors of each building and/or addition.

3. Lines and elevations of sewers and of all outside distribution systems.

4. Lines of elevations of all swales and interment areas.

5. Lines and elevations of roads, streets and parking lots.

E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.

F. Upon completion of the work, the Contractor shall furnish the COR one electronic copy and reproducible drawings at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work, including burial monuments and fifty foot

VA Contract #36C77622C0034 03/31/2023

01 00 00 -19 stationing along new road centerlines. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.

G. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of

Article "Professional Surveying Services".

1.14 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR. After acceptance by the COR the approved sets will be made available to the design team for incorporation into the final Revit file drawings to be provided to the VA.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.15 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the

Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of

VA Contract #36C77622C0034 03/31/2023

01 00 00 -20 acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a.…