About this file

This document is a submittal register for a mechanical/electrical project at Robins Air Force Base. It outlines 49 submittal items required from the contractor, including progress reports, design submittals, material submittals, as-built drawings, warranties, and operation and maintenance manuals. Due dates are provided for each submittal item, with most items due 210 days after notice to proceed. The register will be used by the contractor to organize submissions to the government. It is related to solicitation number FA850124R0001 for mechanical/electrical indefinite-delivery/indefinite-quantity contract services at Robins AFB issued by the Department of the Air Force Materiel Command Air Force Sustainment Center. The solicitation provides for various construction and facility support services at Robins AFB.

View the file

Other files for this federal contract opportunity

Other files attached to Robins AFB Mechanical/Electrical II IDIQ, newest first.
File Type Posted
RFI_230077.230101_Mech.Elec_FINAL_Rev01_01162024.xlsx XLSX spreadsheet
RFI_230077.230101_Mech.Elec_FINAL_01022024.xlsx XLSX spreadsheet
ATTACH25_B670_Drawing_Floor Plan.pdf PDF
ATTACH01_SOW_MechElec_Rev03_12292023.pdf PDF
FA850124R00010001_01022024.pdf PDF
ATTACH24_B670_Fire Plan.pdf PDF
ATTACH18_AF3064_BLANK_SAMPLE.xlsx XLSX spreadsheet
ATTACH19_AF3065_BLANK_SAMPLE.xlsx XLSX spreadsheet
Mech.Elec.2_site.visit.attendance_14Dec2023.pdf PDF
ATTACH20_WD_GA20230322_07212023.pdf PDF
ATTACH17_AF3052_BLANK_SAMPLE.XLS XLS spreadsheet
ATTACH14_DD1354(BLANK)_SAMPLE.PDF PDF
ATTACH13_Form 911 DesignDiscipline Review.docx DOCX document
ATTACH11_TEMPLATE_Schedule of Values_BLANK.PDF PDF
ATTACH08_AppC_Safety_053312023.PDF PDF
ATTACH06_Asbestos Management Plan_2015.PDF PDF
ATTACH19_AF3065_BLANK_SAMPLE.pdf PDF
ATTACH10_SUBMITTAL REGISTER.XLS XLS spreadsheet
ATTACH07_ICD705_Construction and Management_SCIF.PDF PDF
ATTACH04_AFMAN 31-116 Motor Vehicle Traffic Supervision.PDF PDF
ATTACH18_AF3064_BLANK_SAMPLE.pdf PDF
ATTACH16_AF3000_MaterialSubmittal.PDF PDF
ATTACH15_AF2586 Flightline Driving Request.PDF PDF
ATTACH05_AFMAN 32-1084 Civil Engineering Facility Requirements.PDF PDF
ATTACH02_Robins BFS 2022.pdf PDF
FA850124R0001_FINAL_00_11092023.pdf PDF
ATTACH09_WR-ALC SAFE-T-GRAM.PDF PDF
ATTACH22_230101DEMO_Bid Schedule_BLANK.pdf PDF
ATTACH21_230101DEMO_SOW_07102023.pdf PDF
ATTACH12_Master Utility Outage.PDF PDF
ATTACH03_ProceduralGuide_DesignersAE_2023.PDF PDF
ATTACH01_SOW_MechElec_Rev02_08112023.pdf PDF
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

SCHEDULE OF MATERIAL SUBMITTALS
ROBINS AFBPROJECT NO.PROJECT TITLESOLICITATION/CONTRACT NO.
UHHZ230101RPR/RPL HOT WATER HEATING SYSTEM, SHP ACFT GEN PURP, B670
TO BE COMPLETED BY PROJECT ENGINEER
NO. OF COPIES REQUIRED
BEFORE CONSTRAFTER CONSTR
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALSHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONSCATALOG DATAOTHER MATERIAL OR DATACERTIFICATION OF COMPLIANCE AND CLOSEOUTCLOSEOUTMANUFACTURER'S WARRANTYOPERATING INSTRUCTIONS

REQUIRED SUBMITTAL

DATE

DATE

RECEIVED

IN

CONTRACTING DATE

TO

CIVIL

ENGR. RETURN

SUSPENSE

DATEFOLLOW-UPDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL
APPROVALREMARKS
APPROVEDDISAPPROVED
1time ScheduleNTP +210
2Progress reportsMonthly
3List of Valueswith first progress report
4Dailey reportsweekly
5Closeout ReportBefore final inspection
6List of proposed subcontractosNTP +180
7List of proposed productsNTP +180
8bid documents (Drawing and specs)NTP +180
9submittal reginsterNTP +180
10health and safety planNTP +180
11Work and Demolition planNTP +180
12AF Form 3064 & 3065 & 3052NTP +180
13Quality Control planNTP +180
14Environmental protection planNTP +180
15Storm water Pollution Prvention planNTP +180
16Storm Water Notice of IntentNTP +180
17Existing Conditions( Photographs and field Verification Sign-offNTP +180
1830% Design SubmittalNTP+45
1930% Design Submittal Meeting MinutesNTP+73
2060% Design SubmittalNTP+90
2160% Design Submittal Meeting MintuesNTP+118
22100% Design SubmittalNTP+135
23100% Design Submittal meeting MinutesNTP+163
24100% Corrected Design SubmittalNTP+180
25Material SubmittalsNTP+210
26As-builtsNTP+480
27WarrantiesNTP+480
28Operations and Maintenance ManualsNTP+480
29Request for Final InspectionNTP+450
30Systems Functional Test ReportNTP+480
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
NOTE: This Submittal Schedule is for the Contractor's use in assembling and organizing the Submittals to be made to the Government. See individual specification sections for possible additional submittal requirements.
LEGEND:
A - Include with line 9 Operations and Maintenance Manual
B - Include with line 10 Warranty Book
C - Include with line 14 Color Samples

FA4600-11-B-0025

Attachment 3 Page &P

FA4600-11-B-0025

Attachment 3 Page &P

1B-&P

File details come from the government source that posted it. Updated .