This Quality Assurance Surveillance Plan (QASP) outlines the government's systematic method for monitoring and evaluating contractor performance across multiple service and reporting requirements. The document establishes detailed performance standards and acceptable quality levels for various tasks, including reports (such as availability reports, sales reports, and marketing reports), inspections (like country of origin compliance, availability checks, and pricing verification), and deliveries. The Contracting Officer's Representative (COR) will conduct periodic and random inspections using different frequencies (daily, monthly, quarterly, bi-weekly) to ensure 95-100% compliance across different performance metrics.

The QASP includes specific consequences for unsatisfactory performance, such as potential contract termination, loss of future government contracts, and non-exercise of contract options. If performance falls below acceptable levels, the government may issue a Contract Discrepancy Report (CDR), requiring the contractor to respond within three days with explanations and corrective actions. For firm-fixed-price delivery orders, contractors are incentivized to provide quality products timely, as the government can require replacement or correction of work at no additional cost if contract requirements are not met. The document emphasizes comprehensive documentation, with all quality assurance records to be retained for the contract's duration and used in annual performance assessments.

View the file

Other files

File Type Posted
N0018925R00430020.pdf PDF
Norfolk Super Servmart N0018925R0043 Remaining Question and Answer.pdf PDF
N0018925R00430019.pdf PDF
Att 05 Test Market Basket v5.xlsx XLSX spreadsheet
Norfolk Super Servmart N0018925R0043 Remaining Questions and Answers.pdf PDF
N0018925R00430018.pdf PDF
N0018925R00430017.pdf PDF
N0018925R00430016.pdf PDF
N0018925R00430015.pdf PDF
Norfolk Super Servmart N0018925R0043 Questions and Answers.pdf PDF
N0018925R00430014.pdf PDF
Att 05 Test Market Basket v3.xlsx XLSX spreadsheet
N0018925R00430013.pdf PDF
N0018925R00430012.pdf PDF
N0018925R00430011.pdf PDF
N0018925R004300010.pdf PDF
N0018925R00430009.pdf PDF
N0018925R0043 Questions and Answers.docx DOCX document
N0018925R00430008.pdf PDF
N0018925R0043 Questions and Answers.docx DOCX document
Att 05 Test Market Basket v2.xlsx XLSX spreadsheet
N0018925R00430007.pdf PDF
N0018925R004300006.pdf PDF
N0018925R004300005.pdf PDF
N0018925R004300004.pdf PDF
N0018925R004300003.pdf PDF
Att 11 SECNAV 5512 Form.pdf PDF
Att 12 ODP FOR SPONSORS Form.xlsx XLSX spreadsheet
N0018925R004300002.pdf PDF
N0018925R004300001.pdf PDF
Questions and Answers.pdf PDF
Att 3 Prohibited Items Listing.pdf PDF
Att 4 On-Site Items.pdf PDF
Att 7 Past Performance Information Form.docx DOCX document
Att 9 Contract Administration Plan.pdf PDF
Att 2 Mandatory Items Listing.pdf PDF
Att 6 Contractor Discrepancy Report.pdf PDF
Att 8 Past Performance Report Form.docx DOCX document
Att 1 Shopping Procedures.pdf PDF
RFP N0018925R0043.pdf PDF
Att 5 Test Market Basket.xlsx XLSX spreadsheet
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUALITY ASSURANCE SURVEILLANCE PLAN AND MATRIX

1. PURPOSE: This Quality Assurance Surveillance Plan (QASP) is a Government-developed and applied document used to make sure that systematic quality assurance methods are used in the administration of this performance-based service contract and in subsequent orders issued thereunder. The intent is to ensure that the contactor performs in accordance with performance metrics set forth in the contract documents, that the Government receives the quality of services and supplies called for in the contract, and that the Government only pays for the acceptable supplies received. The QASP will be used primarily as a tool to verify that the contractor is performing all services required by the PWS in a timely, accurate, and complete fashion.

2. SCOPE: The QASP is put in place to provide Government surveillance oversight of the contractor’s quality control efforts to assure that they are timely, effective, and are delivering the results specified in the contract or delivery orders. The QASP is not intended to duplicate the contractor’s management plan.

3. PERFORMANCE STANDARDS

a. Schedule - The due dates for deliverables and the actual accomplishment of the schedule will be assessed against original due dates and milestones established for the contract or delivery orders.

b. Deliverables – The deliverables required will be assessed against the specifications for the deliverables detailed in the contract and delivery orders for the required content, quality, timeliness, and accuracy.

c. Past Performance - In addition to any schedule and deliverable aspects of performance discussed above, pursuant to FAR 42.15, the Government will assess the contractor’s record of conforming to contract requirements and to standards of good workmanship, the contractor’s adherence to contract schedules including the administrative aspects of performance, the contractor’s history of reasonable and cooperative behavior and commitment to customer satisfaction, and the contractor’s business-like concern for the interest of the customer.

4. METHODS OF SURVEILLANCE: The primary methods of surveillance used to monitor performance of this contract will include, but not be limited to, random or planned sampling, periodic or complete inspection, and customer feedback. Each phase of the services rendered under the contract is subject to Government inspection during the contractor’s operations and after completion of a task or delivery. Inspections may be routine functions performed by the Contracting Officer’s Representative (COR), or performed by others outside of the command. The contractor shall not substitute Government inspection for effective quality control. Government inspections may be conducted in an unannounced manner by the COR or other individuals designated outside the organization.

5. PERFORMANCE MEASUREMENT AND QASP MATRIX: Performance will be assessed and measured as shown in the QASP Matrix below. If performance is within acceptable levels, it will be considered to be satisfactory. If not, overall performance may be considered unsatisfactory.

Task Performance Requirement

Assessment Method and Frequency

Sample Size Acceptable

Quality Level

REPORTS

97% Availability Report per PWS 11.0(a)

Meets all PWS requirements

Random inspection by COR All 95% accuracy and timeliness

100% Availability Report per PWS 11.0(b)

Meets all PWS requirements

Random inspection by COR All 95% accuracy and timeliness

Monthly Sales & Transactions per PWS 11.0(c)

Meets all PWS requirements

Monthly inspection by COR All 95% accuracy and timeliness

Quarterly List Price Validation Analysis per PWS 11.0(d)

Meets all PWS requirements

Quarterly inspection by

COR

All 95% accuracy and timeliness

Command Metric Call per PWS 11.0(e)

Meets all PWS requirements

Random inspection by COR All 95% accuracy and timeliness

Bi-weekly Situation Summary per PWS 11.0(f)

Meets all PWS requirements

Bi-weekly inspection by

COR

All 95% accuracy and timeliness

Marketing Report per PWS 11.0(g)

Meets all PWS requirements

Monthly inspection by COR All 95% accuracy and timeliness

Monthly Sales Report per PWS 11.0(h)

Meets all PWS requirements

Monthly inspection by COR All 95% accuracy and timeliness

Top 200 Sales Report per PWS 11.0(i)

Meets all PWS requirements

Quarterly inspection by

COR

All 95% accuracy and timeliness

INSPECTIONS

Country of origin compliance checks per

PWS 2.2

Meets all contract requirements

Random/monthly inspection by the COR

Determined by

COR

100% compliance

Availability Inspection per PWS 3.0

Meets all PWS requirements

Random/monthly inspection by COR

Determined by

COR

97% compliance

Availability of Mandatory Items Listing per PWS 3.0

Meets all PWS requirements

Random/monthly inspection by COR

Determined by

COR

98% compliance

Bin label maintenance (green labels for mandatory items) per PWS 5.0(m)

Meets all PWS requirements

Random/monthly inspection by COR

Determined by

COR

98% compliance

Customer service desk manning per PWS 5.0(n)

Meets all PWS requirements

Random/daily inspection by

COR

Determined by

COR

98% compliance

AbilityOne/UNICOR exclusive items per

PWS 7.0

Meets all PWS requirements

Random and quarterly inspection by COR

Determined by

COR

99% compliance

Pricing AbilityOne Pricing per

PWS 3.4 &

7.0(g)

Priced in accordance with the contract

Periodic/quarterly/customer feedback inspection by COR

All 100% compliance

Commercial, GSA, DLA, and UNICOR Pricing per PWS 3.4

Compliance with contractor’s catalogs and discount and/or mark-up rates incorporated into the contract at time of award

Periodic/quarterly/customer feedback inspection by COR

All 100% compliance

Deliveries Delivery service (walk-in store) for customers located at Naval Station Norfolk per PWS 10.0

Meets all PWS requirements

Random/monthly inspection by COR

Determined by

COR

95% compliance

Delivery service (walk-in store) for customers located within the Virginia Hampton Roads area (not on Naval Station Norfolk) and for all special orders and e-commerce orders per PWS 10.0

Delivery in accordance with established timeframes

Random/monthly inspection by COR

Determined by

COR

95% compliance

Fire Extinguisher Inspection per PWS 4.0(l)

Completed inspection Monthly inspection by COR All 95% compliance

Provide a CD of the Meets all PWS Periodic/monthly inspection Determined by 95% compliance walk-in store catalog per PWS 2(e) requirements by COR COR

Combating Trafficking in Persons Training

(FAR 52.222-50)

The contractor shall ensure compliance with

FAR 52.222-50.

The Contracting Officer will review as needed.

All 100% Compliance

NAVSUP Mandatory Training

The contractor shall ensure compliance with All NAVSUP Mandatory Training.

Annual inspection by COR All Employees 100% Compliance

6. DOCUMENTATION: The COR will, in addition to providing documentation to the Contracting Officer, maintain a complete quality assurance file. All such records will be retained for the life of the contract. Information in the quality assurance file will be considered when completing the annual Contractor Performance Assessment Reporting System (CPARS) report.

7. INCENTIVES/DISINCENTIVES: The COR makes an annual report on contractor performance (CPARS or other annual report). The contractor’s failure to achieve satisfactory performance under the contract and/or delivery orders, reflected in the COR’s annual report, may result in termination of the contract and may also result in the loss of future Government contracts and/or task and delivery orders. The contractor’s failure to achieve satisfactory performance under the contract and/or delivery orders may result in the non-exercise of available options.

For each item that does not meet acceptable levels, the Government may issue a Contract Discrepancy Report (CDR). CDRs will be forwarded to the Contracting Officer with a copy sent to the contractor. The contractor must reply in writing within three days of receipt identifying the reason(s) for unsatisfactory performance and corrective action(s) to be taken, and how future occurrences of the problem will be prevented. Based upon the contractor’s past performance and plan to solve the problem, the Contracting Officer will determine if any further action will be taken.

For firm-fixed-price delivery orders, in accordance with the inspection provisions of the contract, the contractor will be incentivized to provide quality products in a timely manner since the Government can require the contractor, at no additional cost, to replace or correct work that fails to meet contract requirements.

File details come from the government source that posted it. Updated .