This is an Inspection and Flow Test report for fire hydrants at Nellis Air Force Base, specifically documenting the annual inspection and testing of Fire Hydrant #BLDG 10440 located in Area II Building 10440. The inspection was conducted by MR. Max McIntyre on 4 MAR 2025 and follows guidelines established under Unified Facilities Criteria (UFC) 3-600-02 and National Fire Protection Association 25 standards.
The dry hydrant inspection verified accessibility, leaks, worn threads, proper functioning, drainage of barrel, and lubrication. The yard monitor nozzles and hose houses were inspected for condition, accessibility, and operational status. The flow test results indicate a static pressure of 30 psig at the primary location and 30 psig at the secondary location. The hydrant manufacturer is Mueller with outlet size coefficient 375. Flow testing recorded 229 GPM at 20 PSI residual pressure and 414 GPM at 0 PSI residual pressure. The pitot pressure reading was 375, and the total flow during test was 375 GPM. All inspection checklist items (A-1.0 through D-1.9) were marked as completed with "X" marks, including verification that the hydrant was left in service. The report includes a pressure versus flow graph displaying the hydrant's performance curve based on the recorded measurements.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Y N/A N Y N/A N
A-1.0 D-1.0
A-1.1 X D-1.1 X
A-1.2 X
A-1.3
D-1.3 X A-1.4 X
B-1.0
B-1.1 X
B-1.2
B-1.3 X
C-1.0
C-1.1 X
C-1.2 X
D-1.9 Hydrant left in Service X
10440
2.5
GPM
Inspector's Initial __________
INSPECTION AND FLOW TEST
Fire Hydrants
The Following inspection and flow testing tasks are to be performed on an ANNUAL basis. These tasks are guidelined under the Unified Facilities Criteria (UFC) 3- 600-02 and National Fire Protection Assocation 25
ALL QUESTIONS ARE TO BE FULLY ANSWERED AND ALL BLANKS TO BE FILLED
LOCATION/BUILDING NUMBER:
Inspector Name: MR. Max McIntyre
Fire Hydrant # BLDG 10440
Inspection of Dry Hydrant: Flow Testing Hydrant:
Inspected for accessibility, leaks, and worn threads Attached pressure gauge to outlet STATIC
Operated to ensure proper functioning D-1.2 Attached pressure gauge to adjacent hydrant and take reading (should be the same) X
Verified drainage of barrel (after all operations and before cold weather) X
Attached diffuser to hydrant being tested Lubricated Hydrant to ensure ease of operation D-1.4
Completely opened hydrant, took and recorded a pitot reading X
Inspection of Yard Monitor Nozzles: D-1.5 Took and recorded the residual pressure on the hydrant cap gauge X
Inspected for condition
Conducted flow test to verify proper function and range of motion X
D-1.6 Took and recorded the residual pressure at the secondary location X
Lubricated to ensure proper operating conditions D-1.7 Closed the hydrant slowly being careful not to cause a "water hammer" and spike the pressure above the normal static pressure on the gauge at the secondary location X
Inspection of Hose Houses:
Inspected for accessibility and condition D-1.8 Verified that all valves closed properly, are not seeping or leaking X
Verified inventory and its condition
AREA II BLDG. 10440
0.9
YEAR 5
WATER FLOW TEST RECORD
WFSM Shop 652-4815
Nellis AFB 99th CES
STATIC PRESSURE
HYDRANT NUMBER PITOT PRESSURE
MANUFACTURER
TOTAL FLOW DURING TEST
Date: ____________________
WATER FLOW GPM
AT 0 PSIAT 20 PSI RESIDUAL
GPM414229
(All "NO" answers to be fully explained.)
MUELER
Date Scheduled: Date Completed: 4 MAR 2025
RWP Number:
OUTLET
SIZE COEFFICIENT SIZE
NO. 375
RESIDUAL PRESSURE PRIMARY RESIDUAL PRESSURE SECONDARY
0 500
Pr es su re
, p si g
Flow, gpm
Data
File details come from the government source that posted it. Updated .