Appendix G - Jones Hall B6902 DD Form 1391.pdf

PDF 321 KB Posted

Attached to
RFQ for Title II for Repair Jones Hall at Keesler AFB
Solicitation number
FA890326R0069
Issued by

About this file

This is a DD Form 1391 (FY 2023 Project Data) prepared by the Air Education and Training Command (AETC) for a military construction repair project at Keesler Air Force Base, Mississippi.

The project involves comprehensive repair and modernization of Jones Hall Building 6902, a training facility built in 1962 that houses the 338th Squadron and ten cyber classes serving approximately 585 students. The total project cost is $49,650,000, with execution planned for FY 2025 using a Design Bid Build approach. The work scope includes repairing the substructure, building shell, and interiors; replacing HVAC systems with improved temperature and humidity controls; upgrading plumbing fixtures, fire alarms, and fire suppression systems; installing new electrical and communications wiring; replacing roof and exterior doors; modernizing classroom finishes including carpeting, acoustical ceilings, and lighting; and removing existing chilled water and air handling systems with modern Direct Digital Controls. Cost estimates are based on 95 percent complete design as of 2025, with a 16.03 percent escalation factor applied to reflect December 2026 construction midpoint pricing. Supporting facility repairs include site preparations, improvements, civil/mechanical utilities, and post-construction award services totaling $607,000. The project includes sustainability measures (1 percent), cyber security upgrades (2.5 percent), a 6.5 percent Supervision, Inspection, and Overhead cost, and a temporary facilities allowance. The repair-to-replacement ratio of 43.48 percent indicates this repair project costs approximately 40 percent of the estimated $114,202,487 full facility replacement cost. USACE has been designated as the execution agent. The design shall conform to Air Force Corporate Facilities Standards, Installation Facilities Standards, and DoD Unified Criteria. Compliance with seismic, antiterrorism, fire protection, economic analysis, and floodplain management rules has been assessed and documented.

View the file

Other files

File Type Posted
SOW_Title_II_09022026.pdf PDF
Appendix A - Air Force Facilities Sustainability Requirements Scoresheet.xlsx XLSX spreadsheet
Appendix M - Arnold Hall B5901 Restroom As-Builts.pdf PDF
Appendix P - Arnold Hall B5901 Asbestos Inspection Report.pdf PDF
Appendix A - Air Force Facilities Sustainability Requirements Scoresheet.xlsx XLSX spreadsheet
Appendix H - Jones Hall RLF Drawings Vol 1 of 2.pdf PDF
Appendix I - Jones Hall B6902 As-Built.pdf PDF
Appendix J - Jones Hall B6902 100 percent Specifications.pdf PDF
Appendix C - Keesler AFB Installation Facilities Standards (IFS).pdf PDF
Appendix D - Keesler AFB Premise Wiring Guidance.pdf PDF
Appendix E - SWPPP Guidance Manual.pdf PDF
Appendix H - Jones Hall SID Binder.pdf PDF
Appendix H - Jones Hall AFB Drawings Vole 2 of 2_optimized.pdf PDF
Appendix L - Arnold Hall B5901 Drawings.pdf PDF
Appendix N - Arnold Hall B5901 Specifications.pdf PDF
Appendix O - Arnold Hall B5901 Hazardous Material Survey.pdf PDF
RFQD-TII-Jones Hall - 17 Jun 2026.pdf PDF
Appendix B - Air Force Sustainable Design and Development (SDD) Implementing Guidance.pdf PDF
Appendix F - Keesler Architectural Compatibility Guide (ACG).pdf PDF
Appendix K - Jones Hall B6902 Hazardous Material Survey.pdf PDF
Appendix Q - Jones Hall B6902 Hazardous Materials Report.pdf PDF
Appendix R - Premise Wiring Guidance.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DD FORM 1391, DEC 99 Previous editions are obsolete Page No

1. COMPONENT

AETC

FY 2023 PROJECT DATA

2. DATE

08 DEC 25

3. INSTALLATION AND LOCATION

KEESLER AIR FORCE BASE

KEESLER AFB SITE #1

MISSISSIPPI

4. PROJECT TITLE:

REPAIR JONES HALL B.6902

5. PROGRAM ELEMENT

22178F

6. CATEGORY CODE

171-623

7. PROJECT NUMBER

MAHG121033

8. PROJECT COST ($000)

$49,650

9. COST ESTIMATE

ITEM UOM QTY UNIT

COST

COST ($000)

PRIMARY FACILITIES

REPAIR

SUBSTRUCTURE SF 102,000 $50 $5,100

BUILDING SHELL SF 102,000 $59 $6,018

BUILDING INTERIORS SF 102,000 $65 $6,630

BUILDING SERVICES (MEP) SF 102,000 $160 $16,320

EQUIPMENT & FURNISHINGS SF 102,000 $0.60 $61

SPECIAL CONSTRUCTION & DEMOLITION SF 102,000 $38 $3,876

SUSTANABILITY/ENERGY MEASURES (1%) LS $380

GENERATOR BUILDING SF 819 $350 $287

TEMPORARY FACILITIES (RLF) LS $6,219

CYBER SECURITY (2.5%) LS $1,122

Total Primary Facility Repair Cost $46,013

SUPPORTING FACILITIES

REPAIR

SITE PREPARATIONS LS $85

SITE IMPROVEMENTS LS $202

SITE CIVIL/MECHANICAL UTILITIES LS $32

POST CONSTRUCTION AWARD SERVICES LS $288

Total Supporting Facility Repair Cost $607

Sub Total REPAIR $46,620 Contingency (10% Include in above) $0

SIOH (6.5%) $3,030

TOTAL REPAIR $49,650

TOTAL PROJECT COST [match block 8] $49,650

This project will be executed as a Design Bid Build project. Project under design.

This estimate is based on a 95% complete design as of 2025.

Note: This project is planned for execution in FY 2025. Costs as shown represent an escalation factor of 16.03% based on DoD’s Building Cost Index dated December 2024 from January 2024 costs to a December 2026 construction mid-point.

DD FORM 1391, DEC 99 Previous editions are obsolete Page No

KEESLER AIR FORCE BASE

KEESLER AFB SITE #1

MISSISSIPPI

4. PROJECT TITLE:

REPAIR JONES HALL B.6902

5. PROGRAM ELEMENT

22178F

6. CATEGORY CODE

171-623

7. PROJECT NUMBER

MAHG121033

8. PROJECT COST ($000)

$49,650

10. DESCRIPTION OF PROPOSED WORK: REPAIR

Repair finishes, replace roof, patch and paint exteriors, repair elevators, HVAC, plumbing fixtures, fire alarms, fire suppression, replace comm wiring and electrical in the entire facility. Remove and replace existing chill water pump and piping; return and make-up air dampers for air handling units; supply and return ducts, registers, and grilles to match existing interior layout of the building. Install re-heat piping, VAV boxes, and Direct Digital Controls to provide adequate temperature and humidity conditions to standards. Replace existing exterior doors to seal facility envelope. Rework all bathroom facilities, replace interior finishes, including carpeting where necessary, acoustical ceilings, lighting fixtures and electrical supply for technical classrooms. Facility is a permanent constructed facility and will comply with the DoD Unified Criteria (UFC) 1-200-01, General Building Requirements.

Sustainable principles, to include life cycle cost-effective practices, will be integrated into the design development, and construction of the project in accordance with UFC 1-200-02.

11. REQUIREMENT

A facility that promotes efficient educational training. Jones Hall is a training facility and acts as a shelter during emergencies. The facility must provide sufficient conditioned space to accomplish training mission as well as modernize classrooms to promote cutting edge student lead learning programs. The space must be climatically conducive to learning and must support heat sensitive equipment, including, CPUs, Laptops, printers, monitors and other heat sensitive equipment. Repairs to the facility are not tenant driven but will comply with AFI32-1020.

CURRENT SITUATION & IMPACT

Building 6902 was built in 1962 and has had no new renovations performed. It is primarily cinder block walls with 10' and 12' ceilings throughout. It has major electrical troughing run along the walls and has mainly VCT or VAT floors and raised floors in some locations. The doors all have 3' transoms above them and the classroom space is primarily as it was when built. Some classrooms have been carved into office space for teachers and are poorly configured. The HVAC systems are generally as originally installed and air movement, humidity controls, and temperature controls are very ineffective. Block walls are primarily painted with traces of mold and pealing paint evident. While there have been some recent renovations to some of the restrooms these are insufficient to provide adequate facilities to the student population. Additionally the renovations were primarily cosmetic and changes should be performed to bring the existing facilities up to standards. The facility currently houses the 338th which teaches 10 Cyber classes. When system failures occur it impacts up to 585 students. HVAC lacks effective humidity controls, combined with exterior leaks creates high humidity and mold growth. A third party survey located mold spores at 28 locations amd a July 2019 Air Survey detected high levels of CO2. FY17 –FY19 maintenance cost were $159.5k. Facility system failures will continue to affect the student Airmen education. To replace the entire facility, construction cost is estimated around $37,705,725.

Repairs and renovation to the facility is about 40% of the replacement cost.

PROJECT

This project is to achieve a modern and updated facility to promote learning and training for student airmen all year long. The students located in this facility must be provided with an area to properly train with secure activities. The improved facility will also be able to handle an increased student population which was significantly different when the facility was first constructed in 1962.

ADDITIONAL

PROJECT COST: $49,650

SOURCE OF FUNDS: O&M

CONSTRUCTION AREA COST FACTOR: 1.00

PRICING DATA SOURCE: RS Means Cost Database 2022

EXECUTION AGENT: USACE

ESTIMATED MILCON REPLACEMENT COST: $114,202,487

REPAIR-TO-REPLACEMENT RATIO: $49,650/$114,202.49 =43.48%

REPAIR-TO-REPLACEMENT RATIO:

The total funded cost of $49.65 is 43.48% of the $114,202.49M estimated cost of a MILCON project to replace the facility.

DD FORM 1391, DEC 99 Previous editions are obsolete Page No

KEESLER AIR FORCE BASE

KEESLER AFB SITE #1

MISSISSIPPI

4. PROJECT TITLE:

REPAIR JONES HALL B.6902

5. PROGRAM ELEMENT

22178F

6. CATEGORY CODE

171-623

7. PROJECT NUMBER

MAHG121033

8. PROJECT COST ($000)

$49,650

COMPLIANCE STATEMENTS

SEISMIC RULE:

Compliance with the seismic 30% repair-to-replacement ratio is not required. The scope of this project complies.

Compliance with the seismic 50% repair-to-replacement ratio is not required. The scope of this project complies.

ANTITERRORISM (AT) RULE:

Compliance with the AT 50% repair-to-PRV ratio is not required.

FIRE PROTECTION RULE:

Compliance with the 50% Fire Protection Rule is not required.

ECONOMIC ANALYSIS (EA) RULE:

This project’s programmed amount does not exceed both $2M and 75% of the estimated cost of a military construction project to replace the facility, therefore an economic analysis of alternatives is not needed.

FLOODPLAIN MANAGEMENT RULE:

This project does not fall within or partly within a 100-year flood plain.

STANDARD DESIGN:

This design shall conform to criteria established in the Air Force Corporate Facilities Standards (AFCFS), the Installation Facilities Standards (IFS), and shall employ the standard facility design.

RENTED OR LEASED FACILITY:

The facility in this project is not a rented or leased facility.

CERTIFICATION: I have reviewed this document and certify it is complete and accurate, and is compliant with appropriate statute(s) and instructions. I have validated the project’s primary and supporting costs and work classification. It has been fully coordinated with the user and other appropriate agencies and approved by the Installation Facility Board.

Christina Castleberry, PE Deputy Base Civil Engineer 81st Civil Engineer Squadron, Keesler AFB

(228) 377-9019

2025-12-08T16:40:03-0600