Appendix_6-003876A-UWS-004183A_Group_2.pdf

PDF 3 MB Posted

Attached to
Countywide Mast Arms - Group 2
Solicitation number
23-0211-ITB-CP
Issued by
Pinellas County, Florida

About this file

This document is a Utility Work Schedule (UWS) for Pinellas County, Florida, involving multiple utility agencies/owners (UAOs) for the Mast Arm Signalization project at 49th Street N and 70th Avenue N, with County Project #003876A. The utility agencies involved include Duke Energy Florida, Frontier Communications, Teco Peoples Gas, Zayo, and MCI Metro Access Transmission Services LLC. The project involves utility relocation, adjustment, installation, and protection activities to support roadway construction, with work primarily focused on relocating existing utility infrastructure, placing conduits, removing and replacing fiber optic cables, and preparing for mast arm foundation installation.

The utility work schedules detail specific requirements for each utility agency, including work durations, station/offset locations, and special conditions. Most agencies have minimal non-construction time and relatively short construction periods ranging from 0-7 days. Each utility agency has unique constraints, such as MCI's request for a 72-business-hour pre-construction notice, Frontier's requirement for 48-hour advance notification, and Zayo's need for extreme caution when working near their facilities. The documents are dated between November 2019 and July 2022, with final acceptance dates in 2022, indicating a coordinated approach to utility management for the intersection improvement project.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Jared Knight

Transportation Engineer

4/15/2022 5/9/2022

Page 1 of 3 PINELLAS COUNTY 11/19//2019

UTILITY WORK SCHEDULE

COUNTY PROJECT #: 003876A PROJECT TITLE: 49th ST N @ 70th AVE N

UTILITY AGENCY/OWNER (UAO): FRONTIER COMMUNICATIONS

A. Summary of Utility Work and Execution

NON-CONSTRUCTION ITEMS ESTIMATED *CALENDAR

DAYS

CONSTRUCTION ITEMS ESTIMATED *CALENDAR

DAYS

Total Preliminary 0 Prior to Pinellas County Project Construction 0 Total Material Procurement 0 During Pinellas County Project Construction 5 Total Right-of-Way Permitting 0 Total NON-Construction Time 0 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.

The following data is based on Pinellas County final design phase construction plans dated 10/11/2021. Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.

UAO Project Representative: Granville Stephens Telephone Number: 727-503-6081 UAO Field Representative: David West Telephone Number: 727-253-1872

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:

(Signature) (Signature) (Signature)

Granville Stephens Tim Messina (Printed Name) (Printed Name) (Printed Name)

Network Enginer,SR Utility Coordinator (Title) (Title) (Title)

11/15/2021 (Date) (Date) (Date)

(Signature)

Jared Knight

Transportation Engineer

4/15/2022 g

5/9/2022

Page 2 of 3 PINELLAS COUNTY 11/19//2019

COUNTY PROJECT #: 003876A PROJECT TITLE: 49th ST N @ 70th AVE N

UTILITY AGENCY/OWNER (UAO): FRONTIER COMMUNICATIONS

B. Special Conditions / Constraints

1. Frontier and Frontier Contractor's normal business hours are from 8am to 5pm, Monday through Friday (excluding Holidays).

2. Any work outside of normal business hours to be scheduled a minimum of 72 hours in advance.

3. The road Contractor is to notify Frontier at 813-486-4650 48 hours prior to start of construction.

4. Extreme caution is to be used when excavating near or around Frontier facilities.

5. Frontier inspector is to be the point of contact during construction and to be notified when working within 2' of Frontier facilities.

6. Frontier is to have access throughout the duration of the project to monitor and maintain facilities for the ability to provide service.

Page 3 of 3 PINELLAS COUNTY 11/19//2019

COUNTY PROJECT #: 003876A PROJECT TITLE: 49th ST N @ 70th AVE N

UTILITY AGENCY/OWNER (UAO): FRONTIER COMMUNICATIONS

SECTION C: UAO’s WORK ACTIVITIES

Consecutive DaysAction

Utility Facility (Type, Size, Material, Status)

From Station/ Offset

To Station/ Offset

Utility Work Description Dependent Activity TCP Phase Prior To During

1 50PR BT/PED NE

Corner MAST ARM DURING

CONSTRUCTION 0 5

Page 1 of 3 Pinellas County

December 14, 2016

PINELLAS PROJECT INFORMATION

Project ID: 0 0 3 8 7 6 A Federal Project ID: n/a Road Number: 4 9 T H S T N Intersecting Road 70TH AVE N

Plans Dated: 1 0 / 1 1 / 2 0 2 1 District Document No.: n/a

UTILITY AGENCY/OWNER (UAO)

Utility Company: Teco Peoples Gas UAO Project Rep: Bolivar A. Feliz Nunez Phone: 813-275-3712 E-mail: Bafeliznunez@tecoenergy.com UAO Field Rep: Raymond Zwissler Phone: 727-423-7124 E-mail: Rszwissler@tecoenergy.com

UTILITY SIGNATURE

I have reviewed the Pinellas plans referenced above and submit this utility work schedule.

UAO Rep. Bolivar A. Feliz Nunez Name Title Gas Design Tech I

Date 1 0 / 14 / 2021

ENGINEER OF RECORD SIGNATURE

I attest this utility work schedule is compatible with the Pinellas plans referenced above.

EOR.

Name , P.E.

Title Engineer of Record

Date / /

APPROVAL BY DISTRICT UTILITIES

This utility work schedule is complete and acceptable to Pinellas County.

Rep.

Name Title

Date / /

SECTION A: SUMMARY OF UTILITY WORK

The below days are the total numbers of days shown for all activities in Section C of this utility work schedule. The breakdown of how these days are to be incorporated into the Pinellas County project and the dependence of these days upon the completion of other activities by the UAO or others is shown in Section C.

Days prior to project construction: Days during project construction: 10

Jared Knight 4 15 2022

Bollolollolllolllollllolololo ivaivaivaiivaiivaivaiivaiivaivaaivaivaiiivaivaarrrrrrr AAAAAAAAAAAAAA.AAAAAAA lFelFelFelFelFFelFelFelFelF lF lFeFelFelF lF lFeF iiiizizziiizziizzzz NunNunNunNunNunununNunNunnNunNunNunNunununezezezezezzzezezezzezzz Bolivar A. Felix Nunez

5/9/2022 Tim Messina Utilities Coordinator

Page 2 of 3 Pinellas County

December 14, 2016

Project ID: 003876A Utility Company: TECO Peoples Gas Plans Dated: 10/11/2021

SECTION B: UAO SPECIAL CONDITIONS/CONSTRAINTS

1. TECO/PEOPLE GAS REQUEST A COPY OF THE CONTRACTOR’S APROVED CPM SCHEDULE WITHING 5 DAYS OF

APPROVAL.

2. THE TECO PEOPLES GAS 24-HOUR EMERGENCY NUMBER 1-877 TECO PGS (1-877-832- 6747).

3. TECO PEOPLES GAS CREW AVAILABILITY MAY BE AFFECTED OR LIMITED DUE TO OUR REQUIRED RESPONSE TO EMERGENCY CONDITIONS ELSEWHERE. THIS LIMITATION WILL BE DEPENDENT UPON THE SEVERITY AND LOCATION

OF THE EMERGENCY.

4. TECO PEOPLES GAS SUBCONTRACTORS NORMAL WORK SCHEDULE IS MONDAY THROUGH FRIDAY FROM 8 A.M. TO 5 P.M., EXCLUDING TECO PEOPLES GAS OBSERVED HOLIDAY'S (NEW YEARS DAY, GOOD FRIDAY, MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANKSGIVING DAY, CHRISTMAS EVE DAY AND CHRISTMAS DAY). ANY TECO PEOPLES GAS ASSISTANCE REQUESTED FROM THE FDOT, THEIR CONTRACTOR OR SUBCONTRACTOR OUTSIDE OF THESE NORMAL WORKING HOURS MUST BE SCHEDULED 48 HOURS IN ADVANCE. TECO PEOPLES GAS REQUIRES VERIFICATION THAT THE CREWS ARE STILL NEEDED ON THE ACTUAL WORKDAY (MONDAY THROUGH FRIDAY) THAT HAD PREVIOUSLY BEEN REQUESTED OR THE LAST BUSINESS DAY BEFORE THE REQUESTED

WEEKEND OR HOLIDAY.

Page 3 of 3 Pinellas County

December 14, 2016

Project ID: 003876A Utility Company: TECO Peoples Gas Plans Dated: 10/11/2021

SECTION C: UAO’s WORK ACTIVITIES

Act.

No.

Utility Facility (type, size, material, status)

From Station/ Offset

To Station/ Offset

Utility Work Activity Description

Dependent Activity TCP Phase

Consecutive Calendar Days

Prior to During Const. Const.

1 2” PE GAS MAIN 252.41+48’

RT

252.41+65’

RT

OBSERVATION OF

CONSTRUCTION TO

AVOID DAMAGE TO GAS

N/A N/A 0 1

Page 1 of 3 Pinellas County

December 14, 2016

PINELLAS PROJECT INFORMATION

Project ID: 0 0 3 8 7 6 A Federal Project ID: n/a Road Number: 4 9 t h S t N Intersecting Road 70th Ave N

Plans Dated: 1 0 / 1 1 / 2 0 2 1 District Document No.: n/a

UTILITY AGENCY/OWNER (UAO)

Utility Company: Zayo UAO Project Rep: Matt Richards Phone: 813-587-2584 E-mail: matt.richards@zayo.com UAO Field Rep: Tess Bentayou Phone: 813.363.6797 E-mail: tess.bentayou@zayo.com

UTILITY SIGNATURE

I have reviewed the Pinellas plans referenced above and submit this utility work schedule.

UAO Rep.

Name Tess Bentayou Title OSP PM CFL

Date / /

ENGINEER OF RECORD SIGNATURE

I attest this utility work schedule is compatible with the Pinellas plans referenced above.

EOR.

Name Jared Knight , P.E.

Title Engineer of Record

Date / /

APPROVAL BY DISTRICT UTILITIES

This utility work schedule is complete and acceptable to Pinellas County.

Rep.

Name Title

Date / /

SECTION A: SUMMARY OF UTILITY WORK

The below days are the total numbers of days shown for all activities in Section C of this utility work schedule. The breakdown of how these days are to be incorporated into the Pinellas County project and the dependence of these days upon the completion of other activities by the UAO or others is shown in Section C.

Days prior to project construction: 3 Days during project construction: 0

4 15 2022

TTTTTTTTTTTTTTTTTTTTTessessessessessesessessessessessessessessessessesesessess BeBeBeBeBeBeBeBeBeBeBeBeBeBeBeBeBeBeBeBeBentantantantantantantantantantantantantantantantantantatataayouyouyouyouyouyouyouyouyouyoyouyouyoyouyouyoyouyouooy

4 15 22

Tim Messina Utilities Coordinator

5/9/2022

Page 2 of 3 Pinellas County

December 14, 2016

Project ID: 003876A Utility Company: Zayo Plans Dated: 10/11/2021

SECTION B: UAO SPECIAL CONDITIONS/CONSTRAINTS

Contact Tess Bentayou at 813.363.6797 48 hours prior to construction.

Zayo requests access to their facilities during construction.

Zayo requests a copy of the Roadway Contractor’s Approved Work Schedule Extreme caution should be exercised when working near Zayo facilities.

Page 3 of 3 Pinellas County

December 14, 2016

Project ID: 003876A Utility Company: Zayo Plans Dated: 1 0 / 1 1 / 2 0 2 1

SECTION C: UAO’s WORK ACTIVITIES

Act.

No.

Utility Facility (type, size, material, status)

From Station/ Offset

To Station/ Offset

Utility Work Activity Description

Dependent Activity TCP Phase

Consecutive Calendar Days

Prior to During Const. Const.

1 (3) 1-1/4” HDPE DUCTS E/W

288CT FOC

250+85/47.5’

RT

254+40/50.2’

RT

Place via Directional Bore None N/A 2 0

2 (1) 24”X36”X30” HH 252+35’/47.5’

RT

252+35’/47.5’

RT

Place Handhole None N/A 1 0

Page 1 of 3 PINELLAS COUNTY 07/20//2022

COUNTY PROJECT #: 003876A PROJECT TITLE: MAST ARM HARDENING

UTILITY AGENCY/OWNER (UAO): MCI METRO ACCESS TRANSMISSION SERVICES LLC.

A. Summary of Utility Work and Execution

NON-CONSTRUCTION ITEMS ESTIMATED *CALENDAR

DAYS

CONSTRUCTION ITEMS ESTIMATED *CALENDAR

DAYS

Total Preliminary 0 Prior to Pinellas County Project Construction 0 Total Material Procurement 0 During Pinellas County Project Construction 7 Total Right-of-Way Permitting 0 Total NON-Construction Time 0 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.

The following data is based on Pinellas County final design phase construction plans dated 10/11/2021 . Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.

UAO Project Representative: ANDREW COLE Telephone Number: 813-847-4037 UAO Field Representative: TONY WHEELER Telephone Number: 727-359-1754

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:

Andrew Cole (Signature) (Signature) (Signature)

ANDREW COLE

(Printed Name) (Printed Name) (Printed Name)

ENG II

(Title) (Title) (Title)

07/28/2022 (Date) (Date) (Date)

Daniel Torres

Utility Coordinator

9/6/2022

Jared Knight

Transportation Engineer

8/15/2022

Page 2 of 3 PINELLAS COUNTY 07/20//2022

COUNTY PROJECT #: 003876A PROJECT TITLE: MAST ARM HARDENING

UTILITY AGENCY/OWNER (UAO): MCI METRO ACCESS TRANSMISSION SERVICES LLC.

B. Special Conditions / Constraints

1. MCI REQUESTS A 72 BUSINESS HOUR PRE-CONSTRUCTION NOTICE WITH THE CONTACT INFORMATION FOR THE BID-AWARDED CONSTRUCTION COMPANY TO ALLOW MCI TO HAVE TIME TO SHARE SAID CONTACT INFORMATION WITH MCI’S CONTRACTING TEAM TO

ESTABLISH COMMUNICATION.

2. PLEASE PROVIDE THE NOTICE TO ANDREW COLE – ANDREW.COLE2@VERIZON.COM

Page 3 of 3 PINELLAS COUNTY 07/20//2022

COUNTY PROJECT #: 003876A PROJECT TITLE: MAST ARM HARDENING

UTILITY AGENCY/OWNER (UAO): MCI METRO ACCESS TRANSMISSION SERVICES LLC.

SECTION C: UAO’s WORK ACTIVITIES

Action

Utility Facility (Type, Size, Material, Status)

From Station/ Offset

To Station/ Offset

Utility Work Description Dependent Activity TCP Phase

Consecutive Days

Prior To During

MCI – (2) 2” HDPE

CONDUITS -

EXISTING

250+80 RT 254+100

RT

MCI IS TO REMOVE FOC AND PLACE CONDUIT OOS.

MCI IS THEN TO PLACE (2) 2” HDPE CONDUITS OUT OF

CONFLICT BY DIRECTIONAL BORE

MAST ARM FOUNDATION

PID 003876A 1 0 7

File details come from the government source that posted it. Updated .