Appendix_1-Permits-004183A_Group_2.pdf

PDF 130 KB Posted

Attached to
Countywide Mast Arms - Group 2
Solicitation number
23-0211-ITB-CP
Issued by
Pinellas County, Florida

About this file

This document is an Appendix 1 Permits Index for the Pinellas County "Countywide Mast Arms - Group 2" infrastructure project, specifically addressing permit requirements for P.I.D. No. 004183A and related project identification numbers. The permits index details four key permit categories to be obtained for the project: Pinellas County Habitat Management Permit, Dewatering Permit, National Pollutant Discharge Elimination System (NPDES) Permit, and Local Building Permits. These permits will be issued to the contractor either following the preconstruction meeting or as directed by the County.

The permit index indicates that three of the four permit types (Habitat Management, Dewatering, and NPDES) will be issued at no permit charge, while Local Building Permits for electrical service connections will have fees dependent on the local jurisdiction. The permits are specifically associated with a project involving signalization infrastructure improvements at four intersections, which include replacing existing signalization with mast arms and making improvements to meet ADA guidelines. The permits appear to be an essential administrative requirement to ensure regulatory compliance and environmental considerations are addressed before and during the construction phase of the project.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX 1

PERMITS

P.I.D. NO. 004183A

PID Nos. 003876A, 004183C, 004183H, 004183I

Countywide Mast Arms – Group 2

PERMIT INDEX

Agency Permit Permit Fee Pinellas County Habitat Management Permit

Issued to Contractor following the Pre-construction Meeting if applicable or as directed by the County

No permit charge

Dewatering Permit Issued to Contractor following the Pre-construction Meeting if applicable or as directed by the County

No permit charge

National Pollutant Discharge Elimination System (NPDES) Permit

Issued to Contractor following the Pre-construction Meeting if applicable or as directed by the County

No permit charge

Local Building Permits Issued to Contractor for electrical service connections by local jurisdiction upon submittal of permit application

Dependent upon local jurisdiction