ak-13506-Signoff_SWPPP_Binder.pdf
PDF 18 MB Posted
- Attached to
- AK DOT 135(6), Glenn Highway Rehabilitation Kings River Bridge Section: MP 66. 0 to 67. 2
- Solicitation number
- 69056719B000032
About this file
This document provides details for a federal construction contract opportunity. The solicitation number is 69056719B000032 for the Alaska Department of Transportation's project to rehabilitate a section of the Glenn Highway between mileposts 66.0 and 67.2, including work on the Kings River Bridge. The opportunity type is an invitation for bid due on an unspecified date. The work requires rehabilitation of the highway section and bridge as further specified in the attached documents. The contracting agency is the Federal Highway Administration working through the Alaska Department of Transportation.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tab 2
NPDES Permit (Construction General Permit or appropriate State Permit)
Insert copy of EPA or applicable State CGP (Also included in Section H of the Contract)
Department of Environmental Conservation
DIVISION OF WATER
Wastewater Discharge Authorization Program
555 Cordova Street Anchorage, Alaska 99501-2617
Main: 907.269.6285 Fax: 907.334.2415 www.dec.alaska.gov/water/wastewater
August 15, 2022
Operator Info Project Info Kings River Bridge Replacement Glenn Highway Mile Post 66.5 Sutton, AK 99674
FHWA Western Federal Lands Highway Division Attn: Scott Smithline
610 E 5TH ST
Vancouver WA 98661
(360) 619-7700 scott.smithline@dot.gov
Est. Start – End: 09/19/2022 - 09/05/2025 Est. Area Disturbed: 32 acres Latitude, Longitude: 61.732100, -148.75000
General Permit Authorization Number: AKR10H031
This email/letter acknowledges that you have submitted a Notice of Intent (NOI) form to be covered under the APDES General Permit for Stormwater Discharges for Construction General Permit Activity (Construction General Permit) and is assigned the permit authorization number: AKR10H031. Please reference your permit authorization number in all future correspondence. The permittee is authorized to discharge storm water under the terms and conditions of this permit upon the issuance date of this letter and expires January 31, 2026 or as per Permit Part 2.6. Permit documents will be posted to the Alaska DEC EDMS Map Explorer at https://dec.alaska.gov/Applications/Water/EDMS/nsite.
According to the NOI information provided (ref: HPK-P99V-JBYD3, recd: 08/15/2022), the location of the SWPPP or the name and telephone number of the contact person for scheduling SWPPP viewing times is as follows:
• SWPPP Location: 2901 E. Bogard Road, Suite 103, Wasilla, 99654
• SWPPP Contact: Stephen Morrow, FHWA Western Federal Lands Highway Division, Environmental Protection Specialist, (360) 619-7700, stephen.morrow@dot.gov, 610 E 5TH ST, Vancouver, WA 98661
Note, as per Permit Part 2.7 the permittee is required to submit a modification NOI within 30 calendar days if any of the following change: Owner/Operator address and contact information, site information, estimated start or end dates, acres disturbed, or SWPPP location and contact information.
Coverage is not transferable. The permittee must submit a Notice of Termination (NOT) instead of an NOI modification to DEC within 30 calendar days when the operator has changed. A change of operator in this case means when an organization changes control of the project. It does not mean when a corporate officer of the organization changes while the organization continues with the project. The new owner/operator must file a new NOI to obtain coverage under the CGP.
A permittee must submit an NOT within 30 calendar days when final stabilization has been achieved on all portions of the site, in accordance with Permit Part 4.5.2 for which the permittee is responsible, all ground disturbing construction activity or use of support activities has been completed, and all temporary Best Management Practices (BMP’s) have been removed; or a new permittee has assumed control over all areas of the site that have not been finally stabilized.
http://www.dec.alaska.gov/water/wastewate scott.smithline@dot.gov https://dec.alaska.gov/Applications/Water/EDMS/nsite stephen.morrow@dot.gov
AKR10H031
As stated above, this letter acknowledges receipt of a Notice of Intent. However, it is not an ADEC determination of the validity of the information you provided. Your eligibility for coverage under the Permit is based on the validity of the certification you provided. Your signature on the Notice of Intent certifies that you have read, understood, and are implementing all of the applicable requirements. An important aspect of this certification requires that you correctly determine whether you are eligible for coverage under this permit.
As you know, the Construction General Permit requires you to have developed and begun implementing a Stormwater Pollution Prevention Plan (SWPPP) and outlines important inspection and record keeping requirements. You must also comply with any additional location-specific requirements applicable to Alaska. A copy of the Construction General Permit must be kept with your SWPPP. An electronic copy of the Permit and additional guidance materials can be viewed and downloaded at https://dec.alaska.gov/water/wastewater/stormwater/construction.
Prior to discharge, please review your authorization and general permit AKR100000 to ensure that you understand the requirements contained within them. If you have general questions regarding the storm water program or your responsibilities under the Construction General Permit, please call 907-269-6285.
https://dec.alaska.gov/water/wastewater/stormwater/construction
Tab 3
CONTRACTOR:
ALASKA PROJECTS ONLY:
File electronic or hard-copy NOI with Alaska Department of Environmental Conservation (ADEC) following instructions at http://dec.alaska.gov/water/wastewater/stormwater/apdesenoi.aspx
If you do not have an existing myAlaska account, follow ADEC instructions to register.
When filling out your NOI, use the same information as the FHWA NOI in tab 3 AND the following:
• Section I. Single/Multiple NOI Project. Fee has been paid by FHWA.
• Section II. Operator Information. Complete this section using information for
YOUR COMPANY.
After your NOI has been signed or paid, you will receive an email certifying that your application was signed or paid and another after being both signed and paid that your application was successfully submitted.
If you submitted a hard-copy signature page, it may take a few days to process.
Provide a copy of this acknowledgement email to the CO.
File copy of Contractor’s NOI and ADEC Acknowledgement e-mail in Tab 3.
http://dec.alaska.gov/water/wastewater/stormwater/apdesenoi.aspx
ALASKA POLLUTANT DISCHARGE ELIMINATION SYSTEM
GENERAL PERMIT FOR DISCHARGES FROM LARGE AND
SMALL CONSTRUCTION ACTIVITIES
(Construction General Permit) – Final
Permit Number: AKR100000
DEPARTMENT OF ENVIRONMENTAL CONSERVATION
Wastewater Discharge Authorization Program
555 Cordova Street
Anchorage, AK 99501
In compliance with the provisions of the Clean Water Act (CWA), 33 U.S.C. §1251 et. seq., as amended by the Water Quality Act of 1987, P.L. 100-4, this permit is issued under provisions of Alaska Statutes
46.03, the Alaska Administrative Code (AAC) as amended, and other applicable State laws and regulations.
Operators of large and small construction activities described in Part 1.4 of this Alaska Pollutant
Discharge Elimination System (APDES) general permit, except for those activities excluded from authorization to discharge in Part 1.4.4 of this permit, are authorized to discharge storm water associated with construction activity to waters of the U.S., in accordance with the conditions and requirements set forth herein. Permit authorization is required from the “commencement of construction activities” until
“final stabilization” as defined in Appendix C.
This permit shall become effective on 2/1/2021.
This permit and the authorization to discharge shall expire at midnight, 1/31/2026.
December 17, 2020
Signature Date
Gene McCabe Program Manager
2021 CGP Permit No. AKR100000
TABLE OF CONTENTS
1.0 COVERAGE UNDER THIS PERMIT
1.1 Introduction
1.2 Person(s) Responsible for Obtaining Authorization under this Permit
1.3 Permit Area
1.4 Eligibility
• Allowable Storm Water Discharges
• Authorized Non-Storm Water Discharges
• Limitations on Coverage
• Emergency Repairs or Reconstruction of a Facility
1.5 Waivers for Certain Small Construction Activities
2.0 AUTHORIZATION UNDER THIS GENERAL PERMIT
2.1 Submittal Requirements Prior to Construction
2.2 How to Obtain Authorization
2.3 How to Submit an Notice of Intent (NOI)
2.4 Submission Deadlines
• New Projects
• Permitted Ongoing Projects
• Change of Permittee for a Permitted Ongoing Project
• Unpermitted Ongoing Project
2.5 Date of Authorization to Begin Discharge
2.6 Continuation of Expired General Permit
2.7 Submittal of a Modification to Original NOI
2.8 Alternative Permits
• DEC Requiring Authorization under an Alternative Permit
• Operator Requesting Authorization under an Alternative Permit
3.0 COMPLIANCE WITH STANDARDS AND LIMITS
3.1 Requirements for all Projects
3.2 Discharge to Impaired Water Body
• Discharging into a Receiving Water Body with an Approved or Established TMDL
(Category 4a or 4b) (e.g., Turbidity or Sediment)
3.3 Protection of Endangered Species
4.0 CONTROL MEASURES
4.1 Control Measure Selection and Design Considerations
4.2 Erosion Control Measures
• Delineation of Site
• Minimize the Amount of Soil Exposed during Construction Activity
• Maintain Natural Buffer Areas
• Clearing Vegetation
• Control Storm Water Discharges and Flow Rates
• Protect Steep Slopes
4.3 Sediment Control Measures
• Storm Water Inlet Protection Measures
• Water Body Protection Measures
• Down-Slope Sediment Controls
• Stabilized Construction Vehicle Access and Exit Points
• Vehicle Trackout
• Dust Generation
• Stockpile Management
• Authorized Non-Storm Water Discharges
• Sediment Basins
4.4 Dewatering
4.5 Soil Stabilization
• Minimum Requirements for Soil Stabilization o Deadline to Initiate Stabilization o Deadline to Complete Temporary Stabilization Activities o Exceptions to the Deadlines for Initiating and Completing Stabilization o Deadline to Complete Final Stabilization
• Stabilization Requirements for Terminating Permit Authorization
4.6 Treatment Chemicals
4.7 Prohibited Discharge
4.8 Good Housekeeping Measures
• Washing of Equipment and Vehicles and Wheel Wash-Down
• Fueling and Maintenance Areas
• Staging and Material Storage Areas
• Washout of Applicators/Containers used for Paint, Concrete, and Other Materials
• Fertilizer or Pesticide Use
• Storage, Handling, and Disposal of Construction Waste
4.9 Spill Notification
4.10 Projects near a Public Water System (PWS)
4.11 Permanent Storm Water Management Control
4.12 Winter Considerations
• Winter Shutdown
• Winter Construction
4.13 Maintenance of Control Measures
4.14 Storm Water Lead and Training of Employees
4.15 Applicable Federal, State, Tribal, or Local Requirements
5.0 STORM WATER POLLUTION PREVENTION PLAN
5.1 Storm Water Pollution Prevention Plan (SWPPP)
5.2 Deadlines for SWPPP Preparation
5.3 SWPPP Contents
• Permittee
• Storm Water Contact(s)
• Project Site-Specific Conditions
• Nature of Construction Activity
• Site Map(s)
• Control Measures
• Construction and Waste Materials
• Locations of Other Industrial Storm Water Discharges
• Non-Storm Water Discharges
5.4 Inspections
5.5 Monitoring Plan (if applicable)
5.6 Documentation of Permit Eligibility Related to a Total Maximum Daily Load
5.7 Documentation of Permit Eligibility Related to Endangered Species
5.8 Post-Authorization Records
• Copy of Permit Requirements
• Additional Documentation Requirements
5.9 Maintaining an Updated SWPPP
• SWPPP Modifications
• SWPPP Amendment Log
• Deadlines for SWPPP Modifications
5.10 Additional SWPPP Requirements
• Retention of the SWPPP
• Main Entrance Signage
• Availability of SWPPP
• Signature and Certification
5.11 Requirements for Different Types of Operators
6.0 INSPECTIONS
6.1 Inspection Frequency
6.2 Case-by-Case Reductions in Inspection Frequency
6.3 Qualified Person
6.4 Site Inspection
• Location of Inspections
• Scope of Inspection
6.5 Linear Project Inspections
6.6 Inspections by DEC or Applicable Government Authority
6.7 Inspection Report
7.0 MONITORING
7.1 General Requirements
7.2 Qualified Person
7.3 Discharge Monitoring Requirements
• Sampling Parameter
• Sampling Frequency
• Sampling Locations
• Representative Discharge Point for a Linear Project
• Commingled Discharges
• Sample Type
• Sampling and Analysis Methods
• Rainfall Monitoring
• Recording Monitoring Data
• Reporting Monitoring Results
7.4 Visual Monitoring for a Linear Project
• Visual Monitoring Frequency
• Visual Monitoring Locations
• Visual Monitoring Parameters
• Recording Visual Monitoring Data
8.0 CORRECTIVE ACTIONS
8.1 Corrective Action Conditions
8.2 Deadlines for Corrective Actions
8.3 Corrective Action Log
8.4 Corrective Action Report
8.5 Substantially Identical Outfalls
9.0 REPORTING AND RECORDKEEPING
9.1 Annual Report
9.2 Corrective Action Report
9.3 Spill of Hazardous Substances Report
9.4 Retention of Records
9.5 Request for Submittal of Records
10.0 TERMINATION OF PERMIT AUTHORIZATION
10.1 Submitting a Notice of Termination (NOT)
10.2 When to Submit a Notice of Termination
10.3 Submitting a Notice of Termination
11.0 PERMIT REOPENER CLAUSE
11.1 Procedures for Modification or Revocation
11.2 Water Quality Protection
11.3 Timing of Permit Modification
Appendix A Standard Permit Conditions
Appendix B Acronyms
Appendix C Definitions
Appendix D Small Construction Waivers and Instructions
Appendix E Forms
• Notice of Intent (NOI)
• Notice of Termination (NOT)
• Notice of Intent Modification
• Low Erosivity Waiver
• Annual Report
TABLES
Table 1: Schedule of Submissions
Table 2: Summary of Permit Required On-Site Documentation
Table 3: SWPPP Submittal within Municipality of Anchorage MS4 area
Table 4: Recommended Experience or Required Training for Specific Roles ..................................... C-13
SCHEDULE OF SUBMISSIONS
The Schedule of Submissions (Table 1) summarizes the required submissions and activities the permittee must complete and/or submit to the Alaska Department of Environmental Conservation (DEC or the Department) during the terms of this permit. The operator is responsible for all submissions and activities even if they are not summarized below.
Table 1: Schedule of Submissions
Permit
Part Type of Project
Submittal
Requirement Frequency Due Date Submit to 1
Prior to Construction
1.4.4.7, 2.1.1, 2.1.2, and 4.11
Projects that will construct Permanent
Storm Water
Management Controls
Engineering
Plans
Once At least 30 calendar days before the start of construction or as required by the MS4
Operator
Permitting
Program or
MS4
Operator
1.5 Small construction
activities that use a waiver in lieu of CGP authorization
Waiver
Certification
Once At least five business days before proposed start of construction
Permitting
Program
2.1.3 Projects that disturb
greater than or equal to
5 acres of land and are outside an MS4 area
SWPPP 2 Once With NOI Permitting
Program
2.1.4 Projects inside an MS4
area
SWPPP Once Depends on requirements of
MS4 operator
MS4
Operator
2.1.5 and
4.6.7
Project that use Cationic
Treatment Chemicals
Engineering
Plans and
Project Details
Once At least 14 calendar days before use of the system
Permitting
Program
2.1.6 Projects that discharge
to an Outstanding
Natural Resource Water
Site-Specific
Antidegradation
Analysis
Once At least 14 calendar days before filing
NOI
Permitting
Program
2.3 Projects that disturb
greater than or equal to
1 acre of land
Notice of Intent Once At least five business days before the start of construction
Permitting
Program
Table 1: Schedule of Submissions
Permit
Part Type of Project
Submittal
Requirement Frequency Due Date Submit to 1
During Construction
2.4.2
2.6
For an authorized permittee if the permittee intends to continue operations and discharges beyond the term of this permit
Submit a complete and accurate new
NOI according to Part 2.3
Once Within 90 calendar days of the effective date of this permit
Permitting
Program
2.7 To update or correct
information on the original NOI
NOI
Modification
As needed As needed Permitting
Program
3.2, 8.4, and
9.2
If the difference between upstream and downstream samples exceed WQS for turbidity
Corrective
Action Report
As necessary
At least 14 calendar days after receiving monitoring results
Compliance
Program
9.1 Projects that disturb
greater than or equal to
20 acres of land
Annual Report As needed for sites meeting
Part 3.2
By December
31st or with
NOT
Compliance
Program
9.5 All projects with an
active NOI
Request for
Submittal of
Records
As requested by DEC
At least 30 calendar days after receipt of request
As requested by
DEC
Post Construction
10.2 All projects with an
active NOI
Notice of
Termination
(NOT)
Once Within 30 calendar days of completion of the project
Permitting
Program
Note:
1 See Appendix A, Part 1.1 for Permitting and Compliance Program contact information and addresses
2 All projects that require an NOI must prepare a SWPPP. However, only operators who are developing projects that disturb greater than or equal to five (5) acres of land and are outside an MS4 area are required to submit a SWPPP to DEC.
REQUIRED ON-SITE DOCUMENTATION
The Summary of Required On-Site Documentation (Table 2) lists the documents the permittee must have available at the project site or the project management office. The permittee is responsible for all documentation even if they are not summarized below.
Table 2: Summary of Permit Required On-Site Documentation
Permit
Part Document Frequency Purpose of Document
2.3 NOI Once at start of project Applicant request for authorization to discharge under permit coverage
2.5 DEC NOI Reply Letter Once at start of project To provide permittee with DEC project tracking number indicating project is covered by CGP
2.7 NOI Modification As needed To modify the original NOI if
project conditions, personnel, or
SWPPP location change
5.0 SWPPP Developed prior to
submitting the NOI.
Updated as necessary.
To describe the project and the control measures to minimize the discharge of pollutants into waters of the U.S.
5.4; 6.7 Inspection Reports Conducted at frequency specified in
SWPPP
To monitor compliance with SWPPP and CGP
5.5; 7.0 Monitoring Plan
(if required)
As needed To describe monitoring of storm water discharge for those projects that disturb more than threshold requirement
5.6 Permit Eligibility related
to Total Maximum Daily
Load (TMDL)
Once at start of project To document compliance with
TMDL requirements
5.7 Permit Eligibility related
to Endangered Species Act
(ESA)
Once at start of project To document compliance with ESA requirements
5.8.1 Copy of this permit Once at start of project To include in SWPPP
5.8.2 Additional Documentation
in the SWPPP
Updated as necessary To maintain summaries of various specific activities at the site to document they were accomplished.
8.3 Corrective Action Log (if
necessary)
Updated as necessary To list the corrective actions taken at a site
8.4; 9.2 Corrective Action Report
(if necessary)
As needed To report exceeding the turbidity requirement and describe
9.1 Annual Report (if
required)
Annually or at NOT To report result of discharge monitoring
9.4 Records As needed To maintain project records
10.2 NOT Once at completion of
project
To notify DEC that the permittee is terminating permit coverage
1.0 COVERAGE UNDER THIS PERMIT
1.1 Introduction
The Alaska Construction General Permit (CGP) authorizes storm water discharges from large and small construction-related activities that result in a total land disturbance of equal to or greater than one acre and where those discharges enter waters of the U.S. (directly or through a storm water conveyance system) or a municipal separate storm sewer system (MS4) leading to waters of the U.S. subject to the conditions set forth in this permit. This permit also authorizes storm water discharges from certain construction support activities and some non-storm water discharges commonly associated with construction sites.
The goal of this permit is to minimize erosion and reduce or eliminate the discharge of pollutants, such as sediment carried in storm water runoff from construction sites through implementation of appropriate control measures. Polluted storm water runoff can adversely affect fish, animals, plants, and humans. In order to ensure protection of water quality and human health, this permit describes control measures that must be used to manage storm water runoff during construction activities. This permit replaces the CGP that became effective February 1, 2016 and expired on January 31, 2021.
1.2 Person(s) Responsible for Obtaining Authorization under this Permit
1.2.1 All operators of large or small construction activities that meet the conditions in Part 1.4 must obtain authorization under this permit. For the purposes of this permit, an “operator” is any party associated with a construction project that meets either of the following two criteria:
1.2.1.1 The party has operational control over construction plans and specifications, including the ability to make modifications to those plans and specifications, or
1.2.1.2 The party has day-to-day operational control of those activities at a project that are necessary to ensure compliance with the permit conditions (e.g., they are authorized to direct workers at a site to carry out activities required by the permit)
Note: Subcontractors generally are not considered operators for the purposes of this permit.
Note: Where there are multiple operators associated with the same project, all operators are required to obtain permit authorization. The following applies in these situations:
• If one operator has control over plans and specifications and a different operator has control over activities at the project site, they may divide responsibility for compliance with the terms of this permit as long as they develop a group storm water pollution prevention plan
(SWPPP) (see Part 5.1), which documents which operator has responsibility for each requirement of the permit.
• If an operator only has operational control over a portion of a larger project (e.g., one of four homebuilders in a subdivision), the operator is responsible for compliance with all applicable effluent limits, terms, and conditions of this permit as it relates to the activities on their portion of the construction site, including protection of endangered species, critical habitat, and historic properties, and implementation of control measures described in the
SWPPP in the areas under their control.
• An operator must ensure either directly or through coordination with other permittees, that their activities do not render another permittee’s pollutant discharge controls ineffective.
1.3 Permit Area
This general permit covers the State of Alaska, except lands within the Metlakatla Indian
Reservation and the Denali National Park and Preserve.
1.4 Eligibility
1.4.1 Eligibility Requirements. To be authorized under this permit, the project must meet the following conditions or be notified by DEC that the site is eligible for permit coverage.
1.4.1.1 The project will disturb one or more acres of land, or will disturb less than one acre of land but is part of a common plan of development or sale that will ultimately disturb one or more acres of land;
1.4.1.2 The site will discharge storm water to waters of the U.S. (directly or through a storm water conveyance system) or a MS4 leading to a waters of the U.S.;
1.4.1.3 The project area is located in an area where DEC is the permitting authority;
1.4.1.4 The project is not already covered under a different APDES permit;
1.4.1.5 The project does not discharge to an impaired waterway with an EPA-approved or established Total Maximum Daily Load (TMDL) that specifically precludes such discharges; and
1.4.1.6 The project is not likely to jeopardize the continued existence or cause a take of any threatened or endangered species protected under the Endangered Species Act (ESA) or their designated critical habitat.
1.4.2 Authorized Storm Water Discharges. Subject to compliance with the terms and conditions of this permit, the following discharges are authorized under this permit:
1.4.2.1 Storm water discharges associated with large and small construction activities, including those that are part of a common plan of development or sale that will ultimately disturb one or more acres of land.
1.4.2.2 Storm water discharges designated by DEC as needing a storm water permit under
40 CFR §122.26(a)(1)(v) or §122.26(b)(15)(ii).
1.4.2.3 Storm water discharges from support activities (such as concrete or asphalt batch plants, equipment staging yards, material storage areas, excavated material disposal areas, borrow areas) (as defined in Appendix C), whether on-site, adjacent to, or off-site, provided:
1.4.2.3.1 The support activity is directly related to the construction site required to have permit authorization for discharges of storm water associated with construction activity under this permit:
1.4.2.3.2 The support activity is not a commercial operation serving multiple unrelated construction projects by different permittees;
1.4.2.3.3 The support activity does not operate beyond the completion of the construction activity at the project it supports; and
1.4.2.3.4 Appropriate control measures are identified in the Storm Water Pollution
Prevention Plan (SWPPP) and pollutant discharges are minimized in compliance with Parts 3.0 and 4.0 of the permit.
1.4.2.4 Discharges composed of allowable discharges listed in Parts 1.4.2 and 1.4.3 commingled with a discharge authorized by a different APDES permit and/or a discharge that does not require APDES permit authorization.
http://www.ecfr.gov/cgi-bin/text-idx?SID=cd32add828dfbfd32ccadd72afd59a58&mc=true&node=se40.22.122_126&rgn=div8 http://www.ecfr.gov/cgi-bin/text-idx?SID=cd32add828dfbfd32ccadd72afd59a58&mc=true&node=se40.22.122_126&rgn=div8
1.4.3 Authorized Non-Storm Water Discharges. Subject to compliance with the terms and conditions of this permit, the following non-storm water discharges are authorized under this general permit, provided the non-storm water component of that the discharge is in compliance with the SWPPP requirements in Part 5.3.9:
1.4.3.1 Discharges from fire-fighting activities;
1.4.3.2 Fire hydrant flushings;
1.4.3.3 Waters used to wash vehicles where detergents are not used;
1.4.3.4 Water used to control dust;
1.4.3.5 Potable water including uncontaminated water line flushings;
1.4.3.6 Routine external building wash down where detergents are not used;
1.4.3.7 Pavement wash waters where spills or leaks of toxic or hazardous materials have not occurred (unless all spilled material has been removed) and where detergents are not used;
1.4.3.8 Uncontaminated air conditioning or compressor condensate;
1.4.3.9 Uncontaminated, non-turbid discharges of ground water or spring water;
1.4.3.10 Foundation or footing drains where flows are not contaminated with process materials such as solvents or contaminated groundwater;
1.4.3.11 Uncontaminated construction dewatering waters that are treated by an appropriate control measure in compliance with Part 4.4.2, or have been treated with treatment chemicals in compliance with Part 4.6; and
1.4.3.12 Landscape irrigation.
1.4.4 Limitations on Coverage. The following discharges are not authorized under this permit:
1.4.4.1 Post-Construction Discharges. Discharges that originate from the project after construction activities have ceased and a Notice of Termination (NOT) has been submitted in accordance to Part 10.0, including any temporary support activity.
1.4.4.2 Discharges that May Exceed Water Quality Standards. Discharges that DEC, prior to authorization under this permit, determines will cause, have the reasonable potential to cause, or contribute to an excursion above any applicable water quality standard
(WQS). Where such a determination is made prior to authorization, DEC may notify the applicant that an individual permit application is necessary in accordance with Part
2.8. However, DEC may provide permit authorization after the applicant has included appropriate controls and implementation procedures designed to bring the discharge into compliance with WQS’s in accordance with Part 3.1.
1.4.4.3 Discharges to Water Quality Impaired Waters. Discharges into receiving waters that are listed as impaired waters in the report Alaska’s Final 2018 Integrated Water
Quality Monitoring and Assessment Report, dated March 26, 2020 (or the most current
EPA-approved version), or with an approved or established TMDL analysis, unless the discharges are in accordance with Part 3.2.
1.4.4.4 Comingled Discharges. Discharges that are mixed with non-storm water, unless they are listed as allowable non-storm water discharges in Part 1.4.3.
1.4.4.5 Discharges Currently or Previously Covered by another Permit. Unless the permittee received written notification from DEC specifically allowing these discharges to be authorized under this permit, the permittee is not eligible for coverage under this permit for any of the following:
http://dec.alaska.gov/water/wqsar/waterbody/integratedreport.htm http://dec.alaska.gov/water/wqsar/waterbody/integratedreport.htm http://dec.alaska.gov/water/wqsar/Docs/Impairedwaters.pdf http://dec.alaska.gov/water/wqsar/Docs/Impairedwaters.pdf
1.4.4.5.1 Storm water discharges associated with construction activity that have been covered under an individual permit, an alternative APDES general permit, or are required to obtain authorization under an alternative general permit in accordance with Part 2.8.
1.4.4.5.2 Discharges from sites where any APDES permit has been or is in the process of being denied, terminated, or revoked by DEC (this does not apply to the routine reissuance of permits every five years).
1.4.4.6 Discharges of Dredged or Fill Material. Discharges of dredged or fill material into waters of the U.S. requiring federal authorization through the U.S Army Corps of
Engineers CWA Section 404 Regulatory Program.
1.4.4.7 Discharges from Nondomestic Treatment Works. Discharges of storm water to the land or groundwater from a nondomestic wastewater treatment works (as defined in
18 AAC 72) using permanent storm water management controls unless they are in compliance with 18 AAC 72.600 and EPA Underground Injection Control regulations1.
1.4.5 Emergency Repairs or Reconstruction of a Facility
1.4.5.1 Discharges from construction activities conducted in response to a disaster (as defined in Alaska Statute 26.23.900) are conditionally authorized, provided that the operator does the following:
1.4.5.1.1 Submits a Notice of Intent (NOI) and SWPPP (if project disturbs five or more acres in accordance with Part 2.1) to the Department in accordance with Part 2.3 and 2.4 within 30 calendar days of initiating construction activities.
1.4.5.1.2 Implements appropriate control measures as soon as possible after initiating construction activities. For discharges occurring during the initial 30 day period, the permittee must demonstrate compliance with the terms and conditions of this permit to the extent practicable depending on the disaster.
1.5 Waivers for Certain Small Construction Activities
1.5.1 Waiver Criteria. An operator of a small construction activity may qualify for a waiver in lieu of obtaining authorization under this permit if one of the following three criteria are met. Details of the three waiver options and procedures for requesting a waiver are provided in Appendix D:
1.5.1.1 The project has a low rainfall erosivity factor;
1.5.1.2 DEC or EPA has established or approved a TMDL that addresses the pollutant(s) of concern and has determined storm water control measures are not needed to protect water quality;
1.5.1.3 The operator develops an equivalent analysis that determined allocations for pollutant(s) of concern are not needed to protect water quality. This waiver is only available for non-impaired waters.
1 For additional information refer to DEC’s Engineered Wastewater Disposal System web page at http://dec.alaska.gov/water/wastewater/engineering/engineered-systems and EPA’s Underground Injection Control web page at http://www.epa.gov/uic/underground-injection-control-region-10-ak-id-or-and-wa https://dec.alaska.gov/commish/regulations/pdfs/18%20AAC%2072.pdf#page=78 https://dec.alaska.gov/commish/regulations/pdfs/18%20AAC%2072.pdf#page=57 http://www.legis.state.ak.us/basis/statutes.asp#26.23.900 http://dec.alaska.gov/water/wastewater/engineering/engineered-systems http://www.epa.gov/uic/underground-injection-control-region-10-ak-id-or-and-wa
2.0 AUTHORIZATION UNDER THIS GENERAL PERMIT
2.1 Submittal Requirements Prior to Construction Depending on the type and location of the project, the operator may be required to submit information to the DEC and/or an MS4 operator for review prior to filing the NOI and commencement of construction activities. The following is a summary of the information to be submitted to each agency by project type and area of jurisdiction.
2.1.1 Permanent Storm Water Management Controls (Outside MS4). An operator installing permanent storm water management controls in accordance with Part 4.11 and where the project is located outside of an APDES permitted MS4, must submit information required by the DEC in Part 4.11 at least thirty (30) calendar days prior to filing the NOI for the project. The operator must receive the DEC’s written reply prior to the commencement of construction activities.
2.1.2 Permanent Storm Water Management Controls (Inside MS4). An operator installing permanent storm water management controls in accordance with Part 4.11 and where the project is located inside the area of an APDES permitted MS4 must submit information required by the MS4 operator for the project and must receive the MS4 operator’s approval prior to the commencement of construction activities. Check with the respective MS4 operator for their particular submittal requirements. (See http://dec.alaska.gov/water/ wastewater/stormwater/swppp-submittal-rqmts for further MS4 operator contact information.)
2.1.2.1 Operators of construction activity within the Municipality of Anchorage (with the exception of ADOT&PF, see 2.1.2.2) shall submit information to:
Municipality of Anchorage
Public Works Department
4700 South Elmore Rd.
P.O. Box 196650
Anchorage, AK 99519-6650
2.1.2.2 Operators of construction activities for Alaska Department of Transportation & Public
Facilities (ADOT&PF) construction projects within the Municipality of Anchorage shall submit information to:
ADOT&PF
Construction and Operations, Central Region
4111 Aviation Ave.
P.O. Box 196900
Anchorage, AK 99519
2.1.2.3 Operators of construction activity within the Fairbanks North Star Borough shall submit information to:
Fairbanks North Star Borough
Department of Public Works
P.O. Box 71267
Fairbanks, AK 99707 http://dec.alaska.gov/water/wastewater/stormwater/swppp-submittal-rqmts
2.1.2.4 Operators of construction activity within the City of Fairbanks shall submit information to:
City of Fairbanks
Engineering Division
800 Cushman St.
Fairbanks, AK 99701
2.1.2.5 Operators of construction activity within the City of North Pole shall submit information to:
City of North Pole
Department of Public Works
125 Snowman Lane
North Pole, AK 99705
2.1.2.6 Operators of construction activity within the Joint Base Elmendorf-Richardson shall submit information to:
Storm Water Lead
673rd CES/CEIEC
724 Quartermaster Drive
Joint Base Elmendorf-Richardson
2.1.2.7 Operators of construction activity within the Port of Anchorage shall submit information to:
Port of Anchorage
Operations and Maintenance
2000 Anchorage Port Road
Anchorage, AK 99501
2.1.2.8 Operators of construction activity within Fort Wainwright shall submit information to:
Water Quality Program
US Army Garrison, Alaska DPW, Environmental Division
3023 Engineer Place
Fort Wainwright, AK 99703
2.1.3 SWPPP Submittal to DEC. An operator developing a project that disturbs five or more acres of land must submit a copy of the SWPPP to the DEC (Appendix A, Part 1.1.1) at the time the NOI is filed (electronic attachments to the eNOI are preferred).
2.1.4 SWPPP Submittal to MS4. An operator developing a project that is located inside the area of an APDES permitted MS4 must submit a copy of the SWPPP to the respective
MS4 operator. Check with the respective MS4 operator for their particular submittal requirements. (http://dec.alaska.gov/water/wastewater/stormwater/swppp-submittal-rqmts for further MS4 operator contact information.)
2.1.4.1 Within the Municipality of Anchorage
2.1.4.1.1 An operator of construction projects disturbing one or more acres of land shall submit a copy of the SWPPP to either DEC or the Municipality based on the project type and operator as shown in the following table.
Table 3: SWPPP Submittal within Municipality of Anchorage MS4 area.
Project Type Submit SWPPP to
Government (Federal, state, or Port of Anchorage) road projects and other government sponsored transportation projects such as ports, railroads, or airports
DEC
Government (municipal) road projects and other government transportation projects Municipality
Public or private utility projects when the utility is initiating the work Municipality
Work that requires a building permit Municipality
Non-publicly funded transportation projects Municipality
2.1.4.1.2 Submittal of the SWPPP to the Municipality shall be made according to the most recent Municipality requirements and be submitted to the address given in Part
2.1.2.1
2.1.4.1.3 Submittal of the SWPPP to the DEC shall be to the address in Appendix A, Part
1.1.1.
2.1.4.2 Within the road service areas of the Fairbanks North Star Borough, check with the
Borough for the latest SWPPP submittal requirements at the address given in Part
2.1.2.3. An operator of a publicly-funded project disturbing one or more acres of land shall submit a copy of the SWPPP to the DEC for review at the address in Appendix
A, Part 1.1.1.
2.1.4.3 Within the City of Fairbanks, check with the City for the latest SWPPP submittal requirements at the address given in Part 2.1.2.4. An operator of a public-funded project disturbing one or more acres of land shall submit a copy of the SWPPP to the
DEC for review at the address in Appendix A, Part 1.1.1.
2.1.4.4 Within the City of North Pole, check with the City for the latest SWPPP submittal requirements at the address given in Part 2.1.2.5. An operator of a public-funded project disturbing one or more acres of land shall submit a copy of the SWPPP to the
DEC for review at the address in Appendix A, Part 1.1.1.
2.1.4.5 Within the Joint Base Elmendorf-Richardson, check with the latest SWPPP submittal requirements at the address given in Part 2.1.2.6.
2.1.4.6 Within the Port of Anchorage, check with the latest SWPPP submittal requirements at the address given in Part 2.1.2.7.
2.1.4.7 Within the Fort Wainwright installation boundary, check with the latest SWPPP submittal requirements at the address given in Part 2.1.2.8.
2.1.5 Projects Using Cationic Treatment Chemicals or an Active Treatment System. Submit engineering plans and projects details listed in Part 4.6.7 to DEC (Appendix A, Part 1.1.1) at least 14 calendar days prior to use at the construction site.
2.1.6 Projects that Discharge to an Outstanding Natural Resource Water. Contact DEC at least 30 calendar days prior to commencement of construction activities that may discharge to a high quality water that constitutes an outstanding national resource, such as a water of a national or state park or wildlife refuge or a water of “exceptional recreational or ecological significance” (as described in Appendix C), to discuss the need to conduct a site-specific antidegradation analysis. If an antidegradation analysis is required, it must be submitted at least 14 calendar days prior to filing the NOI. Before beginning construction activities, operators must receive a written approval of the analysis from the DEC.
Note: No Outstanding Natural Resource Waters are designated in Alaska as of the date of this permit issuance.
2.2 How to Obtain Authorization
2.2.1 To obtain authorization under this permit, an operator must:
2.2.1.1 Be responsible for a project located in the area where DEC is the permitting authority;
2.2.1.2 Meet the eligibility requirements of Part 1.4;
2.2.1.3 Develop a SWPPP according to the requirements in Part 5.0 prior to filing for an NOI and submit a copy of the SWPPP as specified in Part 2.1;
2.2.1.4 Select, design, install, and implement control measures in accordance with Part 4.0 to meet non-numeric effluent limits;
2.2.1.5 Submit a complete and accurate NOI either using DEC’s electronic system or using a paper form in accordance with Part 2.3 prior to commencing construction activities;
2.2.1.6 Pay the general permit authorization fees in accordance with 18 AAC 72.956;
2.2.1.7 Submit any additional information requested by the DEC or MS4 Operator (if applicable); and
2.2.1.8 Be granted authorization to discharge by the DEC.
2.2.2 Submission of the NOI demonstrates the operator’s intent to be covered by this permit; it is not a determination by DEC that the operator meets the eligibility requirements for the permit. A discharge is not authorized if:
2.2.2.1 The operator’s NOI is incomplete or inaccurate;
2.2.2.2 DEC requires the operator to obtain authorization under an individual permit or an alternative general permit; or
2.2.2.3 The discharge does not meet the eligibility requirements under Part 1.4.
2.2.3 If the information on the NOI is incorrect or is missing, the NOI will be deemed incomplete and permit authorization will not be granted. A complete NOI shall include the following information:
2.2.3.1 Operator: organization name, contact person and title, complete mailing address, telephone number, fax number (optional), and email address;
2.2.3.2 Billing Contact: organization name, contact person and title, complete mailing address, telephone number and fax number and email address. If the billing contact information is the same as the operator information, check the box on the NOI indicating that it is the same;
2.2.3.3 Project/site: project/site name, a physical location, the nearest city and zip code, the borough, latitude and longitude, how the latitude and longitude were determined, and estimated project start date and completion date, and an estimate of the area to be disturbed;
2.2.3.4 SWPPP: acknowledgement of whether a SWPPP has been prepared in advance of filing the NOI, the location of the SWPPP – either with the operator, the project/site, or other location, SWPPP contact if different than the operator contact;
2.2.3.5 Discharge: the name(s) of the waterbody to which the project discharges, identification if the project/site discharges to a waterbody that is impaired or has a
TMDL, if so, confirmation that the discharge is consistent with the assumptions and requirements of the TMDL;
http://www.legis.state.ak.us/basis/folioproxy.asp?url=http://wwwjnu01.legis.state.ak.us/cgi-bin/folioisa.dll/aac/query=%5bJUMP:'18+aac+72!2E956'%5d/doc/%7b@1%7d/hits_only?firsthit
2.2.3.6 Signatory information in compliance with Appendix A, Part 1.12.
2.3 How to Submit an Notice of Intent (NOI)
2.3.1 Submittal Options. Each operator must submit an NOI to be authorized to discharge under this permit at least five business days prior to commencement of construction activities. DEC may need additional time for manual processing of NOIs. The complete and accurate NOI can be submitted either:
2.3.1.1 Electronically (strongly encouraged): Go to DEC’s Water Online Application System
(OPA) web page at http://dec.alaska.gov/water/oasys/index.html to prepare and submit electronic NOI (eNOI). Note the eNOI will likely be processed more quickly and result in faster receipt of an authorization to discharge.
2.3.1.2 Paper NOI Form: Complete the CGP NOI form on DEC’s APDES Storm Water
Forms web page at http://dec.alaska.gov/water/wnpspc/stormwater/2016CGPForms.htm. Once the form is complete, scan and email the entire form (5 pages) to the permitting email address in
Appendix A, Section 1.1.1 or submit a paper copy to DEC at the address listed in
Appendix A, Section 1.1.1.
2.3.1.3 Applicants must pay the general permit authorization fee (in accordance with 18 AAC
72.956) before their NOI is considered complete.
2.4 Submission Deadlines
2.4.1 New Projects. The operator must submit a complete and accurate NOI and SWPPP (if project disturbs five or more acres in accordance with Part 2.1) prior to commencement of construction activities consistent with Parts 2.2.1 and 2.3 to obtain authorization under this permit.
2.4.2 Permitted Ongoing Projects.
2.4.2.1 An ongoing permitted project is one that commenced construction activities prior to the effective date of this permit and where the discharges from that project were authorized under the 2016 CGP (AKR100000). To continue coverage, a permittee must:
2.4.2.1.1 Continue to comply with the terms and conditions of the 2016 CGP until the permittee has been granted authorization under this permit or an alternative
APDES permit, or submits a NOT;
2.4.2.1.2 Update the existing SWPPP as necessary to comply with the requirements of Part
3.0, Part 4.0 and Part 5.0 before submitting a new NOI, as described in Part
2.4.2.1.3; and
2.4.2.1.3 Submit a complete and accurate new NOI within 90 calendar days of the effective date of this permit according to Part 2.3. A copy of the updated SWPPP and permit fee is not required to be submitted with the NOI to DEC for permitted ongoing projects.
2.4.2.2 If the permittee is eligible to submit a NOT (e.g., construction is finished and final stabilization has been achieved) before the 90th day, a new NOI is not required to be submitted provided a NOT is submitted within 90 calendar days after the effective date of this permit.
http://dec.alaska.gov/water/oasys/index.html http://dec.alaska.gov/water/wnpspc/stormwater/2016CGPForms.htm http://www.legis.state.ak.us/basis/folioproxy.asp?url=http://wwwjnu01.legis.state.ak.us/cgi-bin/folioisa.dll/aac/query=%5bjump!3A!2718+aac+72!2E956!27%5d/doc/%7bt81252%7d/pageitems=%7bbody%7d?
http://www.legis.state.ak.us/basis/folioproxy.asp?url=http://wwwjnu01.legis.state.ak.us/cgi-bin/folioisa.dll/aac/query=%5bjump!3A!2718+aac+72!2E956!27%5d/doc/%7bt81252%7d/pageitems=%7bbody%7d?
2.4.3 Change of Permittee for an Authorized Ongoing Project.
2.4.3.1 A permittee of an ongoing project who transfers ownership of the project, or a portion thereof, to a different operator, the new operator will be required to submit a complete and accurate new NOI for a new project in accordance with Part 2.3.1 and the original permittee must file a NOT in accordance with Part 2.7.5.
2.4.4 Unpermitted Ongoing Project/Late Notification.
An operator who commences construction activities without authorization to discharge for a project that requires submission of a NOI consistent with Part 2.2 must develop and/or update a project-specific SWPPP and submit a complete and accurate NOI consistent with
Part 2.3 as soon as practicable. The applicant is authorized to discharge in accordance with
Part 2.5. The DEC reserves the right to take enforcement action for any unpermitted discharges or permit non-compliance that occurs between the commencement of construction and discharge authorization.
2.5 Date of Authorization to Begin Discharge
Authorization to discharge under this general permit requires the operator seeking authorization to submit to DEC a complete and accurate NOI and payment of fee. If the project disturbs five or more acres, a copy of the SWPPP must be submitted in accordance with Part 2.1 prior to commencement of construction activities consistent with Parts 2.2.1 and 2.3.. The operator must receive written notification of authorization from DEC that coverage has been granted, and that a specific authorization number has been assigned prior to construction activities.
A permittee is authorized to discharge storm water from construction activities under the terms and conditions of this general permit upon the date specified in the issuance of the
DEC authorization letter, which is posted on DEC’s water permit search website
(http://dec.alaska.gov/Applications/Water/WaterPermitSearch/Search.aspx).
2.6 Continuation of Expired General Permit
If this permit is not reissued prior to the expiration date, it will be administratively continued in accordance with 18 AAC 83.155(c) and remain in force and effect for discharges that were covered prior to expiration.
2.6.1 The permittee is required to abide by all limitations, monitoring, and reporting included herein if the permit enters administrative extension until such time a permit is reissued authorizing the discharge or an NOT is submitted by the permittee.
2.6.2 A permittee who is authorized to discharge under this permit prior to the expiration date, any discharges authorized will automatically remain covered by this permit until the earliest of:
2.6.2.1 Authorization for coverage under a reissued permit or replacement of this permit following a permittee’s timely and appropriate submittal of a complete NOI requesting authorization to discharge under the new permit and compliance with the requirements of the new permit;
2.6.2.1.1 If a permittee fails to submit a timely NOI for coverage under the reissued or replacement permit, the permittee’s coverage will expire at midnight on the date that the NOI is due.
2.6.2.2 Submittal of a NOT;
2.6.2.3 Issuance of an individual permit for the project’s discharges; or http://dec.alaska.gov/Applications/Water/WaterPermitSearch/Search.aspx http://www.legis.state.ak.us/basis/aac.asp#18.83.155
2.6.2.4 A formal permit decision by DEC to not reissue this general permit or not cover a particular discharger previously covered by the general permit, at which time DEC will identify a reasonable time period for covered dischargers to seek coverage under an alternative general permit or an individual permit. Coverage under this permit will cease at the end of this time period.
2.7 Submittal of a Modification to Original NOI
2.7.1 Modification. A permittee must file an NOI modification form to DEC (see Part 2.3) to update or correct the following information on the original NOI within 30 calendar days of the change:
2.7.1.1 Owner/Operator address and contact information;
2.7.1.2 Site information;
2.7.1.3 Estimated start or end dates;
2.7.1.4 Number of acres to be disturbed; or
2.7.1.5 SWPPP location and contact information.
2.7.2 Continuation of expired permit in accordance with Part 2.6.
2.7.3 If the original project disturbance was between one and less than five acres, and will now disturb five acres or more, a SWPPP must be submitted with the NOI modification.
2.7.4 No general permit authorization fee is required when submitting an NOI modification.
2.7.5 NOT Instead of Modification. The permittee must submit a NOT instead of an NOI modification form to DEC within 30 calendar days when the operator has changed.