QA_10-21-2022.pdf
PDF 100 KB Posted
- Attached to
- AK DOT 135(6), Glenn Highway Rehabilitation Kings River Bridge Section: MP 66. 0 to 67. 2
- Solicitation number
- 69056719B000032
About this file
This document contains technical questions and answers related to solicitation number 69056719B000032 for the Alaska Department of Transportation's Glenn Highway Rehabilitation project from milepost 66.0 to 67.2. Key details include clarification that the bid bond number should match the solicitation rather than a preprinted number, confirmation that two pickup trucks provided for government use will be returned to the contractor during winter shutdowns, provision of cross section files to aid quantity takeoffs, a link to the applicable Davis Bacon wage determination, clarification around the scope of special clearing and grubbing work, and confirmation that the government will not provide cross sections for riprap work given excavations up to 15 feet deep.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AK DOT 135(6)
Glenn Highway Rehabilitation, Kings River Bridge Section MP 66.0 to MP 67.2
# General Technical Question Answer Date
1 X it appears the pre‐printed invitation number on the bid bond does match the solicitation number. Would you please confirm which solicitation number we should be using on our bid bond?
This will be addressed under Amendment A001. 10/6/2022
2 X Contractor is to provide 2 pickups for government’s use. Will these vehicles be returned to the contractor during the winter shut‐downs?
This will be addressed under Amendment A002. 10/13/2022
3 X Are cross sections that correspond to the “Earthwork Data Listing” available?
Yes. ak‐13506_Cross Section Labeled.pdf is a file listed under FAR Clause
52.236‐4. Obtain this file from the Physical Data 2.zip file on sam.gov.
10/13/2022
4 X
We are trying to determine Alaska Davis Bacon Wage Rates for the above referenced project. The link provided on SAM.gov for Davis‐Bacon
Act WD #: AK20220007 (applicable rates published on September 8, 2022) does not contain any wage rates.
Please provide the rates for the September 8, 2022 wage determination for Highway Construction.
SAM has updated the wage determination on their site:
https://sam.gov/wage‐determination/AK20220007/0
10/18/2022
5 X
What is the scope of the "SPECIAL CLEARING AND GRUBBING" bid item.
No scope is defined and the quantity is the same as "CLEARING AND
GRUBBING".
Please refer to FP14, Section 202 ADDITIONAL CLEARING AND GRUBBING;
Subsections 202.02(C) and 202.06. Please bid accordingly.
10/19/2022
Are any cross sections available for the riprap guide banks so that we can quantify how much incidental excavation is associated with the riprap item. With excavations as deep as 15' from the original ground surface to bottom of riprap, this quantity will be very large.
The Government will not be providing cross sections for the riprap guide banks. Please bid according accordingly.