- AK DOT 135(6), Glenn Highway Rehabilitation Kings River Bridge Section: MP 66. 0 to 67. 2
- Solicitation number
- 69056719B000032
About this file
This document is an amendment to a solicitation for a construction project. The amendment revises the special contract requirements for Project AK DOT 135(6), Glenn Highway Rehabilitation, Kings River Bridge Section MP 66.0 to MP 67.2 by requiring the contractor to furnish a vehicle for the exclusive use of government personnel during the project period. The vehicle must be a recent model ton pickup truck or full-size SUV maintained in safe working condition with insurance as specified. The amendment also modifies the requirements for field offices and services during winter shutdown when facilities will be returned to the contractor. The solicitation was issued by the Federal Highway Administration with responses due as originally specified in Solicitation Number 69056719B000032 for the identified highway rehabilitation and bridge project.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A002 10/13/2022 N/A See Box 14
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X
69056719B000032
9B. DATED (SEE ITEM 11)
09/29/2022
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A
N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
(__ ) is extended, ( x ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D OTHER (Specify type of modification and authority)
N/A
E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
AK DOT 135(6), Glenn Highway Rehabilitation, Kings River Bridge Section MP 66.0 to MP 67.2
Amendment A002 is issued to revise the following:
SPECIAL CONTRACT REQUIREMENTS Page F-78, Subsection 637.02, General. Revises Subsection.
ENCLOSURES: Pages F-78
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N/A
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
F-78 DIVISION 600
Special Contract Requirements Project: AK DOT 135(6), Glenn Highway Rehabilitation, Kings River Bridge Section: MP 66.0 to MP 67.2
Section 637. — FACILITIES AND SERVICES
08/01/14–FP14
Description
637.01 Add the following:
This work also includes furnishing vehicles for the exclusive use of Government personnel.
Construction Requirements
637.02 General. Add the following to the first paragraph:
Facilities and services are not required during winter shutdown period, and will be returned to the Contractor’s possession during these periods. See Subsection 108.01(b).
637.03 Facilities. Amend as follows:
(a) Field Office. Delete the text of this Subsection and substitute with the following:
Furnish and maintain a field office within 5 miles of the project site according to Table 637-1.
(b) Residential Housing. Delete this Subsection and substitute the following:
(b) Vehicle. Provide a ½ ton, 4x4 wheel drive, two-door pickup truck or full-size body on frame, 4x4 wheel drive SUV, manufactured within 5-years of the Award date. Deliver the vehicles to project location.
Furnish vehicles with no visible Contractor’s company name or logo. Maintain the vehicle in such a manner to provide safety and reasonable comfort for the operator with all factory equipment in working order.
Provide all fuels, maintenance, and collision and comprehensive insurance. Insurance is for the Contractor’s protection. The Government will be responsible for all Government caused damage to the vehicle beyond normal wear and tear. The Government will not indemnify the Contractor for Government caused damage to third parties. Damage due to no fault of the Government will be the responsibility of the Contractor. Secure vehicle insurance according to the standards established by the state in which the vehicle is owned/operated.
Revised by Amendment A002