This document contains questions and answers regarding solicitation number 69056719B000032, an IFB for the AK DOT 135(6) Glenn Highway Rehabilitation, Kings River Bridge Section project from MP 66.0 to MP 67.2 issued by the Department of Transportation Federal Highway Administration.

The questions and answers provide clarification on the bid bond number requirement, the return of pickup vehicles to the contractor during winter shutdowns, the availability of cross section files corresponding to an earthwork data listing, the applicable Alaska Davis Bacon wage rates and wage determination number, and the scope of work for a special clearing and grubbing bid item. Bidders are directed to review amendments A001 and A002 for details on the bid bond number and vehicle return terms, and to refer to contract section 202 for additional information on clearing and grubbing.

View the file

Other files

File Type Posted
Bid Tabulation_AK DOT 135(6).pdf PDF
BidSum.pdf PDF
QA_11-07-2022.pdf PDF
Amendment A005.pdf PDF
QA_11-01-2022.pdf PDF
QA_10-28-2022.pdf PDF
QA2_10-27-2022.pdf PDF
QA_10-27-2022.pdf PDF
QA_10-26-2022.pdf PDF
Amendment A004.pdf PDF
Amendment A003.pdf PDF
QA_10-24-2022.pdf PDF
QA_10-21-2022.pdf PDF
QA_10-18-2022.pdf PDF
QA2_10-13-2022.pdf PDF
Amendment A002.pdf PDF
QA_10-13-2022.pdf PDF
Amendment A001.pdf PDF
QA_10-06-2022.pdf PDF
AK DOT 135(6) - Kings River Bridge - EXISTING BRIDGE AS_BUILTS.pdf PDF
ak-13506-Signoff-Plans.pdf PDF
ak-13506-Blue Top-RTB Report.pdf PDF
ak-13506-Red Top-XYZ Report.pdf PDF
Geotech Report No 08-19 Kings River Bridge Final Geotechnical Report.pdf PDF
AK DOT 135(6) - Kings River Bridge - EXISTING BRIDGE INSPECTION 2019.pdf PDF
ak-13506_Earthwork Report.pdf PDF
ak-13506-Signoff_ControlSheet.xlsx XLSX spreadsheet
Physical Data 1.zip ZIP file
ak-13506-Red Top-RTB Report.pdf PDF
ak-13506-Signoff-Superelvation.pdf PDF
ak-13506-Signoff_Alignments.pdf PDF
IFB 69056719B000032 .pdf PDF
ak-13506-Signoff_SWPPP_Binder.pdf PDF
FINAL_GR10-14_Glenn Highway Preliminary Geotechnical Recommendations Report.pdf PDF
Physical Data 2.zip ZIP file
ak-13506-Blue Top-XYZ Report.pdf PDF
ak-13506-Slope Stake Note-FHWA Version 2.pdf PDF
ak-13506-Slope Stake Note-XYZ Report.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AK DOT 135(6)

Glenn Highway Rehabilitation, Kings River Bridge Section MP 66.0 to MP 67.2

# General Technical Question Answer Date

1 X it appears the pre‐printed invitation number on the bid bond does match the solicitation number. Would you please confirm which solicitation number we should be using on our bid bond?

This will be addressed under Amendment A001. 10/6/2022

2 X Contractor is to provide 2 pickups for government’s use. Will these vehicles be returned to the contractor during the winter shut‐downs?

This will be addressed under Amendment A002. 10/13/2022

3 X Are cross sections that correspond to the “Earthwork Data Listing” available?

Yes. ak‐13506_Cross Section Labeled.pdf is a file listed under FAR Clause

52.236‐4. Obtain this file from the Physical Data 2.zip file on sam.gov.

10/13/2022

4 X

We are trying to determine Alaska Davis Bacon Wage Rates for the above referenced project. The link provided on SAM.gov for Davis‐Bacon

Act WD #: AK20220007 (applicable rates published on September 8, 2022) does not contain any wage rates.

Please provide the rates for the September 8, 2022 wage determination for Highway Construction.

SAM has updated the wage determination on their site:

https://sam.gov/wage‐determination/AK20220007/0

10/18/2022

5 X

What is the scope of the "SPECIAL CLEARING AND GRUBBING" bid item.

No scope is defined and the quantity is the same as "CLEARING AND

GRUBBING".

Please refer to FP14, Section 202 ADDITIONAL CLEARING AND GRUBBING;

Subsections 202.02(C) and 202.06. Please bid accordingly.