About this file

AG-03R6-S-15-0052 Amendment 0002 Q A's

View the file

Other files for this federal contract opportunity

Other files attached to Building 26, Phase 2 North Wing Renovation, newest first.
File Type Posted
S150052FinalAmendmen0003QAs.pdf PDF
102113_-_PHENOLIC-CORE_TOILET_COMPARTMENTS.pdf PDF
102800_-_TOILET_BATH_AND_LAUNDRY_ACCESSORIES.pdf PDF
093013_-_CERAMIC_TILING.pdf PDF
104413_-_FIRE_PROTECTION_CABINETS.pdf PDF
20150728Build26Phase2Sign-In.pdf PDF
123661_-_SIMULATED_STONE_COUNTERTOPS.pdf PDF
02_-_PROJECT_REPRESENTATIVES.pdf PDF
115213_-_PROJECTION_SCREENS.pdf PDF
S150052FinalAmendmen0001QAs.pdf PDF
064116_-_PLASTIC-LAMINATE-FACED_ARCHITECTURAL_CABINETS.pdf PDF
Wage_Rate_Decision_No.pdf PDF
Arch2-_A1.1.pdf PDF
Arch4-_D2.0_D7.2.pdf PDF
Arch1-_Cover_Sheet_Signed.pdf PDF
Arch6-_A2.0_A2.3.pdf PDF
Specifications_1_-_DIV00_DIV12.pdf PDF
Security-_Basement_1st_2nd.pdf PDF
Mech-_DM2.0_M9.8.pdf PDF
Structural2-_S2.0_S9.1.pdf PDF
Plumbing_-_DP2.0_P9.1.pdf PDF
20150707FinalAG03R6S150052Build26Phase2.pdf PDF
Civil2-_C9.1_C9.4.pdf PDF
Arch9_-_A7.0_A9.5.pdf PDF
Arch3-_A1.2.pdf PDF
Arch10_-_SP2.1_SP2.2.pdf PDF
Civil1-_C1.1_C3.2.pdf PDF
Arch8_-_A5.1_A6.10.pdf PDF
Elec1-_E0.1_E2.5.pdf PDF
DOLBuildingMT150064MslaCo.htm HTM file
Arch5-_D9.1.pdf PDF
Arch7_-_A3.1_A4.2.pdf PDF
FireSprinkler-_F0.1_F9.1.pdf PDF
Specifications2-_DIV21_DIV33.pdf PDF
Elec2_-_E7.0_E9.5.pdf PDF
Show all 35

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF

CONTRACT

1. CONTRACT ID CODE PAGE OF PAGES

1 7

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

0002 08/06/2015

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

USDA, Forest Service

Western Montana Acquisition Zone

24 Fort Missoula Road

Missoula, MT 59804

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.

Potential Offerors

AG-03R6-S-15-0052

9B. DATED (SEE ITEM 11)

07/09/15

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 01 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(X) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN

THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return * copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.

AG-03R6-S-15-0052, Amendment 0002, Building 26, Phase 2, North Wing Renovation

1. This amendment is to provide responses to that have been submitted on August 6, 2015. Any additional pending questions will be answered in another amendment. Please see the following pages for the questions and answers.

2. Response date for the RFP has NOT changed and RFP is still due on August 11, 2015 at 4:00 p.m. local time.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

N. JEAN WINDLE

Contracting Officer

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

30-105 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

Building 26 – Phase 2, North Wing Renovation, Fort Missoula, Missoula, MT

Amendment No. 0002, dated 08/06/15 Page 2 of 7

Building 26, Phase 2, North Wing Renovation

Solicitation Number AG-03R6-S-15-0052

Amendment 0002 – Questions and Answers Thursday, August 06, 2015

Q1.) The project “USAF Northern Region Building 26 Phase 2” has some sound masking in it spec. My company is a manufacturer of sound masking and I was wondering if you were entertaining any other manufacturers beside

Dynasound for the sound masking portion. If so I would love to have one of our local dealer put in a bid for this project. When you get a chance if you could let me know, or point me in the right direction that would be extremely helpful.

A1.) Dynasound will be the required product for the sound masking because of compatibility with those products installed elsewhere In the building during the past year.

Additional Clarification and Changes:

Sheet A2.2F: Clarification, Stair 221: "Sheet Carpet" indicated shall be installed to coordinate with existing conditions, and align with previous Phase 1 stair carpet runner. Provide finished rolled edge to exposed sheet carpet edge, and match Phase 1 installation in Stair 201. Repair wood stair within Stair 221, as necessary. Prime and paint exposed wood stair, tread, riser and stringers, refer to Finish Schedule A9.1.

Sheet A9.1:

-Plot 223, Files 225, change Flooring Finish to CPT-3.

-Clarification: Marmo-2 is NOT USED.

Sheet E2.0: Delete General Note 9.

Section 064800 Wood Frames:

-Delete 2.2 Interior Frames and Jambs for Transparent Finish.

-2.3, Interior Frames and Jambs for Opaque Finish, Add "D. Fire-Rated Interior Frames and Jambs: Products fabricated from fire-retardant particleboard or fire-retardant medium-density fiberboard with veneered exposed surfaces and listed and labeled by a testing and inspecting agency acceptable to authorities having jurisdiction, for fire ratings indicated, based on testing according to NFPA 252. Fire Rating: 60 minutes."

Section 102113 Solid Pheonlic Toilet Compartments:

- 2.2, A. shall read, "Bobrick, DuraLine, 1080 Series."

See following photos of attic space for visualization of that space, Refer to Asbestos Report for removal requirements and materail designation.

Amendment No. 0002, dated 08/06/15 Page 3 of 7

Amendment No. 0002, dated 08/06/15 Page 4 of 7

Amendment No. 0002, dated 08/06/15 Page 5 of 7

Amendment No. 0002, dated 08/06/15 Page 6 of 7

Amendment No. 0002, dated 08/06/15 Page 7 of 7