Wage_determination.pdf

PDF 289 KB Posted

Attached to
Co-Located Sitka Office Renovation Federal contract opportunity
Solicitation number
AG-0116-S-14-0021
Issued by
Department of Agriculture Forest Service R10-Alaska Region

About this file

Wage Determination

View the file

Other files for this federal contract opportunity

Other files attached to Co-Located Sitka Office Renovation, newest first.
File Type Posted
A09.pdf PDF
A08.pdf PDF
Sitka_Amendment_Drawings_Civil_A07.pdf PDF
Sitka_Amendment_Sign_Pages_A07.pdf PDF
A07.pdf PDF
A06.pdf PDF
A05.pdf PDF
Sig-in_sheet.pdf PDF
Pre-Proposal_Site-Visit_Agenda.pdf PDF
A04.pdf PDF
A03.pdf PDF
E1SitkaElecSitePlan-20140730_A02.pdf PDF
panel_a_woodshop_A02.pdf PDF
FlagPoleLight_A02.pdf PDF
237219FIXED_PLATE_AIR_A02.pdf PDF
260529_A02.pdf PDF
235216-BIOMASS_BOILER_A02.pdf PDF
A02.pdf PDF
236200-AIR_TO_WATER_HEAT_PUMPS_A02.pdf PDF
260548_A02.pdf PDF
221429_sf-SUMP_PUMPS_A02.pdf PDF
CreeAreaAREEDGDASpecSheet_A02.pdf PDF
M-P-Drawingreplacement-20140730_A02.pdf PDF
panel_b_autoshop_A02.pdf PDF
211000_SF-Fire-Suppression_Systems_A02.pdf PDF
A01.pdf PDF
Factor_3_form.pdf PDF
lpta_questionnaire.pdf PDF
SitkaOfficeSiteDev_ACM_LBP_reports.pdf PDF
Factor_1_form.pdf PDF
D60441FINAL_sitka_geotech.pdf PDF
Factor_2_form.pdf PDF
070914_Drawings.pdf PDF
SITKA_solicitation.pdf PDF
ColocatedSitkaOfficeSiteDev7_8_14.pdf PDF
Sitka_Specifications.pdf PDF
Technical_Criteria_Pre-Notice.pdf PDF
LPTA_Factor_1_form.pdf PDF
lpta_questionnaire.pdf PDF
LPTA_Factor_3_form.pdf PDF
LPTA_Factor_2_form.pdf PDF
DRAFTColocatedSitkaOfficeSiteDev6-14-14.pdf PDF
DRAFT_Sitka_CD_Drawings.pdf PDF
Show all 43

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 3 –Wage Determination Co-located Sitka Office Renovation

REFERENCE NO. OF DOCUMENT BEING ATTACHED

AG-0116-S-14-0021

PAGE

OF

General Decision Number: AK140001 04/25/2014 AK1

Superseded General Decision Number: AK20130001

State: Alaska

Construction Types: Building and Heavy

Counties: Alaska Statewide.

BUILDING AND HEAVY CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and apartments up to and including 4 stories)

Modification Number Publication Date

0 01/03/2014

1 01/17/2014

2 02/07/2014

3 02/21/2014

4 03/07/2014

5 04/11/2014

6 04/18/2014

7 04/25/2014

ASBE0097-001 09/02/2013

Rates Fringes

Asbestos Workers/Insulator

(includes application of all insulating materials protective coverings, coatings and finishings to all types of mechanical systems).........................$ 34.88 18.67

ASBE0097-002 09/02/2013

HAZARDOUS MATERIAL HANDLER

(includes preparation, wetting, stripping, removal scrapping, vacuming, bagging, and disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems).........$ 34.88 18.67

BOIL0502-002 01/01/2013

Rates Fringes

BOILERMAKER......................$ 42.97 26.60

REFERENCE NO. OF DOCUMENT BEING ATTACHED

AG-0116-S-14-0021

PAGE

BRAK0001-002 07/01/2013

Bricklayer, Blocklayer, Stonemason, Marble Mason, Tile Setter, Terrazzo Worker.....$ 39.03 18.86

Tile & Terrazzo Finisher.........$ 33.27 18.86

CARP1501-001 09/01/2013

MILLWRIGHT.......................$ 34.99 20.54

CARP2520-003 09/01/2013

Diver

Stand-by....................$ 40.90 22.59

Tender......................$ 39.90 22.59

Working.....................$ 80.70 22.59

Piledriver

Carpenter...................$ 36.59 22.59

Piledriver; Skiff Operator and Rigger..................$ 36.59 22.59

Sheet Stabber...............$ 36.59 22.59

Welder......................$ 42.15 22.59

DEPTH PAY PREMIUM FOR DIVERS BELOW WATER SURFACE:

50-100 feet $1.00 per foot

101 feet and deeper $2.00 per foot

ENCLOSURE PAY PREMIUM WITH NO VERTICAL ASCENT:

5-50 FEET $1.00 PER FOOT/DAY

51-100 FEET $2.00 PER FOOT/DAY

101 FEET AND ABOVE $3.00 PER FOOT/DAY

SATURATION DIVING:

The standby rate applies until saturation starts. The saturation diving rate applies when divers are under pressure continuously until work task and decompression are complete. the diver rate shall be paid for all saturation hours.

WORK IN COMBINATION OF CLASSIFICATIONS:

Employees working in any combination of classifications within the diving crew (except dive supervisor) in a shift are paid in the classification with the highest rate for that shift.

REFERENCE NO. OF DOCUMENT BEING ATTACHED

AG-0116-S-14-0021

PAGE

CARP4059-001 09/01/2013

CARPENTER

Carpenter...................$ 36.59 22.59

Lather/Drywall Applicator...$ 36.59 22.59

* ELEC1547-004 04/01/2014

CABLE SPLICER....................$ 39.82 3%+$23.56

Electrician;Technician...........$ 38.79 3%+$23.81

ELEC1547-005 04/01/2014

Line Construction

CABLE SPLICER....................$ 51.52 3%+27.73

Linemen (Including Equipment

Operators, Technician)...........$ 49.77 3%+27.73

Powderman........................$ 47.77 3%+27.73

TREE TRIMMER.....................$ 35.34 3%+$20.01

ELEV0019-002 01/01/2014

ELEVATOR MECHANIC................$ 50.42 26.785+a+b

FOOTNOTE: a. Employer contributes 8% of the basic hourly rate for over 5 year's service and 6% of the basic hourly rate for 6 months to 5 years' of service as vacation paid credit. b. Eight paid holidays:

New Year's Day; Memorial Day; Independence Day;

Labor Day; Veteran's Day; Thanksgiving Day; Friday after

Thanksgiving and Christmas Day

REFERENCE NO. OF DOCUMENT BEING ATTACHED

AG-0116-S-14-0021

PAGE

ENGI0302-002 01/01/2014

Power equipment operators:

GROUP 1.....................$ 39.28 20.35

GROUP 1A....................$ 41.04 20.35

GROUP 2.....................$ 38.51 20.35

GROUP 3.....................$ 37.79 20.35

GROUP 4.....................$ 31.58 20.35

TUNNEL WORK

GROUP 1....................$ 43.21 20.35

GROUP 1A...................$ 45.14 20.35

GROUP 2....................$ 42.36 20.35

GROUP 3....................$ 41.57 20.35

GROUP 4....................$ 34.74 20.35

POWER EQUIPMENT OPERATOR CLASSIFICATIONS

GROUP 1: Asphalt Roller: Breakdown, Intermediate, and

Finish; Back Filler; Barrier Machine (Zipper); Beltcrete with power pack and similar conveyors; Bending Machine;

Boat Coxwains; Bulldozers; Cableways, Highlines and

Cablecars; Cleaning Machine; Coating Machine; Concrete

Hydro Blaster; Cranes-45 tons and under or 150 foot boom and under (including jib and attachments): (a) Hydralifts or Transporters, all track or truck type,(b) Derricks;

Crushers; Deck Winches-Double Drum; Ditching or Trenching

Machine (16 inch or over); Drilling Machines, core, cable, rotary and exploration; Finishing Machine Operator, Concrete Paving, Laser Screed, Sidewalk, Curb and Gutter

Machine; Helicopters; Hover Craft, Flex Craft, Loadmaster, Air Cushion, All Terrain Vehicle, Rollagon, Bargecable, Nodwell, and Snow Cat; Hydro Ax: Feller Buncher and similar; Loaders (2 1/2 yards through 5 yards, including all attachments): Forklifts with telescopic boom and swing attachment, Overhead and front end, 2 1/2 yards through 5 yards, Loaders with forks or pipe clamps; Loaders, elevating belt type, Euclid and similar types; Mechanics, Bodyman; Micro Tunneling Machine; Mixers: Mobile type w/hoist combination; Motor Patrol Grader; Mucking Machines:

Mole, Tunnel Drill, Horizontal/Directional Drill Operator, and/or Shield; Operator on Dredges; Piledriver Engineers, L. B. Foster, Puller or similar Paving Breaker; Power

Plant, Turbine Operator, 200 k.w. and over (power plants or combination of power units over 300 k.w.); Scrapers-through

40 yards; Service Oiler/Service Engineer; Sidebooms-under

45 tons; Shot Blast Machine; Shovels, Backhoes, Excavators with all attachments, and Gradealls (3 yards and under), Spreaders, Blaw Knox, Cedarapids, Barber Greene, Slurry

Machine; Sub-grader (Gurries, Reclaimer, and similar types); Tack tractor; Truck mounted Concrete Pumps, Conveyor, Creter; Water Kote Machine; Unlicensed off road hauler

GROUP 1A: Camera/Tool/Video Operator (Slipline), REFERENCE NO. OF DOCUMENT BEING ATTACHED

AG-0116-S-14-0021

PAGE

Cranes-over 45 tons or 150 foot (including jib and attachments): (a) Clamshells and Draglines (over 3 yards),

(b) Tower cranes; Licensed Water/Waste Water Treatment

Operator; Loaders over 5 yds.; Certified Welder, Electrical

Mechanic, Camp Maintenance Engineer, Mechanic (over 10,000 hours); Motor Patrol Grader, Dozer, Grade Tractor, Roto-mill/Profiler (finish: when finishing to final grade and/or to hubs, or for asphalt); Power Plants: 1000 k.w.

and over; Quad; Screed; Shovels, Backhoes, Excavators with all attachments (over 3 yards), Sidebooms over 45 tons;

Slip Form Paver, C.M.I. and similar types; Scrapers over 40 yards;

GROUP 2: Boiler-fireman; Cement Hog and Concrete Pump

Operator; Conveyors (except as listed in group 1); Hoist on steel erection; Towermobiles and Air Tuggers;

Horizontal/Directional Drill Locator;Licensed Grade

Technician; Loaders, (i.e., Elevating Grader and Material

Transfer Vehicle); Locomotives: rod and geared engines;

Mixers; Screening, Washing Plant; Sideboom (cradling rock drill regardless of size); Skidder; Trencing Machine under

16 inches; Waste/ Waste Water Treatment Operator.

GROUP 3: "A" Frame Trucks, Deck Winches: single power drum;

Bombardier (tack or tow rig); Boring Machine; Brooms-power;

Bump Cutter; Compressor; Farm tractor; Forklift, industrial type; Gin Truck or Winch Truck with poles when used for hoisting; Grade Checker and Stake Hopper; Hoist, Air

Tuggers, Elevators; Loaders: (a) Elevating-Athey, Barber

Green and similar types (b) Forklifts or Lumber Carrier

(on construction job site) (c) Forklifts with Tower (d)

Overhead and Front-end, under 2 1/2 yds. Locomotives:Dinkey

(air, steam, gas and electric) Speeders; Mechanics (light duty); Oil, Blower Distribution; Post Hole Diggers, mechanical; Pot Fireman (power agitated); Power Plant, Turbine Operator, under 200 k.w.; Pumps-water; Roller-other than Plantmix; Saws, concrete; Skid Steer with all attachments; Straightening Machine; Tow Tractor

GROUP 4: Rig Oiler/Crane Assistant Engineer;Parts and

Equipment Coordinator; Swamper (on trenching machines or shovel type equipment); Spotter; Steam Cleaner; Drill

Helper.

FOOTNOTE: Groups 1-4 receive 10% premium while performing tunnel or underground work. Rig Oiler/Crane Assistant

Engineer shall be required on cranes over 85 tons or over

100 feet of boom.

REFERENCE NO. OF DOCUMENT BEING ATTACHED

AG-0116-S-14-0021

PAGE

IRON0751-003 08/01/2013

Ironworkers:

BRIDGE, STRUCTURAL,

ORNAMENTAL, REINFORCING

MACHINERY MOVER, RIGGER,

SHEETER, STAGE RIGGER,

BENDER OPERATOR.............$ 33.55 25.53

FENCE, BARRIER AND

GUARDRAIL INSTALLERS........$ 30.05 25.53

GUARDRAIL LAYOUT MAN........$ 30.79 25.53

HELICOPTER, TOWER...........$ 34.55 25.53

LABO0341-005 07/01/2013

Laborers: South of the 63rd

Parallel & West of Longitude

138 Degrees

GROUP 1.....................$ 29.25 22.32

GROUP 2.....................$ 30.25 22.32

GROUP 3.....................$ 31.15 22.32

GROUP 3A....................$ 34.43 22.32

GROUP 3B....................$ 35.26 22.32

GROUP 4.....................$ 18.82 22.32

TUNNELS, SHAFTS, AND RAISES

GROUP 1....................$ 32.18 22.32

GROUP 2....................$ 33.28 22.32

GROUP 3....................$ 34.27 22.32

GROUP 3A...................$ 37.87 22.32

GROUP 3B...................$ 38.79 22.32

LABORERS CLASSIFICATIONS

GROUP 1: Asphalt Workers (shovelman, plant crew); Brush

Cutters; Camp Maintenance Laborer; Carpenter Tenders; Choke

Setters, Hook Tender, Rigger, Signalman; Concrete

Laborer(curb and gutter, chute handler, grouting, curing, screeding); Crusher Plant Laborer; Demolition Laborer;

Ditch Diggers; Dump Man; Environmental Laborer (asbestos

(limited to nonmechanical systems), hazardous and toxic waste, oil spill); Fence Installer; Fire Watch Laborer;

Flagman; Form Strippers; General Laborer; Guardrail

Laborer, Bridge Rail Installers; Hydro-Seeder Nozzleman;

Laborers (building); Landscape or Planter; Laying of

Decorative Block (retaining walls, flowered decorative block 4 feet and below); Material Handlers; Pneumatic or

Power Tools; Portable or Chemical Toilet Serviceman; Pump

Man or Mixer Man; Railroad Track Laborer; Sandblast, Pot

Tender; Saw Tenders; Scaffold Building and Erecting; Slurry

Work; Stake Hopper; Steam Point or Water Jet Operator;

Steam Cleaner Operator; Tank Cleaning; Utiliwalk, Utilidor

Laborer and Conduit Installer; Watchman (construction projects); Window Cleaner

REFERENCE NO. OF DOCUMENT BEING ATTACHED

AG-0116-S-14-0021

PAGE

GROUP 2: Burning and Cutting Torch; Cement or Lime Dumper or

Handler (sack or bulk); Choker Splicer; Chucktender (wagon, airtrack and hydraulic drills); Concrete Laborers (power buggy, concrete saws, pumpcrete nozzleman, vibratorman);

Culvert Pipe Laborer; Cured in place Pipelayer;

Environmental Laborer (marine work, oil spill skimmer operator, small boat operator); Foam Gun or Foam Machine

Operator; Green Cutter (dam work); Gunnite Operator; Hod

Carriers; Jackhammer or Pavement Breakers (more than 45 pounds);Laying of Decorative Block (retaining walls, flowered decorative block above 4 feet); Mason Tender and

Mud Mixer (sewer work); Pilot Car; Plasterer, Bricklayer and Cement Finisher Tenders; Power Saw Operator; Railroad

Switch Layout Laborer; Sandblaster; Sewer Caulkers; Sewer

Plant Maintenance Man; Thermal Plastic Applicator; Timber

Faller, chain saw operator, filer; Timberman

GROUP 3: Alarm Installer; Bit Grinder; Guardrail Machine

Operator; High Rigger and tree topper; High Scaler;

Multiplate; Slurry Seal Squeegee Man

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill

Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

GROUP 4: Final Building Cleanup

TUNNELS, SHAFTS, AND RAISES CLASSIFICATIONS

GROUP 1: Brakeman; Muckers; Nippers; Topman and Bull Gang;

Tunnel Track Laborer

GROUP 2: Burning and Cutting Torch; Concrete Laborers;

Jackhammers; Nozzleman, Pumpcrete or Shotcrete.

GROUP 3: Miner; Retimberman to, wagon drills, air track drills; hydraulic drills);

type drills); Pipelayers.

Tunnel shaft and raise rates only apply to workers regularly employed inside a tunnel portal or shaft collar.

REFERENCE NO. OF DOCUMENT BEING ATTACHED

AG-0116-S-14-0021

PAGE

LABO0942-001 07/01/2013

Laborers: North of the 63rd

Parallel & East of Longitude

138 Degrees

GROUP 1.....................$ 29.25 22.32

GROUP 2.....................$ 30.25 22.32

GROUP 3.....................$ 31.15 22.32

GROUP 3A....................$ 34.43 22.32

GROUP 3B....................$ 35.26 22.32

GROUP 4.....................$ 18.82 22.32

TUNNELS, SHAFTS, AND RAISES

GROUP 1....................$ 32.18 22.32

GROUP 2....................$ 33.28 22.32

GROUP 3....................$ 34.27 22.32

GROUP 3A...................$ 37.87 22.32

GROUP 3B...................$ 38.79 22.32

LABORERS CLASSIFICATIONS

GROUP 1: Asphalt Workers (shovelman, plant crew); Brush

Cutters; Camp Maintenance Laborer; Carpenter Tenders; Choke

Setters, Hook Tender, Rigger, Signalman; Concrete

Laborer(curb and gutter, chute handler, grouting, curing, screeding); Crusher Plant Laborer; Demolition Laborer;

Ditch Diggers; Dump Man; Environmental Laborer (asbestos

(limited to nonmechanical systems), hazardous and toxic waste, oil spill); Fence Installer; Fire Watch Laborer;

Flagman; Form Strippers; General Laborer; Guardrail

Laborer, Bridge Rail Installers; Hydro-Seeder Nozzleman;

Laborers (building); Landscape or Planter; Laying of

Decorative Block (retaining walls, flowered decorative block 4 feet and below); Material Handlers; Pneumatic or

Power Tools; Portable or Chemical Toilet Serviceman; Pump

Man or Mixer Man; Railroad Track Laborer; Sandblast, Pot

Tender; Saw Tenders; Scaffold Building and Erecting; Slurry

Work; Stake Hopper; Steam Point or Water Jet Operator;

Steam Cleaner Operator; Tank Cleaning; Utiliwalk, Utilidor

Laborer and Conduit Installer; Watchman (construction projects); Window Cleaner

GROUP 2: Burning and Cutting Torch; Cement or Lime Dumper or

Handler (sack or bulk); Choker Splicer; Chucktender (wagon, airtrack and hydraulic drills); Concrete Laborers (power buggy, concrete saws, pumpcrete nozzleman, vibratorman);

Culvert Pipe Laborer; Cured in place Pipelayer;

Environmental Laborer (marine work, oil spill skimmer operator, small boat operator); Foam Gun or Foam Machine

Operator; Green Cutter (dam work); Gunnite Operator; Hod

Carriers; Jackhammer or Pavement Breakers (more than 45 pounds);Laying of Decorative Block (retaining walls, flowered decorative block above 4 feet); Mason Tender and

Mud Mixer (sewer work); Pilot Car; Plasterer, Bricklayer and Cement Finisher Tenders; Power Saw Operator; Railroad

REFERENCE NO. OF DOCUMENT BEING ATTACHED

AG-0116-S-14-0021

PAGE

Switch Layout Laborer; Sandblaster; Sewer Caulkers; Sewer

Plant Maintenance Man; Thermal Plastic Applicator; Timber

Faller, chain saw operator, filer; Timberman

GROUP 3: Alarm Installer; Bit Grinder; Guardrail Machine

Operator; High Rigger and tree topper; High Scaler;

Multiplate; Slurry Seal Squeegee Man to, wagon drills, air track drills; hydraulic drills);

type drills); Pipelayers

GROUP 4: Final Building Cleanup

TUNNELS, SHAFTS, AND RAISES CLASSIFICATIONS

GROUP 1: Brakeman; Muckers; Nippers; Topman and Bull Gang;

Tunnel Track Laborer

GROUP 2: Burning and Cutting Torch; Concrete Laborers;

Jackhammers; Nozzleman, Pumpcrete or Shotcrete.

GROUP 3: Miner; Retimberman to, wagon drills, air track drills; hydraulic drills);

type drills); Pipelayers.

Tunnel shaft and raise rates only apply to workers regularly employed inside a tunnel portal or shaft collar.

REFERENCE NO. OF DOCUMENT BEING ATTACHED

AG-0116-S-14-0021

PAGE

PAIN1959-001 04/01/2014

NORTH OF THE 63RD PARALLEL

PAINTER

BRUSH/ROLLER PAINT OR WALL

COVERER.....................$ 31.10 19.48

TAPING, TEXTURING,

STRUCTURAL PAINTING,

SANDBLASTING, POT TENDER,

FINISH METAL, SPRAY,

BUFFER OPERATOR, RADON

MITIGATION, LEAD BASED

PAINT ABATEMENT, HAZARDOUS

MATERIAL HANDLER............$ 31.62 19.48

PAIN1959-002 04/01/2014

SOUTH OF THE 63RD PARALLEL

Painters:

Brush, Roller, Sign, Paper and Vinyl, Swing Stage, Hand Taper/Drywall, Structural Steel, and

Commercial Spray............$ 29.34 19.23

Machine Taper/Drywall.......$ 30.59 19.23

Spray-Sand/Blast, Epoxy and Tar Applicator..........$ 30.69 19.23

PAIN1959-003 01/01/2014

NORTH OF THE 63RD PARALLEL

GLAZIER..........................$ 36.51 19.31

PAIN1959-004 07/01/2012

FLOOR LAYER: Carpet.............$ 30.09 13.02

PAIN1959-006 01/01/2014

SOUTH OF THE 63RD PARALLEL

GLAZIER..........................$ 36.51 18.59

REFERENCE NO. OF DOCUMENT BEING ATTACHED

AG-0116-S-14-0021

PAGE

PLAS0867-001 02/01/2014

PLASTERER

North of the 63rd parallel..$ 35.94 19.89

South of the 63rd parallel..$ 35.69 19.89

PLAS0867-004 02/01/2014

CEMENT MASON/CONCRETE FINISHER

North of the 63rd parallel..$ 35.69 19.89

South of the 63rd parallel..$ 35.44 19.89

PLUM0262-002 07/01/2013

East of the 141st Meridian

Plumber; Steamfitter.............$ 36.02 25.62

PLUM0367-002 07/01/2013

South of the 63rd Parallel

Plumber; Steamfitter.............$ 38.46 20.74

PLUM0375-002 07/01/2013

North of the 63rd Parallel

Plumber; Steamfitter.............$ 39.96 20.85

PLUM0669-002 07/01/2013

SPRINKLER FITTER.................$ 42.05 21.67

SHEE0023-003 07/01/2013

South of the 63rd Parallel

Sheet Metal Worker...............$ 39.99 20.58

REFERENCE NO. OF DOCUMENT BEING ATTACHED

AG-0116-S-14-0021

PAGE

SHEE0023-004 07/01/2013

North of the 63rd Parallel

Sheet Metal Worker...............$ 44.93 19.79

TEAM0959-003 09/01/2013

TRUCK DRIVER

GROUP 1.....................$ 38.89 18.57

GROUP 1A....................$ 40.16 18.57

GROUP 2.....................$ 37.63 18.57

GROUP 3.....................$ 36.81 18.57

GROUP 4.....................$ 36.23 18.57

GROUP 5.....................$ 35.47 18.57

GROUP 1: Semi with Double Box Mixer; Dump Trucks (including rockbuggy and trucks with pups) over 40 yards up to and including 60 yards; Deltas, Commanders, Rollogans and similar equipment when pulling sleds, trailers or similar equipment; Boat Coxswain; Lowboys including attached trailers and jeeps, up to and including 12 axles; Ready-mix over 12 yards up to and including 15 yards); Water Wagon

(250 Bbls and above); Tireman, Heavy Duty/Fueler

GROUP 1A: Dump Trucks (including Rockbuggy and Trucks with pups) over 60 yards up to and including 100 yards; Jeeps

(driver under load)

GROUP 2: Turn-O-Wagon or DW-10 not self-loading; All Deltas, Commanders, Rollogans, and similar equipment; Mechanics;

Dump Trucks (including Rockbuggy and Trucks with pups) over

20 yards up to and including 40 yards; Lowboys including attached trailers and jeeps up to and including 8 axles;

Super vac truck/cacasco truck/heat stress truck; Ready-mix over 7 yards up to and including 12 yards; Partsman;

Stringing Truck

GROUP 3: Dump Trucks (including Rockbuggy and Trucks with pups) over 10 yards up to and including 20 yards; batch trucks 8 yards and up; Oil distributor drivers; Oil

Distributor Drivers; Trucks/Jeeps (push or pull); Traffic

Control Technician

GROUP 4: Buggymobile; Semi or Truck and trailer; Dumpster;

Tireman (light duty); Dump Trucks (including Rockbuggy and

Truck with pups) up to and including 10 yards; Track Truck

Equipment; Grease Truck; Flat Beds, dual rear axle; Hyster

Operators (handling bulk aggregate); Lumber Carrier; Water

Wagon, semi; Water Truck, dual axle; Gin Pole Truck, Winch

Truck, Wrecker, Truck Mounted "A" Frame manufactured rating over 5 tons; Bull Lifts and Fork Lifts with Power Boom and

REFERENCE NO. OF DOCUMENT BEING ATTACHED

AG-0116-S-14-0021

PAGE

Swing attachments, over 5 tons; Front End Loader with

Forks; Bus Operator over 30 passengers; All Terrain

Vehicles; Boom Truck/Knuckle Truck over 5 tons; Foam

Distributor Truck/dual axle; Hydro-seeders, dual axle;

Vacuum Trucks, Truck Vacuum Sweepers; Loadmaster (air and water); Air Cushion or similar type vehicle; Fire

Truck/Ambulance Driver; Combination Truck-fuel and grease;

Compactor (when pulled by rubber tired equipment); Rigger

(air/water/oilfield); Ready Mix, up to and including 7 yards;

GROUP 5: Gravel Spreader Box Operator on Truck; Flat Beds, single rear axle; Boom Truck/Knuckle Truck up to and including 5 tons; Pickups (Pilot Cars and all light duty vehicles); Water Wagon (Below 250 Bbls); Gin Pole Truck, Winch Truck, Wrecker, Truck Mounted "A" Frame, manufactured rating 5 tons and under; Bull Lifts and Fork Lifts (fork lifts with power broom and swing attachments up to and including 5 tons); Buffer Truck; Tack Truck; Farm type

Rubber Tired Tractor (when material handling or pulling wagons on a construction project); Foam Distributor, single axle; Hydro-Seeders, single axle; Team Drivers (horses, mules and similar equipment); Fuel Handler (station/bulk attendant); Batch Truck, up to and including 7 yards;

Gear/Supply Truck; Bus Operator, Up to 30 Passengers;

Rigger/Swamper

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is union or non-union.

Union Identifiers

An identifier enclosed in dotted lines beginning with characters other than "SU" denotes that the union

REFERENCE NO. OF DOCUMENT BEING ATTACHED

AG-0116-S-14-0021

PAGE

classification and rate have found to be prevailing for that classification. Example: PLUM0198-005 07/01/2011. The first four letters , PLUM, indicate the international union and the four-digit number, 0198, that follows indicates the local union number or district council number where applicable , i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination.

The date, 07/01/2011, following these characters is the effective date of the most current negotiated rate/collective bargaining agreement which would be July 1, 2011 in the above example.

Union prevailing wage rates will be updated to reflect any changes in the collective bargaining agreements governing the rates.

0000/9999: weighted union wage rates will be published annually each January.

Non-Union Identifiers

Classifications listed under an "SU" identifier were derived from survey data by computing average rates and are not union rates; however, the data used in computing these rates may include both union and non-union data. Example: SULA2004-007

5/13/2010. SU indicates the rates are not union majority rates, LA indicates the State of Louisiana; 2004 is the year of the survey; and 007 is an internal number used in producing the wage determination. A 1993 or later date, 5/13/2010, indicates the classifications and rates under that identifier were issued as a General Wage Determination on that date.

Survey wage rates will remain in effect and will not change until a new survey is conducted.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour

Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the

Davis-Bacon survey program. If the response from this initial

REFERENCE NO. OF DOCUMENT BEING ATTACHED

AG-0116-S-14-0021

PAGE

contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the

Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations

Wage and Hour Division

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator

(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator

U.S. Department of Labor

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative

Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

U.S. Department of Labor

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

REFERENCE NO. OF DOCUMENT BEING ATTACHED

AG-0116-S-14-0021

PAGE

RESERVED

File details come from the government source that posted it. Updated .