This document is a set of specifications for a federal construction contract to complete short term improvements at the Phantom Ranch Wastewater Treatment Plant located in Grand Canyon National Park, Arizona. The work includes installing a new influent screen, replacing equipment such as mixers, retrofitting tanks with new technologies, modifying blowers and digesters, upgrading controls and instrumentation, and related civil, structural, mechanical, and electrical elements. Subcontractors must be approved, and prevailing wage requirements apply. The contractor must maintain continuous plant operations, requiring coordination of shutdowns and submittal of maintenance plans. Specified interim completion dates and final completion dates apply. The contractor is responsible for obtaining necessary permits and complying with environmental, health and safety requirements.

View the file

Other files for this federal contract opportunity

Other files attached to GRCA - 229035 Phantom Ranch Wastewater Treatment P, newest first.
File Type Posted
Sol_140P2021R0127_Amd_0006.pdf PDF
Amendment_6_Sched_of_Changes_0006.pdf PDF
Amendment_5_Sched_of_Changes_0005.pdf PDF
E15_Deliverables_LmtOnSubconRpt_REQD_0005.pdf PDF
Sol_140P2021R0127_Amd_0005.pdf PDF
WA614890_-_PRELIM_DESIGN_0004.pdf PDF
Sol_140P2021R0127_Amd_0004.pdf PDF
Amendment_4_Sched_of_Changes_0004.docx DOCX document
140P2021R0127_0004.pdf PDF
PR_WWTP_229035_Photo_Graphic_Part_3_0004.pptx PPTX presentation
PR_WWTP_229035_Photo_Graphic_Part_2_0004.pptx PPTX presentation
PR_WWTP_229035_Photo_Graphic_Part_1_0004.pptx PPTX presentation
Headworks_As-builts_C7_showing_DEMO_0004.pdf PDF
TCWL_Geotechnical_Baseline_0004.pdf PDF
PR_WWTP_ACD_GRCA_113_41073_D_0004.pdf PDF
GCNPS_Phantom_Ranch_WWTP_test_report_0004.pdf PDF
Asbestos_Survey_-_Phantom_Ranch_WWTP_0004.pdf PDF
Sol_140P2021R0127_Amd_0003.pdf PDF
Amendment_3_SF30_with_changes_to_L_M_0003.pdf PDF
GRCA_PreProposal_Presentation_Final8_3_0003.pdf PDF
Amendment_3_Sched_of_Changes_0003.pdf PDF
Vol1_Specifications_Final_Construction_Documents_May_2021_0002.pdf PDF
Vol2_Drawings_Final_Construction_Documents_June_2021_0002.pdf PDF
Sol_140P2021R0127_Amd_0002.pdf PDF
Question_and_Answers_0001.pdf PDF
Sol_140P2021R0127_Amd_0001.pdf PDF
A06_NPS_Phantom_Ranch_Vol3_Details_Final_Construction_Documents_0001.pdf PDF
A04_NPS_Phantom_Ranch_Vol2_Drawings_100__Complete_CD.pdf PDF
SF2416d.pdf PDF
B08_Solit_ConstructionClauseTemplate_REQD.pdf PDF
Proposal_Submission_Package.pdf PDF
WDOL.pdf PDF
Sol_140P2021R0127.pdf PDF
Show all 33

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

100% Complete Construction Documents

Volume 1 Specifications

March 2021

Prepared for the

National Park Service

Phantom Ranch Wastewater Treatment Plant

Short Term Improvements

100% Complete Construction Documents

Volume 1 Specifications

March 2021

Prepared for the

National Park Service

Phantom Ranch Wastewater Treatment Plant

Short Term Improvements

PPS0323210011CVO

NATIONAL PARK SERVICE

GRAND CANYON NATIONAL PARK

BIDDING REQUIREMENTS

AND

CONTRACT DOCUMENTS

for the construction of the

PHANTOM RANCH WASTEWATER TREATMENT PLANT

SHORT TERM IMPROVEMENTS

Contract No. GRCA-229632

100 Percent Complete Construction Documents

SPECIFICATIONS

CH2M

Phoenix, Arizona

March 2021

Project No. D3167624 Copy No.

GRCA - 229632 00 01 10 - 1

MARCH 2021 TABLE OF CONTENTS

TABLE OF CONTENTS

Pages

VOLUME 1

SPECIFICATIONS

DIVISION 01—GENERAL REQUIREMENTS

01 11 00 Summary of Work .................................................................... 1- 5 01 26 01 Contract Modification Procedures ........................................... 1- 6 01 27 00 Definition of Contract Line Items ............................................ 1- 1 01 31 00 Project Management and Coordination ................................... 1- 16 01 32 16 Construction Schedule ............................................................. 1- 10 01 32 33 Photo Documentation for Historic Preservation Projects ........ 1- 2 01 33 23 Submittal Procedures ............................................................... 1- 9 Supplement:

Submittal List ........................................................................... 1- 10 01 35 13.22 Archeological Protection ......................................................... 1- 3 01 35 23 Safety Requirements ................................................................ 1- 4 01 35 91 Historic Preservation Treatment Procedures ........................... 1- 7 01 40 00 Quality Requirements .............................................................. 1- 9 Supplements:

Fabricator’s Certificate of Compliance .................................... 1- 1 Statement of Structural Tests and Special Inspections ............ 1- 8 01 42 00 Reference Standards................................................................. 1- 11 01 43 00 Manufacturers’ Field Services ................................................. 1- 4 Supplement:

Manufacturer’s Certificate of Proper Installation .................... 1- 1 01 50 00 Temporary Facilities and Controls ........................................... 1- 8 01 57 19.11 Indoor Air Quality Management .............................................. 1- 6 01 57 19.12 Noise & Acoustics Management ............................................. 1- 2 01 57 23 Temporary Storm Water Pollution Prevention ........................ 1- 9 01 67 00 Product Requirements .............................................................. 1- 10 01 73 29 Cutting and Patching ................................................................ 1- 4 01 73 40 Execution ................................................................................. 1- 8 01 74 19 Construction Waste Management and Disposal ...................... 1- 9 Supplements:

Appendix A: Project Waste Management Plan Worksheet ..... 1- 1 Appendix B: Standard Solid Waste Conversions .................... 1- 6 01 77 00 Closeout Procedures................................................................. 1- 5 Supplement:

Closeout and Operation & Maintenance Requirements........... 1- 2 01 78 23 Operation and Maintenance Data ............................................. 1- 9 01 79 00 Demonstration and Training .................................................... 1- 4 01 81 13 Sustainable Design Requirements for Non LEEDTM Projects . 1- 4

Pages

GRCA - 229632 00 01 10 - 2

01 88 15 Anchorage and Bracing ............................................................ 1- 6 01 91 14 Equipment Testing and Facility Startup .................................. 1- 6 Supplements:

Unit Process Startup Form ....................................................... 1- 1 Facility Performance Demonstration/Certification Form ........ 1- 1

DIVISION 02—EXISTING CONDITIONS

02 41 00 Demolition ............................................................................... 1- 4

DIVISION 03—CONCRETE

03 30 10 Structural Reinforced Concrete ................................................ 1- 23 Supplements:

Concrete Mix Design, Class 5000F3S1P2C2 .......................... 1- 2 Concrete Mix Design, Class 4500F1S1P0C1 .......................... 1- 2 03 62 00 Grouting ................................................................................... 1- 9 Supplement:

24-hour Evaluation of Nonshrink Grout Test Forms and Grout Testing Procedures ..................................................... 1- 3

DIVISION 04—NOT USED

DIVISION 05—METALS

05 05 19 Post-Installed Anchors ............................................................. 1- 7 05 50 00 Metal Fabrications ................................................................... 1- 11 05 53 00 Metal Gratings ......................................................................... 1- 5

DIVISIONS 06 THROUGH 08—NOT USED

DIVISION 09—FINISHES

09 90 00 Painting and Coating ................................................................ 1- 19 Supplements:

Paint System Data Sheet (PSDS) ............................................. 1- 1 Paint Product Data Sheet (PPDS) ............................................ 1- 1 09 96 35 Chemical-Resistant Coatings ................................................... 1- 9 Supplements:

Chemical-Resistant Coating Data Sheet (CRCDS) ................. 1- 1 Chemical-Resistant Coating Product Data Sheet (CRCPDS) .. 1- 1

DIVISIONS 10 THROUGH 25—NOT USED

GRCA - 229632 00 01 10 - 3

DIVISION 26—ELECTRICAL

26 05 02 Basic Electrical Requirements ................................................. 1- 6 26 05 04 Basic Electrical Materials and Methods .................................. 1- 12 26 05 05 Conductors ............................................................................... 1- 9 26 05 26 Grounding and Bonding for Electrical Systems ...................... 1- 4 26 05 33 Raceway and Boxes ................................................................. 1- 18 26 05 70 Electrical Systems Analysis ..................................................... 1- 7 Supplement:

Figure 1: Example Arc Flash Label ......................................... 1- 1 26 08 00 Commissioning of Electrical Systems ..................................... 1- 14 26 20 00 Low-Voltage AC Induction Motors ......................................... 1- 4 26 24 16 Panelboards .............................................................................. 1- 6 26 24 19 Low-Voltage Motor Control .................................................... 1- 7 26 27 26 Wiring Devices ........................................................................ 1- 7 26 29 23 Low-Voltage Adjustable Frequency Drive System ................. 1- 9

DIVISIONS 27 THROUGH 30—NOT USED

DIVISION 31—EARTHWORK

31 10 00 Site Clearing............................................................................. 1- 2 31 23 16 Excavation................................................................................ 1- 3 31 23 23 Fill and Backfill ....................................................................... 1- 5 31 23 23.15 Trench Backfill ........................................................................ 1- 9

DIVISION 32—NOT USED

DIVISION 33—UTILITIES

33 05 01 Conveyance Piping—General .................................................. 1- 7 33 05 01.12.03 Polyvinyl Chloride (PVC)—Gravity Sanitary Sewer Data Sheet ............................................................................. 1- 1 33 05 13 Manholes .................................................................................. 1- 9

DIVISIONS 34 THROUGH 39—NOT USED

DIVISION 40—PROCESS INTERCONNECTIONS

40 05 15 Piping Support Systems ........................................................... 1- 10 Supplements:

Table 1: Nonchemical Areas .................................................... 1- 1 Table 2: Chemical Areas .......................................................... 1- 1 40 05 33 Pipe Heat Tracing .................................................................... 1- 5 40 27 00 Process Piping—General ......................................................... 1- 17 Supplement:

Piping Schedule ....................................................................... 1- 1

GRCA - 229632 00 01 10 - 4

40 27 00.07 Galvanized Steel Pipe and Malleable Iron Fittings Data Sheet ............................................................................. 1- 3 40 27 00.08 Stainless Steel Pipe and Fittings—General Service Data Sheet ............................................................................. 1- 2 40 27 00.10 Polyvinyl Chloride (PVC) Pipe and Fittings Data Sheet ......... 1- 2 40 27 01 Process Piping Specialties........................................................ 1- 9 40 27 02 Process Valves and Operators .................................................. 1- 8 Supplement:

Self-Regulated Valve Schedule ............................................... 1- 1 40 80 01 Process Piping Leakage Testing .............................................. 1- 6 40 90 01 Instrumentation and Control for Process Systems ................... 1- 19 Supplements:

Component Specifications ....................................................... 1- 10 Instrument List ......................................................................... 1- 1 Control Descriptions ................................................................ 1- 5 PLC Input/Output List ............................................................. 1- 8 Preparation for Testing and Functional Test Forms ................ 1- 4 Performance Acceptance Test Sheet ........................................ 1- 2

DIVISIONS 41 AND 42—NOT USED

DIVISION 43—PROCESS GAS AND LIQUID HANDLING, PURIFICATION,

AND STORAGE EQUIPMENT

43 22 56.01 Submersible Mixers ................................................................. 1- 4

DIVISION 44—POLLUTION AND WASTE CONTROL EQUIPMENT

44 42 56.04 Submersible Pump ................................................................... 1- 5 Supplement:

Screen Washwater Pump Data Sheet ....................................... 1- 2 44 42 56.10 Horizontal End Suction Centrifugal Pumps ............................. 1- 5 Supplements:

Filter Feed Pump 1 and 2 Data Sheet....................................... 1- 2 Filter Effluent Pump Data Sheet .............................................. 1- 2 Final Effluent Pump Data Sheet .............................................. 1- 2 44 42 56.16 Peristaltic Hose Pump .............................................................. 1- 5 Supplement:

Peristaltic Hose Pump Data Sheet ............................................ 1- 3 44 43 15 Automatic Backwash Filter Equipment ................................... 1- 6 44 44 57 Tube Settler System ................................................................. 1- 8 44 45 16.01 Coarse Bubble Air Diffuser System ........................................ 1- 10 44 53 16 Screw Screen ............................................................................ 1- 9

GRCA - 229632 00 01 10 - 5

DIVISION 45—NOT USED

DIVISION 46—WATER AND WASTEWATER EQUIPMENT

46 53 36 Integrated Fixed-Film Activated Sludge Equipment ............... 1- 7

DIVISIONS 47 THROUGH 49—NOT USED

VOLUME 2

DRAWINGS

END OF SECTION

SPECIFICATIONS

GRCA - 229632 01 11 00 - 1

091015 SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work phases.

3. Work under other contracts.

4. Government Furnished Materials.

5. Contractor use of premises.

6. Public use of site.

7. Occupancy requirements for buildings.

8. Work Restrictions.

9. Special Construction Requirements.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location:

1. Grand Canyon National Park

Phantom Ranch Wastewater Treatment Plant Grand Canyon, Arizona

2. The Phantom Ranch Wastewater Treatment Plant is located at the base of the Grand Canyon, near the confluence of Bright Angel Creek with the Colorado River. The plant serves Phantom Ranch, which provides campgrounds, dormitories and cabins for hikers and mule riders. The hike to Phantom Ranch is approximately 7.5 miles down the South Kaibab Trail or 10 miles on the Bright Angel Trail.

B. The Work consists of the following:

1. The Work includes interim improvements to the Phantom Ranch Wastewater Treatment Plant, which supports all visitor and support services for Phantom Ranch and Bright Angel Campground. The plant is rated for a maximum month wastewater flow of 7,000 gallons per day and a maximum day of 12,000 gallons per day. The completed Work will provide improvements for enhanced performance and include the following:

a. New influent screen. Construction of a new influent screen with integral washer and compacter and headworks structure. Backwash pump will convey water from the Effluent Storage (Chlorine Contact) Tank.

b. Equalization tank mixer replacement. Construction of a new submersible mixer in the existing equalization tank.

c. Aeration tank retrofit with integrated fixed film activated sludge (IFAS) technology.

Retrofit of the existing aeration tank with an IFAS technology for carbon, nitrogen and solids removal.

d. Blower modifications. Construction of new adjustable frequency drives for the three existing blowers and ancillary piping and valves.

GRCA - 229632 01 11 00 - 2

e. Final clarifier tube settler replacement. Retrofit of the existing final clarifier with new tuber settlers for enhanced settling performance.

f. Tertiary filter replacement. Construction of a new tertiary filter with chemical addition and automatic backwashing to replace the existing, retired filter.

g. Digester modifications. Construction of coarse bubble diffusers to provide mixing and process air for digestion.

h. Instrumentation and control and main control panel upgrades.

i. Electrical upgrades.

j. Demolition.

k. Temporary facilities and controls.

C. Continuous operation of the Phantom Ranch Wastewater Treatment Plant is of critical importance.

Schedule and conduct activities to enable existing facilities to operate continuously, unless otherwise specified. Contractor shall perform work as required to maintain compliance with the facility Aquifer Protection Permit and facility operating requirements.

D. Project will be constructed under a single prime contract.

1.3 WORK UNDER OTHER CONTRACTS

A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.

B. Concurrent Work: Government will award separate contract(s) for the following construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract.

1. Phantom Ranch Wastewater Treatment Plant Effluent Disposal Improvements: A separate contract will be awarded for construction of a new percolation basin to discharge treated effluent from the WWTP.

2. Grand Canyon National Park SCADA System Upgrade: A separate contract will be awarded for the configuration and programming of a new SCADA system at the Grand Canyon National Park sites. This contractor will be responsible for programming, field testing and commissioning services for the SCADA system for the Phantom Ranch Wastewater Treatment Plant Short Term Improvements.

C. Future Work: Government will award separate contract(s) for the following additional work to be performed at site after Final Completion. Completion of that work will depend on successful completion of preparatory work under this Contract.

1. Phantom Ranch Water and Wastewater Treatment Plants: Separate contracts will be awarded for construction of a new Water Treatment Plant and a new Wastewater Treatment Plant on the Delta, adjacent to the existing Phantom Ranch Wastewater Treatment Plant.

GRCA - 229632 01 11 00 - 3

1.4 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to the WWTP building and as noted on the drawings.

2. Limit site disturbance, including earthwork and clearing of vegetation, to 40 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter; 15 feet beyond primary roadway curbs and main utility branch trenches; and 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.

B. Storage of Materials: Confine storage of materials to areas located on the Drawings.

C. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with

Contracting Officer and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

E. Construction Camp: Establishment of a camp will be permitted in Phantom Ranch Village. Provide utilities as specified in Division 1 Section “Temporary Facilities and Controls”. Keep camp neat and clean and return site to previous condition at completion of work. These requirements also apply to all Contractors’ employees who may, with prior approval, establish their own camping facilities.

F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

GRCA - 229632 01 11 00 - 4

1.5 PUBLIC USE OF SITE

A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.

Building closures will be permitted, when required, upon specific approval of Contracting Officer for a maximum of 8 hours.

1.6 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.

b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.

1.7 CONDUCT OF OPERATIONS

A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.8 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during working hours of 6:00 a.m. to 6:00 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend Hours: 8:00 am to 5:00 pm.

2. Early Morning or Night Hours: Upon approval only.

3. Hours for outdoor activities: 8:00 am to 5:00 pm.

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

GRCA - 229632 01 11 00 - 5

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than ten days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. Hours for Utility Shutdowns: Between 12 pm and 4 am for 4 hours.

D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.

1.9 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.

1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.

1.10 SOILS INVESTIGATION REPORT

A. A soils investigation was not conducted for this project.

B. It is the responsibility of the Contractor to assess the conditions during the mandatory site visit.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

GRCA - 229632 01 26 01 - 1

031414 CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager, Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

GRCA - 229632 01 26 01 - 2

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Trash removal, dumpsters

5. Barricades

6. Small tools

7. Safety supplies

8. Scaffolding

9. Daily cleaning

10. Traffic control

11. Temporary signage

12. Temporary power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:

1) Social Security

2) Medicare

3) Workers Compensation– Policy and company calculation to be made available.

4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.

5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.

6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

GRCA - 229632 01 26 01 - 3

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.

Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction

GRCA - 229632 01 26 01 - 4

Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.

Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.

Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

GRCA - 229632 01 26 01 - 5

4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.

Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10% Profit……………………10%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

GRCA - 229632 01 26 01 - 6

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 012601

GRCA - 229632 01 27 00 - 1

082714 DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item No. 0001 Phantom Ranch WWTP Short Term Improvements.

1. This item consists of all components necessary to demolish, prepare, install, operate and maintain the new equipment at the WWTP, including a new influent screen, equalization tank mixer, integrated fixed film activated sludge (IFAS) system, blower modifications, final clarifier tube settlers, automatic backwash filter, digester coarse bubble diffusers, main control panel upgrades, ancillary equipment, instrumentation and electrical gear. The work includes civil, structural, mechanical, instrumentation and control and electrical elements.

2. Measurement for payment will be in accordance for the Schedule of Values.

3. Payment will be made at the contract lump sum price in accordance with the percentage of work completed.

END OF SECTION 01 27 00

GRCA - 229632 01 31 00 - 1

091015 PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on

Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination.

3. Submittals

4. Coordination Drawings.

5. Requests for Information (RFIs).

6. NPS/DSC SharePoint Project Website.

7. Project meetings.

8. Environmental Coordination.

9. Permits

10. Reference Points and Surveys

B. Related Requirements:

1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.

4. Section 01 91 14 “Equipment Testing and Facility Startup” for coordinating the work with

Contracting Officer’s Commissioning Authority.

1.2 DEFINITIONS

A. Agency with Jurisdiction

B. Construction Permits – Contractor Provided

C. Government Furnished Permits

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the

Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

GRCA - 229632 01 31 00 - 2

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Permit requirements.

7. Pre-installation conferences.

8. Project closeout activities.

9. Commissioning activities.

1.4 SUBMITTALS

A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.

1. Content: Project-specific information, drawn accurately to scale. Do not base

Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the Contracting Officer (CO) for resolution of such conflicts.

c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

GRCA - 229632 01 31 00 - 3

d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.

e. Indicate required installation sequences.

2. Sheet Size: At least 8-1/2 by 11 inches but no larger than 22 by 34 inches.

3. Number of Copies: Submit two opaque copies of each submittal. Contracting Officer will return one copy.

4. Refer to individual Sections for Coordination Drawing requirements for Work in those

Section

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.

2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.

3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.

4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.

5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.

6. Mechanical and Plumbing Work: Show the following:

a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.

b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.

7. Electrical Work: Show the following:

a. Runs of vertical and horizontal conduit 1-inch in diameter and larger.

b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.

c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.

d. Location of pull boxes and junction boxes, dimensioned from column center lines.

8. Review: Contracting Officer (CO) will review coordination drawings to confirm that the

Work is being coordinated, but not for the details of the coordination, which are

Contractor's responsibility. If CO determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, CO will so inform

Contractor, who shall make changes as directed and resubmit.

C. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:

1. File Preparation Format: AutoCad.dwg, Version 2020, operating in Microsoft Windows operating system.

GRCA - 229632 01 31 00 - 4

2. File Submittal Format: Submit or post coordination drawing files using Portable Document

Format (PDF) file format.

3. Contracting Officer (CO) will furnish Contractor one set of digital data files

(AutoCad.dwg) of Drawings for use in preparing coordination digital data files.

a. CO makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings.

b. Digital Data Software Program: Drawings are available in AutoCad.dwg.

D. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention Plan.

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the

Contactor and all subcontractors.

8. Waste Management Plan.

9. Quality Control Plan.

10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP).

11. Indoor Air Quality (IAQ) Management Plan.

12. Contractors Commissioning Plan.

13. Historic Preservation Treatment Plan.

14. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit.

b. The Agency(ies) with Jurisdiction issuing the permit.

c. Information required from the Government to complete the permit application.

E. All items listed must be provided to the Contracting Officer before the Pre-Construction

Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the

Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.

1. CO will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

GRCA - 229632 01 31 00 - 5

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

8. Contractor's signature.

9. Requested date for response.

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:

1. Enter the general information at the top of the form.

2. Under the “Action” section at the bottom of the form, select “Question” then select “CMR” in the drop-down of the “Send to” box.

3. Enter the details of the question and attach related documents.

4. Select “Submit Form” at the bottom of the page.

D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond.

CO will determine the critical nature of each RFI and issue a response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. CO's action on RFIs may result in the need for a change to the Contract Time or the

Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

1.6 PROJECT WEB SITE

A. Use the NPS/DSC SharePoint Project website for communication throughout the contract period.

The NPS/DSC SharePoint Project website will be used for the following functions:

1. Project directory.

2. Project correspondence.

GRCA - 229632 01 31 00 - 6

3. Meeting agendas and minutes.

4. Contract modifications forms and logs.

5. RFI form and processing.

6. Task and issue management.

7. Photo documentation.

8. Baseline schedule, schedule updates and calendar management.

9. Submittal form and processing.

10. Payment coordination documentation.

11. Drawing and specification document hosting, viewing, and updating.

12. Online document collaboration.

13. Reminder and tracking functions.

14. Archiving functions.

15. Notification of submittal and RFI statuses and current responsible party.

16. Permits and addendums

B. Some documents however are not…